Professional Documents
Culture Documents
Setting out Site Layout as shown including Site Office, Guard House, Hoarding and etc. Setting up Bentonite Plant for the construction of Diaphragm Wall. Complete Ultimate Pile Load Test and GMP trial test as per specification. Proceed with Diaphragm Wall Construction,
2.
I .C. I .C. I .C.
S E R A N G O O N
R O A D
Sequence at Month 4
CITY SQUARE MALL
BOUNDARY LINE
GATE GATE 1 1
TURFING
3.
BARE EARTH SURFACE TO BE COVERED WITH CANVASS SHEET IF THERE IS NO ON-GOING ACTIVITY
4.
S IL T WATE R HOLD ING T ANK FROM M ONTH -9 T O MONT H - 22 I L =101.668 S TORA GE T ANK FOR T RE AT ED WATER
I L =102.384
Hydraulic Grab
1.
Diaphragm wall construction is completed and GMP works in progress. Proceed with Bore Piling Works follow by King Post Installation. Proceed with excavation along the diaphragm wall for capping beam casting.
Crawler Crane
2.
Truck Excavator
I.C.
I.C.
I.C.
Boundary Line Boundary Line Hoarding Line Hoarding Line Building Outline Building Outline T.O.L. T.O.L. Slab Opening at B1Opening Slab Storey at B1 Storey
Sequence at Month 7
CITY SQUARE MALL
BOUNDARY LINE
GATE GATE 1 1
TURFING
GMP Machine
3.
Crawler Crane
Truck Excavator
GMP Machine
Crawler Crane
S ILT WA TE TA N K FR R HOLD IN G OM MONT H -9 TO MON TH -22 IL=10 1.668 S TORA GE TAN K FOR TREA TED WA TER
IL=10 2.384
S ILT TRAP 1 m X 1m X
1 m(D)
Construction Sequence Section 1 1. Complete construction of capping beams on top of the diaphragm wall. Complete Bore Piling Works and king-post installation. Proceed with construction of Level 1 Slab.
2.
I.C. I.C. I.C.
Boundary Line Boundary Line Hoarding Line Hoarding Line Building Outline Building Outline T.O.L. T.O.L. Slab Opening at B1Opening Slab Storey at B1 Storey
Sequence at Month 10
CITY SQUARE MALL
BOUNDARY LINE
GATE 1
TURFING
Crawler Crane
3.
Mixer Truck
S ILT WA TE TA N K FR R HOLD IN G OM MONT H -9 TO MON TH -22 IL=10 1.668 S TORA GE TAN K FOR TREA TED WA TER
IL=10 2.384
S ILT TRAP 1 m X 1m X
1 m(D)
Construction Sequence Section 1 1. Complete construction of permanent RC slab [which serves as concrete strut to diaphragm wall and working platform during excavation and construction of Basements] at Level-1 with access openings.
I .C.
I .C.
I .C.
Crawler Crane
BOUNDARY LINE
LEVEL 3
CITY
GATE GATE 1 1
TURFING
2.
3.
Crawler Crane
Truck
Mixer Truck
S IL T WATE R HOLD ING T ANK FROM M ONTH -9 T O MONT H - 22 I L =101.668 S TORA GE T T RE AT ED ANK FOR WATER
I L =102.384
LEVEL 1
Boundary Line Boundary Line Hoarding Line Hoarding Line Building Outline Building Outline T.O.L. T.O.L. Slab Opening at B1Opening Slab Storey at B1 Storey
LEVEL B1
Sequence at Month 13
SQUARE MALL
Complete construction of RC slab at Basement 1. Proceed with the construction of RC slab at Basement 2.
BOUNDARY LINE
CITY
GATE GATE 1 1
TURFING
Crawler Crane
S ILT WA TE R HOLD IN G TA N K FR OM MONT TO MON H -9 TH -22 IL=10 1.668 S TORA GE TREA TED TAN K FOR WA TER
IL=10 2.384
S ILT TRAP 1 m X 1m X
1 m(D)
LEVEL 3
LEVEL 1
Boundary Line Boundary Line Hoarding Line Hoarding Line Building Outline Building Outline T.O.L. T.O.L. Slab Opening at B1Opening Slab Storey at B1 Storey
LEVEL B1
Sequence at Month 16
SQUARE MALL
Erect two Tower Cranes on Level-1 Slab. Construction of level-4 slab in progress & proceed with the excavation and construction of RC slab at Basement 3 concurrently.
BOUNDARY LINE
LEVEL 4
CITY
GATE 1
TURFING
TUR FING
G SE EN T
Tower Crane
Crawler Tower
S ILT WA TE TA N K FR R HOLD IN G OM MONT H -9 TO MON TH -22 IL=10 1.668 S TORA GE TAN K FOR TREA TED WA TER
IL=10 2.384
S ILT TRAP 1 m X 1m X
1 m(D)
LEVEL 3
Boundary Line Boundary Line Hoarding Line Hoarding Line Building Outline Building Outline T.O.L. T.O.L. Slab Opening at B1Opening Slab Storey at B1 Storey
LEVEL 1
LEVEL B1
Sequence at Month 18
SQUARE MALL
Construction of Podium structure until Lev-6 is in progress. Construction of Basement 4 slab in progress. Proceed with truss installation works in Podium.
3.
BOUNDARY LINE
CITY
GATE 1
Section 2 1.
Boring Rig
Complete demolition of existing MRT exit/ entrance. Proceed with the Bore Pile Installation
2.
Crawler Tower
LEVEL 7
LEVEL 6
LEVEL 5
LEVEL 4
LEVEL 3
Boundary Line Boundary Line Hoarding Line Hoarding Line Building Outline Building Outline T.O.L. T.O.L. Slab Opening at B1Opening Slab Storey at B1 Storey
LEVEL 1
LEVEL B1
Sequence at Month 20
SQUARE MALL
Complete Construct Basement Slabs until Basement-4 Proceed with the construction of Upper Tower Structure and Level-2 slab. Proceed with Basement Internal Finishing. Dismantle one no. Tower Crane
2.
Tower Crane
I .C.
I .C.
I .C.
BOUNDARY LINE
CITY
GATE 1
3.
Excavator
4.
Section 2
Excavator Truck
1.
S IL T WATE R HOLD ING T ANK FROM M ONTH T O MONT -9 H - 22 I L =101 .668 S TORA GE T ANK FOR
I L =102 .384
ROOF
LEVEL 9
LEVEL 8
LEVEL 7
LEVEL 6
LEVEL 5
LEVEL 4
LEVEL 3
LEVEL 1
Boundary Line Boundary Line Hoarding Line Hoarding Line Building Outline Building Outline T.O.L. T.O.L. Slab Opening at B1Opening Slab Storey at B1 Storey
LEVEL B1
Sequence at Month 22
SQUARE MALL
Complete Construct of the Tower Structure Complete Metal Roof Truss Curtain wall installation works in Podium in progress.
2. 3.
I .C.
I .C.
I .C.
BOUNDARY LINE
CITY
GATE 1
S IL T WATE R HOLD ING T ANK FROM M ONTH T O MONT -9 H - 22 I L =101.668 S TORA GE T T RE AT ED ANK FOR WATER
I L =102.384
ROOF
LEVEL 9
LEVEL 8
LEVEL 7
LEVEL 6
LEVEL 5
LEVEL 4
LEVEL 3
LEVEL 2
LEVEL 1
Boundary Line Boundary Line Hoarding Line Hoarding Line Building Outline Building Outline T.O.L. T.O.L. Slab Opening at B1Opening Slab Storey at B1 Storey
LEVEL B1
Sequence at Month 24
SQUARE MALL
Curtain wall works in podium is completed and Curtain Wall works in Tower is in progress. Dismantle Tower Crane. Proceed with the Internal Finishing for the Tower
2.
I.C. I.C. I.C.
BOUNDARY LINE
CITY
GATE 1
3.
Section 2 1. Complete RC structure of the Sunken Plaza and proceed with the installation of Sail Roof Proceed with the Installation of Escalator and Finishing Works
2.
S ILT WA TE R HOLD IN G TA N K FR OM MONT TO MON H -9 TH -22 IL=10 1.668 S TORA GE TAN K FOR TREA TED WA TER
IL=10 2.384
S ILT TRAP 1 m X 1m X
ROOF
1 m(D)
LEVEL 9
LEVEL 8
LEVEL 7
LEVEL 6
LEVEL 5
LEVEL 4
LEVEL 3
LEVEL 2
Boundary Line Boundary Line Hoarding Line Hoarding Line Building Outline Building Outline T.O.L. T.O.L. Slab Opening at B1Opening Slab Storey at B1 Storey
LEVEL 1
LEVEL B1
Sequence at Month 31
SQUARE MALL
Flat Roof
1. 2.
Complete Internal Finishing for the New Retail Outlet Complete External Works surround the New Retail Outlet
Roof Garden at 7th floor Roof at 6th floor Roof at 6th floor
Section 2
Flat Roof
1.
Complete the External Works & Water Feature surround the Front Phase of the New Retail Outlet
Boundary Line Boundary Line Hoarding Line Hoarding Line Building Outline Building Outline T.O.L. T.O.L. Slab Opening at B1Opening Slab Storey at B1 Storey
Sequence at Month 34
CITY SQUARE MALL