Professional Documents
Culture Documents
Managing specific metallic alloy in a cyclical market is a challenge for aerospace industry. When demand for new aeroplanes fluctuates, glut and shortages of raw materials may occur. Suppliers think of exit from the industry. Boeing has faced raw material shortages which resulted in expediting costs to increase and in worst cases shutdown. This problem has been studied and CPFR is being used. It should generate planned demand for components and raw materials throughout supply chain. It should help mills producing raw materials plan their capacity and dampen oscillations throughout S.C.
Introduction
Study involves metallic alloy which constitutes 40% of world demand. Figures 18.1 and 18.2 show the demand for aeroplane, price and alloy price & production. Fluctuation in demand for alloy causes fluctuation in production capacity. Companies are forced to adjust to Fluctuation. Boeing had to stop production for 20 days as cos could not supply components. Prices increased, LT also increased by factor of 8. Study indicated that oscillations were caused by delays in the system. Delay include order processing, delivery, production, capacity adjustment. Reduce delays but use of IT.
Figure 18.1 : The cyclical nature of the commercial airplane market, from all airplane manufacturers, causes fluctuation in the demand, production and price of aerospace metal. Source: Roskill Information Services (1998)
Figure 18.2 : The increase in demand for raw material, hence shipment, creates a dramatic increase in lead-time (baseline 1993).
RM SPW
SPW FST
Fastener Suppliers
CB
SAM
FST SAB
A/C Model
MILL
CB
RM PM
Processing House
PM
SAB CB PM CM
Machine Shops
Figure 18.4 : The lag that occurs from raw material production to airplane delivery is due to the production and delivery delay within the supply chain network in which most of the entities adopt the make-to-order policy.
Figure 18.10 : Simulated result of lead-time for various entities within the supply chain. The simulation is for the case in which the process house and mill wait to adjust production capacity.
Manufacturing dynamics for process hours and machine shops are shown in figure. Carrying inventory is costly for mills and hence they produce rods, bars & billets. Orders are batched to minimize set up cost. Dynamic modeling; system dynamics that operates in a jobshop environment is used.
The dynamics in a cell for a manufacturing facility that operates in a jobshop environment
Cell
Beginning Inventory
Process
Beginning Inventory
Forging
Machining
Assembly
Billet Conversion
Hammer
Interaction among the entities in the current environment. Only demand from the immediate downstream entity is passed along.
Mill Forging House Machine Shop Issue PO To Mill Issue PO To Mill Issue PO To Mill Forge Parts Machine Parts An Assembly House
Issue PO Forging House
Final Assembly
Delivery Schedule
Issue internal PO
assemble
Model
Demand Fulfillment Backlog Cancellation b tj u tj u j Release to Production rjt p tj Completion Rate Filling From Stock C
t j
Demand
ju j Parts On hand Receiving q tj Ordering from suppliers wtj Parts on Order v tj tj Canceling order Parts Consumption
Mathematical expression
t +1 j
= b +c f u e
t j t j t j t j
t j
t +1 j
= p +u u u
t j t j t j
t T j j
= w +q v
t j t j t j
t j
u t T j rjt +1 = t u j u t T j f jt = 0 u t T j rjt +1 = t u j
MTO MTS
Each mode in the supply chain performs demand fulfillment & parts replenishment funcitons. MTO, MTS production policies can use this
Model Consists
Final assembly facilities that produce unique aroplane models; these facilities also produce subassemblies and components. Subassembly manufacturers from whom the equipment manufacturer purchases the buy subassemblies. Component manufacturers from whom the subassembly and the original equipment manufacturers purchase the buy component for subassemblies. Process houses that manufacturer processed raw materials for making components. Fastener manufacturers that produce fasteners for assembly. Speciality wires for fasteners. Mills that provide ingots and billets.
Forecast
MRP
MRP Component Purchase Component manufacturing POU Raw Material Sub-Assembly Purchase Sub-Assembly manufacturing POU Raw Components
MPS
Final Assembly
PM
Processed material Speciality wire Fastener Components for Boeing Component manufacturer Subassemblies produced for Boeing Major subassemblies
SPW FST CB
CM SAB SAM
800% increase in lead time from the mill caused by approximate 100% increase in OEM production. Simulations carried out & observed behaviour is shown in figure 18.10 Figure 18.11 gives simulated response of lead time dynamics when mills and process houses are 80%. responsive
600% 500
10 20 30 40 50 60 When the mill adjusts its production capacity as a response to a doubling in demand, the mill 100 70 80 90 Time Unit experiences a low percentage increase in its lead time.
Sourcing policies determine the selection of specific suppliers to provide certain parts. Transportation policies determine the time, method and route of transportation. End-item demand drives the downstream requirements in the supply chain. To completely describe S.C. network, software requires data on initial inventory levels, cost, price, weight etc. Data composed of 200 suppliers, 40 material types, tons of thousands of parts & assemblies and ten years of record. This enabled researcher to observe the behaviour of SC when changes are made.
In Practicum
Figure 18.1 is an output from the simulation model. It can be seen in the figure that processing shops experience ups and downs of the delivery of planes. Figure 18.13 shows the result of inventory policies for suppliers of Tiers 1 through 5. Shortage or surpluses are observed. Purchasing ordering habits of Boeings Global Supply Base are studied. Due to long lead time nature of industry under study, the supply base must place its orders far into the future. Boeing should anticipate problems rather than react to problems, the serious perturbations in the supply chain can be mitigated.
Figure 18.11 : When the mill adjusts its production capacity as a response to a doubling in demand, the mill experiences a low percentage increase in its lead-time
Figure 18.12 : Raw material shipped to Processing House XYZ and Machine Shop ABC.
Figure 18.13 : Inventory policies using various safety stocks levels for Tiers 1 through 5 in the supply chain.