PT EQUITORIA OFFSHORE BERJAYA

PROYEK PEMBANGUNAN PIPA


28” TRANSMISI GAS GRESIK-
SEMARANG
CONTENT LIST
PROJECT PROFILE

PROFILE
Piping Lane Consist 168 point location, total 3540m long.
EQUIPMENT

Diameter 28 inch
1. Pipa 28” & 32” FOR CASING 4. Excavator PC200
Project Location : GRESIK - SEMARANG 2. Hidrolic Auger Boring Machine 5. Total Station/ Surveying
3. Rotary Auger Machine tools
6. Mobilize vehicle.

Project Scope: HORIZONTAL AUGER DRILLING/ TRUSTBORING


SCOPE OF WORK

INSTALLATION OF :
1. PIPE CROSSING 28”
2. INCLUDING PIPE CASING 32” FOR SOME LOCATION

FOR TYPICAL MAIN ROAD AND RAILWAY OF LINEPIPE


TRANSMISSION SEMARANG TO GRESIK BY
HORIZONTAL AUGER DRILLING
PROJECT ORGANIZATION STRUCTURE
PROJECT SCHEDULE
PROJECT TARGET
IDENTIFY DRILLING PATHS
1. Gas Pipeline enter the Railway Line Area Surabaya – Semarang;
- The position of Gas Pipeline streches from Gresik to Semarang

Purwodadi Lamongan
Bojonegoro
Cepu Babat
Duduksampeyan
Padangan Gresik

Banjarsari
IDENTIFY DRILLING PATHS
2. Typical Crossing Pipe;
- Typical Rail Way Crossing
IDENTIFY DRILLING PATHS
3. Typical Crossing Pipe;
- Typical Major Road Crossing
CONTROLLING AND MONITORING
HSE • Control & Monitoring Implementasi HSE Plan dan CSMS
• HSE Induction, Safety Patrol, Walkthrough
• Socialize Procedure, Drill
• SIKA, JSA, TBM, Safety Award
TIME • Monitoring Milestone
• Schedule monitoring dan tracking
(Critical Path, S Curve, Ganth chart, Ms.Project, Recovery
Schedule)

QUALITY • Implementasi QA/QC Plan & ITP


• Daily Contruction Inspection
• Quality Traceability

COST • Progress and Invoicing Verification


• Management CO
• Material Balancing

GENERAL • Progress Reporting (Daily, weekly, monthly Project report)


• Internal Meeting (War Room, Coordination Meeting)
• External Meeting (Weekly, Monthly Meeting, Rapat-rapat khusus)
• WA Group
SEQUENCE HORIZONTAL AUGER DRILLING
- AUGER BORING METHOD
1. Starting Excavation Entry & Exit Pit
2. Install Auger Rail & Machine at Entry Pit
SEQUENCE HORIZONTAL AUGER DRILLING
- AUGER BORING METHOD
3. Prepare Pipe Casing Ø 32 Inch & Main Pipe Ø 28 Inch
4. Insert Auger Bit into Pipe Casing
SEQUENCE HORIZONTAL AUGER DRILLING
- AUGER BORING METHOD
5. Lowering Auger Bore & Fit Up to Machine
6. Auger Boring & Fit Up Extension Bor Set
SEQUENCE HORIZONTAL AUGER DRILLING
- AUGER BORING METHOD
7. Commence Auger Boring
8. Receive Pipe Casing at Exit Pipe
SEQUENCE HORIZONTAL AUGER DRILLING
- AUGER BORING METHOD
9. Pull Out Auger Bit
10. Insert Service Pipe Ø 28 Inch with The Spacer
SEQUENCE HORIZONTAL AUGER DRILLING
- AUGER BORING METHOD
11. Service Pipe Fully Inserted into Casing
12. Tie In Service Pipe & Install Casing Accessories
SEQUENCE HORIZONTAL AUGER DRILLING
- AUGER BORING in SCENES

1. Land Clearing 2. Entry Pit and Exit Pit Construction 3. Installation of Auger Boring Rails
SEQUENCE HORIZONTAL AUGER DRILLING
- AUGER BORING in SCENES

4. Installation of Auger Boring 5. Installation of Auger Boring Unit 6. Preparing for Drilling
Machine Includes Casing and Alignment Setting
SEQUENCE HORIZONTAL AUGER DRILLING
- AUGER BORING in SCENES

7. Implementation of Drilling 8. Drill Position in Casing 9. Plugging Drill and Casing


SEQUENCE HORIZONTAL AUGER DRILLING
- AUGER BORING in SCENES

10. Drilling is continued after 11. After The Casing penetrates 12. Draw withdrawal after
Drill Hooking and Casing The Exit Pit, The Drill is removed Drilling process
QUALITY PLAN
• Design Requirement • Engineering Deliverable List
• Design Specification • Data Sheet & Calculation
ENGINEERING
• Design Approval • IFA  IFC
• Design Revision • Review Document

• AML Pertamina Gas


• Equipment vendor list
PROCUREMENT • Delivery time & Acceptance Test • Equipment On Schedule
• After sales service • Equipment Guarantee

• Data Sheet & Drawing


• Construction Method • PIC All Dicipline
CONSTRUCTION
& • Construction equipment • Test Report & Chekclist
• Construction Supervision
INSTALLATION
• Construction Quality

• Mechanical Completion &


• Hand over document Comm Acceptance
COMMISIONING
• Operational Acceptance • Document Dossier & MDR
• Final Acceptance
HEALTH and SAFETY ENVIRONMENT + SECURITY
EMERGENCY MEDICAL EVACUATION
Kecelakaan/
Lengkapi Laporan
Incident 1 x 24 jam ke :
- Supervisor Leader
- Project Leader
- Manager Operasi
TIDAK - Client rep
Kecela
Lengkapi Laporan
kaan
serius 1 x 24 jam

YA

Injury/Cedera

Dibutuh TIDAK
kan
mediva Perawatan medis
c /kotak p3K

YA

Bawa ke Rumah
Sakit Trauma Center
Terdekat
THANK YOU