How to Validate Computerized

Systems
An example from practice for the
pharmaceutical ERP system
Scarabaeus+
at Lindopharm GmbH
(Hilden - Germany)

© 2003 Manuel Droesler, IT-Engineer and certified Computer Validation Specialist,


Industrial Automation Partners BV - GTI GmbH Germany
What is Validation?
• A definition:
– Validation is the documented evidence, in
accordance with the GMP-requirements,
that all used methods, processes,
equipment, materials, workflows and
systems lead to the specified results and to
the specified characteristics of a product.
» Interpretation of the EU-GMP-Guide by the
German Inspector K.-H. Menges, Darmstadt «

© 2003 Manuel Droesler, IT-Engineer and certified Computer Validation Specialist,


Industrial Automation Partners BV - GTI GmbH Germany
Qualification vs. Validation
– Qualification by definition of the EU-GMP-
Guide is...
...the documented evidence that all used equipment
works correctly within its specification and leads
to the specified results.
– Since computerized Systems are more than
just Equipment (they contain Hardware,
Software, Processes and Personnel),
Qualification is a Part of the CS-Validation.
– Rule: Only qualified Computer-Systems can
be validated.
© 2003 Manuel Droesler, IT-Engineer and certified Computer Validation Specialist,
Industrial Automation Partners BV - GTI GmbH Germany
A Computerized System
More than just Hardware and Software !
• Software • Hardware/Equipment
– Standard Packages – Computers and Network
– Individual Solutions – Devices
– Interfaces/Add-Ons – Machines
– Software- – Hardware-
Documentation Documentation

• Processes/Documents • Personnel
– SOPs – Employees
– Validation – Specialists
– Logbooks – Consultants
– Change-Control – All must be trained!

© 2003 Manuel Droesler, IT-Engineer and certified Computer Validation Specialist,


Industrial Automation Partners BV - GTI GmbH Germany
Rules and Standards to Follow
• For the European Union
– EU GMP Guideline 91/356 and 91/412 (Article 9)
– EU GMP Guide
• particularly Annex 11 „Computerized Systems“
• For the U.S.
– FDA 21 CFR Part 211
• particularly Subpart D „Equipment“
– FDA 21 CFR Part 11
• „Electronic Records/Electronic Signatures“
• Worldwide recognized Interpretations and Guidances
– GAMP 4 (Good Automated Manufacturing Practice)
– PIC/S Draft-Guidance „Computerized Systems“
– New FDA Draft-Guidance „Part 11,...-Scope and Application“
– ISPE White Paper „Risk-Based
Approach to 21 CFR Part 11“
© 2003 Manuel Droesler, IT-Engineer and certified Computer Validation Specialist,
Industrial Automation Partners BV - GTI GmbH Germany
Who is Lindopharm
 Founded in 1947
 120 employees
 12 in field service
 Turnover 2002: 15 Mio €

 3700 m² pharmaceutical
production and service
 Distribution to Wholesalers
 Full-Service
 Development
 Laboratory
 Contract Manufacturing

© 2003 Manuel Droesler, IT-Engineer and certified Computer Validation Specialist,


Industrial Automation Partners BV - GTI GmbH Germany
Lindopharm Products

Capsules

Sprays
Liquids

and Drageés

Sachets

© 2003 Manuel Droesler, IT-Engineer and certified Computer Validation Specialist,


Industrial Automation Partners BV - GTI GmbH Germany
The use of Scarabaeus+
Dedicated pharmaceutical processes
• Recipes and detailed • Computer Controlled
Manufacturing Weighing and Step-By-
Instructions Step Instructions
• Production Planning • Covering every stage of
• Optimized Purchase production
• Batch oriented Material • Testing and Release of
Management Semi-Finals and Finals
• Warehouse and Stock • Sales and Order
Management management
• Automatic Status • Picking, Shipping,
Checking Invoicing
• Integrated Quality
Control Module
© 2003 Manuel Droesler, IT-Engineer and certified Computer Validation Specialist,
Industrial Automation Partners BV - GTI GmbH Germany
Assessing the GMP-Impact
GMP Risk in %
Purchase
50%
Finance/MIS Warehouse/ Stock
10% 90%

Marketing/ Sales Production


20% 100%
50%
Shipping/ Logistics QC/ Lab
100%

© 2003 Manuel Droesler, IT-Engineer and certified Computer Validation Specialist,


Industrial Automation Partners BV - GTI GmbH Germany
Phases of the Validation Cycle
• Phase 0: Planning and Definition
• Phase 1: Specification
• Phase 2: Implementation and Test
• Phase 3: Installation
• Phase 4: Qualification Testing
• Phase 5: Going Productive
• Phase 6: Keep it Validated

© 2003 Manuel Droesler, IT-Engineer and certified Computer Validation Specialist,


Industrial Automation Partners BV - GTI GmbH Germany
Phase 0: Planning and Definition
Activity / Document Responsibility
• SOP System for CS Validation System Owner

• CS Validation Master Plan System Owner

• User Requirement Spec. (URS) System Owner

• Vendor Auditing / Vendor Selection System Owner

• Functional Specification (FS) Vendor

© 2003 Manuel Droesler, IT-Engineer and certified Computer Validation Specialist,


Industrial Automation Partners BV - GTI GmbH Germany
Setting up the Framework:
SOP-System for Computer Validation
• SOP 1: Validation of Computerized • SOP 10: Error Handling and
Systems in GMP-Environment Escalation Strategy
• SOP 2: Risk Assessment for • SOP 11: Change Control for
Computerized Systems Computerized Systems
• SOP 3: Requirements for the User
Requirement Specification • SOP 12: Revalidation of
Computerized Systems
• SOP 4: Requirements for the
Functional Specification • SOP 13: Requirements for the
• SOP 5: Training for Computerized Validation Plan
Systems • SOP 14: Requirements for the
• SOP 6: Data Backup and Recovery Validation Report
• SOP 7: Security, Protection and • SOP 15: Vendor Auditing for
Access Rights Computerized Systems
• SOP 8: Breakdown of Computerized • SOP 16: FDA 21 CFR Part 11
Systems Compliance Strategy
• SOP 9: Recovery of Computerized
Systems after Breakdown

© 2003 Manuel Droesler, IT-Engineer and certified Computer Validation Specialist,


Industrial Automation Partners BV - GTI GmbH Germany
Validation Master Plan for
Computerized Systems
• General Commitment of the
Management
• Organisation and Responsibility
• Validation Policy
• Categories of Computerized Systems
• Classification of Components
• Validation Phases and Activities
• Problem Management and Error
Escalation
• Configuration and Version
Management
• Change Control Policy
• Living List of GMP-relevant
Computerized Systems in the Appendix

© 2003 Manuel Droesler, IT-Engineer and certified Computer Validation Specialist,


Industrial Automation Partners BV - GTI GmbH Germany
The V-Model
Finish
Risk Assessment
User Requirement Performance
Specification Qualification (PQ)

Funtional Operational
Specification Qualification (OQ)

Design Specification Installation


Design Qualification (DQ) Qualification (IQ)

System Module
Implementation Testing

© 2003 Manuel Droesler, IT-Engineer and certified Computer Validation Specialist,


Industrial Automation Partners BV - GTI GmbH Germany
Do Ask Questions First,
Shoot Later...
• User Requirement Specification (URS)
– Definition of the User‘s Needs
– Definition of the Environment, Standards, Rules and Legal Requirements
– Provide Demand Numbers for Crossreference Matrix
• Vendor Auditing / Vendor Selection
– Assessment of Vendor‘s Organisation and Product Portfolio
– Assessment of Vendor‘s QM-System
– Use Checklist (i.e. from GAMP 4 Appendix M2)
– Reduce Time and Effort by Joint Audits
– Put Your Decision in a written Document!!!
• Functional Specification (FS)
– Given by the selected Vendor
– Definition, how Vendor plans to fulfill the Demands
– Demand Numbers should be used
for Crossreference to URS

© 2003 Manuel Droesler, IT-Engineer and certified Computer Validation Specialist,


Industrial Automation Partners BV - GTI GmbH Germany
Phase 1: Specification
Activity / Document Responsibility
• Project Validation Plan (PVP) System Owner
• Project Quality Plan (PQP)
• Hardware Design Specification Vendor /
System Owner
• Software Design Specification Vendor

• Software Module Specification Vendor

• Design Qualification (DQ) System Owner

© 2003 Manuel Droesler, IT-Engineer and certified Computer Validation Specialist,


Industrial Automation Partners BV - GTI GmbH Germany
Project Validation Plan (PVP)
Project Quality Plan (PQP)

• Defines the Validation Strategy for the specific Computerized System


• Exact Planning for the Validation of the specific Computerized System
• Contains an continously updated Task- and Time-Schedule
• PVP and PQP are very often maintained
together in one Document

© 2003 Manuel Droesler, IT-Engineer and certified Computer Validation Specialist,


Industrial Automation Partners BV - GTI GmbH Germany
Design Specification and
Design Qualification (DQ)
• Hardware Design Specification
– Fixed Environment given by System Owner
• Facilities, Installation, Building, Rooms, Cabling, Power etc.
– Required Environment given by Vendor
• Minimum and Recommended Hardware, Devices, Workstations, Servers, Network,
Interfaces to Side-Systems
• Software Design Specification
– Drill-Down of FS into Software Functionalities
– Should refer to Demand Numbers from URS for Crossreference
– Given by Vendor
• Software Module Specification
– Very Detailed Specification of Module Design and Data Structures
– Given by Vendor and used by Vendor‘s Developers to implement the
Software according to the Requirements
• Design Qualification (DQ)
– Optional formal Act of checking
Design Documents for Completeness
© 2003 Manuel Droesler, IT-Engineer and certified Computer Validation Specialist,
Industrial Automation Partners BV - GTI GmbH Germany
Phase 2: Implementation and Test
Activity / Document Responsibility
• Risk Assessment / Risk Analysis System Owner/
• Testplans for FAT, SAT, IQ, OQ, PQ Vendor
• Software Development Vendor

• Module Testing (100% !) Vendor

• Optional Factory Acceptance Test System Owner/


(FAT) Vendor

© 2003 Manuel Droesler, IT-Engineer and certified Computer Validation Specialist,


Industrial Automation Partners BV - GTI GmbH Germany
Risk Assessment / Risk Analysis
• A permanent Meassure to assess GMP-Risks in all Phases
• Most important to determine the Depth and the Effort of the different Test
Phases (Module Testing, IQ, OQ, PQ)
• Should be carried out by using standard Risk Assessment Methods (i.e. FMEA)
• Should be supported by a Risk Assessment Tool
• FMEA (Failure Mode and Effect Analysis) Adaptation for CS-Validation:
Preparation: Define a Risk Assessment Team for the CS
Step 1: Identify all Functionalities of the CS (use URS, FS and DS for Reference)
Step 2: Assess the GMP-Relevance of every Functionality
Step 3: Identify possible Malfunctions by reversing the Effect of every intended
Funtionality
Step 4: Assess the Probability of Appearance (low = 1, medium = 2, high = 3),
the Importance (low = 1, medium = 2, high = 3, extreme = 4) and the
Probability of Detection (high = 1, medium = 2, low = 3) of the Fault
Step 5: Calculate Risk Priority Value (A x I x D)
Step 6: For RP-Values of 7 or higher define protective Meassures (Module
Testing, IQ Tests, OQ Tests, PQ Test, Maintenance)
Step 7: Re-assess Risk, taking successful protective Meassures into account.
This time, the RP-Values should be below 7

© 2003 Manuel Droesler, IT-Engineer and certified Computer Validation Specialist,


Industrial Automation Partners BV - GTI GmbH Germany
Risk Assessment Tool

© 2003 Manuel Droesler, IT-Engineer and certified Computer Validation Specialist,


Industrial Automation Partners BV - GTI GmbH Germany
Test Planning
• Module Testing
– Carried out by Vendor
– Should be 100% of all Functionalities (GMP- and Non-GMP-
Relevant Functions)
– Normally also required by QA-System of a GMP-compliant Vendor
(i.e. complete Test Documentation available for Scarabaeus+)
– Can be referenced as Part of the Validation (no Need to repeat all
Tests!)
– Should be supported by a Test Specification Tool to ease Test
Planning for all Test Phases
• Factory Acceptance Test (FAT)
– Optional Test against the Functional Specification in Vendor‘s
Environment
– Required by GAMP4; can be omitted, if Vendor or CS is Standard or
has reliable References
– If successful, CS is released for Delivery and Installation

© 2003 Manuel Droesler, IT-Engineer and certified Computer Validation Specialist,


Industrial Automation Partners BV - GTI GmbH Germany
Test Specification/Protocol Tool

© 2003 Manuel Droesler, IT-Engineer and certified Computer Validation Specialist,


Industrial Automation Partners BV - GTI GmbH Germany
Phase 3: Installation

Activity / Document Responsibility


• Delivery and Configuration Vendor

• Optional Site Acceptance Test (SAT) System Owner

• Training Plan and User Training System Owner/


Vendor

© 2003 Manuel Droesler, IT-Engineer and certified Computer Validation Specialist,


Industrial Automation Partners BV - GTI GmbH Germany
Bringing the System On Stage
• Delivery and Configuration of the CS at the Target Location
• Vendor should have SOP for the Process of Delivery and Installation
• Vendor provides Installation Plan and writes down an Installation
Protocol and a Configuration Protocol
• Neccessary Modifications during Installation MUST be tracked according
to Change Control Procedures
• Site Acceptance Test (SAT)
– Optional Test for correct Installation in System Owner‘s Environment
– Very often covered by IQ to reduce Costs and Effort
• Training Phase
– System Owner (and Vendor) create(s) Training Plan
– Separated Training System should be made available (i.e. parallel
Installation of an identical second Instance of the CS)
– Users are training according to Training Plan
– Trainings have to be documented!

© 2003 Manuel Droesler, IT-Engineer and certified Computer Validation Specialist,


Industrial Automation Partners BV - GTI GmbH Germany
Phase 4: Qualification Testing

Activity / Document Responsibility


• Installation Qualification (IQ) System Owner

• Operational Qualification (OQ) System Owner

• Performance Qualification (PQ) System Owner

• FDA 21 CFR Part 11 Compliance System Owner/


Paper (if required) Vendor

© 2003 Manuel Droesler, IT-Engineer and certified Computer Validation Specialist,


Industrial Automation Partners BV - GTI GmbH Germany
Testing for Qualification
• Tests during Installation Qualification (IQ)
– Should ensure correct Installation of the CS
– Checked against general System Design Specification
– Focussed on Hardware, Network, Equipment and Interfaces
– Testplan can be derived from Risk Assessment and reduced to GMP-relevant
Risks
• Tests during Operational Qualification (OQ)
– Should ensure correct Implementation of the required Functionalities
– Checked against Functional Specification
– Testplan can be derived from Risk Assessment and reduced to GMP-relevant
Risks
• Tests during Performance Qualification (PQ)
– Should ensure correct System Operation under real productive Conditions
– Should consider Stress Tests and intentional System Failures
– Checked against User Requirement Specification
– Testplan can be derived from Risk Assessment and reduced to GMP-relevant
Risks

© 2003 Manuel Droesler, IT-Engineer and certified Computer Validation Specialist,


Industrial Automation Partners BV - GTI GmbH Germany
Phase 5: Going Productive

Activity / Document Responsibility


• Maintenance Plan System Owner /
• Maintenance and Service Contract Vendor
• Validation Report System Owner

• Release of CS for Production System Owner

© 2003 Manuel Droesler, IT-Engineer and certified Computer Validation Specialist,


Industrial Automation Partners BV - GTI GmbH Germany
Reaching the Target...
• Maintenance
– System Owner should create Maintenance Procedures for the CS
– Vendor should provide a Maintenance Contract
– Version Management and Change Control Procedures must be
ready and operative
• Validation Report
– Document collects all results of all Validation Activities
– All Actions must be completed according to Validation Plan
– The correct Sequence of Actions must be evident
– Deviations and Follow-Up Meassures must be reported
• ...and then
– Release of the validated Computerized System for
productive Operation by the Responsible
of the System Owner

© 2003 Manuel Droesler, IT-Engineer and certified Computer Validation Specialist,


Industrial Automation Partners BV - GTI GmbH Germany
Phase 6: Keep it Validated
Activity / Document Responsibility
• Maintain System and Error System Owner
Logbooks
• Follow Data Backup Procedures System Owner

• Configuration and Version System Owner


Management
• Follow Change Control Procedures System Owner

• Self-Inspections and (Re-)Training System-Owner


of Users

© 2003 Manuel Droesler, IT-Engineer and certified Computer Validation Specialist,


Industrial Automation Partners BV - GTI GmbH Germany
For More Information go to...

www.iapbv.nl
www.gti-scarabaeus.com
www.csv-pharma.de

© 2003 Manuel Droesler, IT-Engineer and certified Computer Validation Specialist,


Industrial Automation Partners BV - GTI GmbH Germany