You are on page 1of 35

Guided By:

By: By:-

(2nd Sem MBA PM)

Mr. K.K. Morya


Prof., UPES

Mr. K.R. Barwa


G.M.- RRVUN
Tuesday, June 28, 2011

Mohit Nebhwani (38), 38), Mohit Tyagi(39), Tyagi(39), Sudhanshu Gupta(68), Gupta(68), Umanshu (74), 74), COMET GROUP Varun Goel (82) 82)

Process of electricity distribution


loss 3-4%
Loss Upto 30%

Say generation Cost per unit= X

Cost per unit = Y where Y = X+ T.C.

Cost per unit=Z Where Z= X+Y+D.C.

Transmission Losses AT&C Losses

3-4% upto 30%

Power cost increases by 35-50% from generation ex-bus to consumer meter 35exTuesday, June 28, 2011 COMET GROUP 2

Generation Tariff
Tariff can be defined as the cost per unit of service. There are two types of tariffs Single Part Tariff Two Part Tariff

The single part tariff is considered more suitable for wind power. Two part tariff is applied to the Thermal Power Plants.

Tuesday, June 28, 2011

COMET GROUP

Two Part Tariff


Components of Two Part Tariff 1. Capacity Charges/Fixed Charges/Annual Fixed Cost 2. Energy Charge/ Variable Charges

Generation Tariff= Capacity Charges + Energy Charges

Tuesday, June 28, 2011

COMET GROUP

Components of Capacity Charges


1.

Return on equity Interest on loan capital Depreciation Operation and maintenance expenses Interest on working capital. Cost of secondary fuel(for coal based & lignite fired generating stations only) Special allowance in lieu of R&M or separate compensation allowance, wherever applicable.
COMET GROUP 5

2.

3.

4.

5.

6.

7.

Tuesday, June 28, 2011

Comparative Analysis of CERC Regulations


Component of Capacity Charges Return on Equity Regulations -2009-14 Regulation-2004-09

15.5%

14%

Interest on Loan Capital

As per Actual

As per Actual

Depreciation

5.28%

3.6% + AAD

Interest on Working Capital

Based on Normative Parameters Based on Normative Parameters


COMET GROUP

Based on Normative Parameters Based on Normative Parameters


6

Operations & Maintenance Costs


Tuesday, June 28, 2011

1.Return on Equity
Component of Capacity Charges Return on Equity Regulation-2009-14 Regulation-2004-09

15.5%

14%

Additional Return

0.5% (For projects N/A st of April commissioned after 1 2009 with in specified timeline) 17.48% 15.78%

Return on Equity if MAT is applicable

Return on Equity if Corporate Tax is applicable

23.481%

21.20%

Tuesday, June 28, 2011

COMET GROUP

2.Interest on Loan Capital


Component of Capacity Charges Benefit of Re-Financing Regulation-2009-14 Regulation-2004-09

In ratio 2:1 i.e. 2/3rd to beneficiary and 1/3rd to generator. Weighted average on outstanding normative loan

100% benefit goes to the beneficiary.

Rate of Interest

Weighted average on outstanding normative loan

Normative Loan

Repayment shall be deemed to be equal to the depreciation allowed for the year.

As per Regulatory approval 70% > Actual loan amount

Tuesday, June 28, 2011

COMET GROUP

3. Depreciation
Component of Capacity Charges Regulation-2009-14 Regulation-2004-09

Depreciation rate

5.28%

3.6% + AAD

AAD

Discontinued

Applicable

Tuesday, June 28, 2011

COMET GROUP

4. Operation and Maintenance Expenses


Component of Capacity Charges Regulation-2009-14 Regulation-2004-09

Escalation Rate

5.72%

4%

For year 2004-05

Rs 5.2 lakhs/MW

For year 2009-10

Rs 14.8 lakhs/MW

Tuesday, June 28, 2011

COMET GROUP

10

5. Interest on Working Capital


Component of Capacity Charges Fuel Cost Liquid Fuel Cost Regulation-2009-14 1 month month Regulation-2004-09 1 month month

O&M Expenses Spares

1 month 30% of the O&M Expenses

1 month 1% of historical cost of the project 6% 2 months

Escalation on Spares Receivables Rate of Interest on Working Tuesday, June 28, 2011 Capital

Discontinued 2 months

As per SBI- PLR as on 1st April As per SBI- PLR as on 1st April COMET GROUP 11 of tariff year of tariff year

Norms of Operations
As per Regulation 2009-14 For gas based thermal generating plants Normative Annual Plant Availability Factor 85%

As per Regulation 2004-09 For gas based thermal generating plants Target Plant Load Factor- 80%

Incentives The new CERC regulation states that the incentive would be based on Plant Availability Factor (PAF) rather than the Plant Load Factor (PLF).

Tuesday, June 28, 2011

COMET GROUP

12

Plant Details
Rajasthan Rajya Vidyut Utpadan Nigam
Generation Capacity :- 100MW Station Heat Rate :- 2075Kcal/KWh PLF :- 80% PAF :- 85% No. of units :- 1
Tuesday, June 28, 2011 COMET GROUP 13

Means of Finance
Capital investment :- Rs 1000 Lacs Additional Capitalisation :- 40 Lacs Total Capital Investment :- 1040 Lacs Debt/Equity ratio :- 70:30 Debt :- 728 Lacs

Equity :- 312 Lacs Cost of land :- 100 Lacs(Assumed)


Tuesday, June 28, 2011 COMET GROUP 14

Additional Capitalisation
Additional Capitalisation' means the capital expenditure incurred or projected to be incurred, after the date of commercial operation of the project and admitted by the Commission after prudence check Initial Spares. Capitalised as a percentage of the original project cost,  (i) Coal-based/lignite-fired thermal generating stations - 2.5% Coal-based/lignite (ii) Gas Turbine/Combined Cycle thermal generating stations - 4.0%

Tuesday, June 28, 2011

COMET GROUP

15

Additional Capitalisation
(i) Undischarged liabilities; (ii) Works deferred for execution. (iii) Procurement of initial capital spares within the original scope of work . (iv) Liabilities to meet award of arbitration or for compliance of the order or decree of a court. (v) Change in law.
Tuesday, June 28, 2011 COMET GROUP 16

Components of Capacity Charges


1.

Return on equity Interest on loan capital Depreciation Operation and maintenance expenses Interest on working capital. Cost of secondary fuel(for coal based & lignite fired generating stations only) Special allowance in lieu of R&M or separate compensation allowance, wherever applicable.
COMET GROUP 17

2.

3.

4.

5.

6.

7.

Tuesday, June 28, 2011

1. Return on Equity(A)
Return on Equity 15.5% Equity 312 Lacs @15.5% ROE=48.4Lacs per yr A=48.4Lacs

Tuesday, June 28, 2011

COMET GROUP

18

2. Interest on Loan(B)
Gross Normative loan 728lacs Loan repayment period 10-15yrs 10Net loan amt payable for 1st year 48.53 lacs Opening balance after 1 year 728-48.53= 679 .47 Lacs 728Interest on loan @10% is 728 lac. for the 1st year lac. B= 72.80 Lacs
Tuesday, June 28, 2011 COMET GROUP 19

3. Depreciation(C)
Depreciation of assets upto 90% Depreciation rate 5.28% Depreciable value of the asset 846 lacs(less land cost) lacs(less Depreciation per year @ 5.28% for 1st year is 44.67 lacs(by SLM lacs(by method) C= 44.67Lacs
Tuesday, June 28, 2011 COMET GROUP 20

4. Operation and Maintenance Cost(D)


For Spares 14.8Lacs/MW Escalation rate 5.72% For 100MW Total O&M Cost for yr 1st is 1480Lacs and escalated further per year @ 5.72% D = 1480 Lacs
Tuesday, June 28, 2011 COMET GROUP 21

5. Interest on Working Capital(E)


Components are 1. Fuel cost 1 month 2. Liquid fuel cost month 3. O&M expenses 1 month 4. Spares 30% of O&M cost 5. Receivables 2 months

Tuesday, June 28, 2011

COMET GROUP

22

Interest on Working Capital(E)


Fuel cost(in Rs Lacs) Lacs) 1. Fuel cost 1 month = 755.18 2. Liquid fuel cost month = 164.25 3. O&M expenses 1 month =1480/12=123.33 4. Spares 30% of O&M cost = 444 5. Receivables 2 months = 1820.79 Total = 3307.5 Lacs Interest on WC @10.25%= 339 Lacs E=339Lacs
Tuesday, June 28, 2011 COMET GROUP 23

Total Capacity Charges


Sum of all component values i.e. A+B+C+D+E = 48.4 +72.80+ 44.67+1480+ 339 Total Capacity Charges= 1984.9 Lacs (A+B+C+D+E) Capacity charges per unit=1984.9*100000/total units generated =0.2920 Rs/unit
Tuesday, June 28, 2011 COMET GROUP 24

Energy Charges
Price of Natural Gas fuel = 3910.16 Rs/1000CM Price of Naptha/Liquid fuel = 19790.49 Rs/MT Naptha/Liquid Escalation rate 4% per yr GCV of natural gas = 9038.82 Kcal/CM GCV of Naptha/liquid fuel = 11330.22 Kcal/Lit. Naptha/liquid GSHR = 2075KCal/KWh
Tuesday, June 28, 2011 COMET GROUP 25

Energy Charges per Unit


Energy Charge Rate(ECR) ECR = Price of fuel*GSHR/GCV of Fuel ECR
for gas

= 3910.16*2075/9038.82 in Rs/unit

ECR for gas = 0.89 Rs/KWh ECR for Naptha = 3.62 Rs/KWh
Tuesday, June 28, 2011 COMET GROUP 26

Generation Details
Capacity :- 100MW :PLF :- 80% :Auxiliary consumptions :- 3% :Total no of units generated= PLF*Installed capacity*8760*(100%-3%)*1000 capacity*8760*(100%Which comes out 679.78MUs
Tuesday, June 28, 2011 COMET GROUP 27

Fuel Cost
Operating pattern on the basis of type of fuel Gas :- 84% :Liquid fuel :- 16% :Gas Fuel cost = units produced by gas fuel*ECRgas fuel*ECR = 571.01 MUs*0.89 Rs/KWh Which comes out Rs 5120.09Lacs For Naptha Rs 3942.05Lacs Total Fuel cost(gas+naptha)= 5129.09+3942.05 cost(gas+naptha)= = 9062.14 in Rs Lacs

Tuesday, June 28, 2011

COMET GROUP

28

Fuel Cost
9062.14/12 755.18 Lacs Liquid fuel cost for month =3942.05/24 164.25 Lacs Fuel cost for 1 month =

Tuesday, June 28, 2011

COMET GROUP

29

Energy Charges
Total sum of Fuel costs due to gas as well as by the liquid fuel(naptha) divided by total no. of fuel(naptha) units generated Energy charges per unit = 9062.14Lacs/679.78MUs ECR per unit
Tuesday, June 28, 2011

1.33Rs/KWh
COMET GROUP 30

Tariff
Sum of Capacity charges per unit and Energy charges per unit

Tariff = (0.292+1.33)Rs/unit = 1.625 Rs/unit

Tuesday, June 28, 2011

COMET GROUP

31

Multi year Capacity charges

Tuesday, June 28, 2011

COMET GROUP

32

Multi year Energy charges

Tuesday, June 28, 2011

COMET GROUP

33

Tariff for Multi year

Tuesday, June 28, 2011

COMET GROUP

34

Tuesday, June 28, 2011

COMET GROUP

35

You might also like