RUHLING MANUFACTURING COMPANY

Sourcing Dilemma

YOGESH KUMAR(190) HARSH SINGH(191) SMIT RAKESH(194) VIJAYA KRUSHNA(215)

Introduction
Cyrus Ruhling founded the Ruhling Manufacturing Company in 1901 Until 1915, the firm made electric motors After World War I, Cyrus decided to cater to the small but growing home appliance industry Today, Ruhling is one of the nations largest appliance manufacturers Ruhling has a small capacity installed internally for contingency.

Background
Company issued an invitation for bids for 11/32-horsepower motors for a six-month period at an estimated price of $29 per unit. Quantity estimated for six month period is 48000. Ordering Frequency : Daily Lead Time : Maximum one Week Company follows dual sourcing policy on some places three suppliers may be in contract.

Bids Received
Able Electric Beta Products Gamma Manufacturing Delta Electric Epsilon Products $30.00 $28.00 $32.00 $29.25 $30.00

Epsilon Proposal
Proposed Price : $23.75 Flexible ordering period Lead time: 3 days(guaranteed) Would keep inventroy required for one month at its disposal. Would increase capacity if warranted Conditions :
Contract period : one year Shall source the entire requirements

The Questions
Should Epsilon's alternative be considered? Comment on the practice of dual sourcing when part of the requirement is produced internally. Relate this practice to the advantage and disadvantage of a 100 % requirement contract?

Options to consider
Continue with dual sourcing policy by accepting bids from Beta Electric ($28.00) and Delta Electric ($29.25). Single sourcing from the Epsilon ($23.75) and keep its own plant as a contingency source. This option will lead to 17.03 % over other.

Should Epsilons alternative proposal be considered?


Taking the cost into consideration we should go for single sourcing , provided there is no risk of continuity in supply. Only considering the proposal of Epsilon is neither ethically correct nor it can give us competitive advantage. Advantages:
Flexible ordering period Lead time: 3 days(guaranteed) Would keep inventory required for one month at its disposal. Would increase capacity if warranted

Disadvantages:
Risk of meeting Contingency requirements Lack of alternatives Risk of running out of inventory

100% contracting Vs. Dual sourcing


100% requirements contract
Better cost advantage Risk of continuity of supply

Dual sourcing:
To ensure the continuity of availability To mitigate the risks In these two strategies, there is a trade off between risk and cost.

Recommendation
Ruhling should move to single sourcing model. As it can mitigate the risks by using its internal capacity. It should negotiate with all the bidding companies to get the best price and contract terms. It will reduce the cost of material (in case Epsilon by 17.03 %) as compared to dual sourcing model.