You are on page 1of 49

INDEPENDENT PROJECT ANALYSIS, INCORPORATED

Presented by:
Dean Findley

THE AMERICAS u THE NETHERLANDS u AUSTRALIA u CHINA


Why Labor Productivity?

• This is the second report back on a three year IBC


study of construction labor productivity
• Why worry about productivity:
– About one-quarter of all construction cost is field labor
– Labor is usually the largest non-material cost in a project
– Very little is really understood about how to best measure
field productivity or how to influence it
– In developed economies of Europe and North America
construction labor shortages will become more and more
common as the population ages
– In low wage countries, poor labor productivity is the
primary obstacle to low cost manufacturing facilities

Labor Productivity Phase II 2 INDEPENDENT PROJECT ANALYSIS


Goals of This Research

• Phase I Goals
– Develop and validate a reliable approach to measuring
labor cost and productivity
– Understand the relationships between labor
productivity and the project practices that IPA has
traditionally gathered (FEL, etc.)
• Phase II Goals
– Explore the relationship between engineering and
construction execution practices and labor productivity
in high wage countries

• Phase III Goals


– Explore the relationship between engineering and
construction execution practices and labor productivity
in low wage countries
Labor Productivity Phase II 3 INDEPENDENT PROJECT ANALYSIS
Outline

• Measuring labor productivity


• Review of first year’s work

• More Practices and Productivity

• Productivity in Europe v. North America

• Doing something about the weather

• Conclusions

Labor Productivity Phase II 4 INDEPENDENT PROJECT ANALYSIS


Labor Productivity Database

• 1185 projects in the United States and Europe


• 103 companies represented

Greater Houston
Europe 20%
27%

W. USGC
5%

E. USGC
US Northeast 14%
15%
N. Calif.
2%
US Midwest
US S. East S. Calif
4%
10% 3%

- Labor Productivity Phase II 5 INDEPENDENT PROJECT ANALYSIS


European Labor Productivity Database
• 295 projects in Europe
• 35 companies represented

Netherlands
17% Spain
Germany 4%
8%

United Kingdom
33%

France
34%
Belgium
4%

- Labor Productivity Phase II 6 INDEPENDENT PROJECT ANALYSIS


Labor Productivity Database

Average Median Range

Project Size $36.6 MM $12 MM $0.054 MM -


$1547.07 MM

Start Year of 1995 1996 1972 - 2001


Construction

1988 USD basis

- Labor Productivity Phase II 7 INDEPENDENT PROJECT ANALYSIS


Labor Productivity Database

Greenfield/Colocated
23% Revamp
32%

Add-on
24%
Expansion
21%

- Labor Productivity Phase II 8 INDEPENDENT PROJECT ANALYSIS


Defining Labor Cost

• Labor cost is the amount of money spent on field


construction, including
– Wages
– Benefits
– Small tools
– Subcontractor profits and fees
– Overtime premiums
• Does not include
– Construction equipment (e.g. cranes, bulldozers,
backhoes, etc.)
– Construction supervision
– Field engineering
Labor Productivity Phase II 9 INDEPENDENT PROJECT ANALYSIS
Methodology (1)

• Projects were again grouped according to


process type and project type to minimize scope
variations

• A base location was created in Europe

• Database was increased from 570 to 1100

• Both large and small projects were added

• Labor cost breakouts were available for all


projects

Labor Productivity Phase II 10 INDEPENDENT PROJECT ANALYSIS


Methodology (2)

• Each group provides a good like-for-like field work


to be performed
• Modular projects were excluded to minimize error
• Each group has good dispersal of projects
geographically
• Each group has a good sample of projects in Greater
Houston to provide a US Gulf Coast anchor
• As the methodology develops, other “anchors” will
be developed and become interchangeable
– Rotterdam has been added this year
– Singapore and São Paulo will be added next year
Labor Productivity Phase II 11 INDEPENDENT PROJECT ANALYSIS
Methodology (3)

• Effective Labor Cost Index compares the amount


of labor required within each group; groups are
then aggregated
– The Labor Cost Index measures the relative
amount of money a project spent on field labor
– Greater Houston is set equal to 1.0
• The Labor Productivity Index is created by
adjusting the all-in wages to the same US dollar
basis
– The Labor Productivity Index measures the
comparative number of labor hours that like scope
required to complete
Labor Productivity Phase II 12 INDEPENDENT PROJECT ANALYSIS
Labor Productivity Index

WORSE
WORSE

1.4

Poorer Labor
Productivity
Labor Productivity Index

1.2

0.8
Better Labor
Productivity

BETTER
BETTER

0.6

- Labor Productivity Phase II 13 INDEPENDENT PROJECT ANALYSIS


Outline

• Measuring labor productivity

• Review of first year’s work


• More Practices and Productivity

• Productivity in Europe v. North America

• Doing something about the weather

• Conclusions

Labor Productivity Phase II 14 INDEPENDENT PROJECT ANALYSIS


Primary Conclusions

• There is little variation in effective labor cost


from region to region
– Standard error across regions is only 7 percent
– Corrected by company standard error is 4 percent
• There is more variation in productivity from
region to region
– Standard error is 10 percent
– 7 percent corrected by company
• Variation in productivity is dampening the
variation in effective labor cost
• Labor unions on average supply considerably
more productive labor in the United States
Labor Productivity Phase II 15 INDEPENDENT PROJECT ANALYSIS
Conclusions About Regional Variation

• Very little true region-to-region variation in cost,


especially in the same general labor market
– Contradicts perceptions of many company estimators

– Because they extrapolate their company’s experiences


or listen to contractors’ whining

– Accords better with economic theory

• Average productivity differences probably driven


by differential skill levels

• Much of the regional variation is really variation


by company
Labor Productivity Phase II 16 INDEPENDENT PROJECT ANALYSIS
FEL Drives Labor Cost Index

1.15 Pr < .001

1.10
Labor Cost Index

1.05

1.00

0.95

TOO MUCH BEST Practical GOOD FAIR POOR


0.90
2 2.5 3 3.5 4 4.5 FEL
5 Index
5.5 6 6.5 7 7.5 8 8.5 9 9.5

- Labor Productivity Phase II 17 INDEPENDENT PROJECT ANALYSIS


FEL Drives Labor Productivity

• Significant components are:


– Definition of soils

– Definition of health and safety

– Engineering status

• By far the most important FEL Component for


Productivity is Execution Planning

Labor Productivity Phase II 18 INDEPENDENT PROJECT ANALYSIS


Execution Planning Drives Productivity
1.15

Pr <.006
Labor Productivity Index

1.10
8 percent better
than average
1.05

1.00

0.95

0.90
Assumed Preliminary Definitive

- Labor Productivity Phase II 19 INDEPENDENT PROJECT ANALYSIS


The Effects of Detailed Scheduling
All Projects

1.10 Pr < .001

1.05
Labor Cost Index

1.00

0.95

0.90
Milestone Integrated
Critical Path Resource-loaded
Schedule

- Labor Productivity Phase II 20 INDEPENDENT PROJECT ANALYSIS


The Effects of Detailed Scheduling
Small Projects

1.15
Resource loading is not necessary to
improve labor productivity on small
1.10 projects. (But it does produce shorter
schedules).
Labor Cost Index

1.05

1.00

0.95

0.90
Integrated
Milestone Critical Path Resource-loaded
Schedule
- Labor Productivity Phase II 21 INDEPENDENT PROJECT ANALYSIS
Labor Productivity and the VIPs

• Value engineering + 5 percent

• Predictive maintenance + 7 percent

• Design to Capacity + 9 percent

• 3D CAD + 7 percent (and up)

• No other relationships with VIPs, including no


relationship with Constructability Reviews!

Labor Productivity Phase II 22 INDEPENDENT PROJECT ANALYSIS


Outline

• Measuring labor productivity


• Review of first year’s work
• More Practices and Productivity
– contracting
– teams
– planning and control
– construction supervision
– use of overtime
• Productivity in Europe v. North America
• Doing something about the weather
• Conclusions
Labor Productivity Phase II 23 INDEPENDENT PROJECT ANALYSIS
Contracting and Productivity

• Union jobs are almost 17 percent more


productive on average than open/merit shop in
the USA

• Union jobs averaged a labor cost index of 0.998


versus 1.08 for non-union construction outside
the USGC

• Mixed union/non-union jobs are slightly less


(Poorer) productive than open shop and much
less productive than union jobs

• Subcontractor supplied labor is 13 percent more


productive on average than direct-hire
Labor Productivity Phase II 24 INDEPENDENT PROJECT ANALYSIS
Teams and Productivity

• Integrated team projects have 6 percent more


productive field labor
– environmental specialist involvement is important

– health & safety specialist is important

• Using an owner scheduling engineer, starting in


FEL, is associated with 7 percent better
productivity

Labor Productivity Phase II 25 INDEPENDENT PROJECT ANALYSIS


WORSE Whose Cost/Schedule Control Plan?

1.2

1.1

0.9
BETTER

0.8
Owner “Integrated” Separate Contractor
only owner Owner & only
contractor contractor
- Labor Productivity Phase II 26 INDEPENDENT PROJECT ANALYSIS
Any Deviation from Construction Plan
Drives Poor Productivity
WORSE

1.10
Productivity Index

1.05

1.00

0.95
BETTER

0.90
-30 -25 -20 -15 -10 -5 0 5 10 15 20

Percent Schedule Deviation in Construction

- Labor Productivity Phase II 27 INDEPENDENT PROJECT ANALYSIS


Added Supervision
Improves Productivity
WORSE

1.10

1.05
Productivity Index

1.00

0.95 Below 5-to-1, productivity rises


but labor costs increase

0.90
BETTER

0.85
5 6 7 8 9 10
Ratio of Workers to Supervisors

- Labor Productivity Phase II 28 INDEPENDENT PROJECT ANALYSIS


The Effect of Overtime on Productivity

• The use of overtime is the most common way to


recover slipped schedules and accelerate projects
that are schedule-driven
• Overtime is also sometimes used to attract labor when
shortages occur
• Overtime was used on over a third of North American
projects and a quarter of European projects
• The use of overtime is increasing
• The adverse effect of overtime on productivity is
accepted as fact despite the dearth of empirical
analysis, especially for the process industries
Labor Productivity Phase II 29 INDEPENDENT PROJECT ANALYSIS
Productivity Declines as
Work Week Increases
WORSE

1.2

1.15
Productivity Index

1.1

1.05

1
BETTER

0.95
35 40 45 50 55 60 65 70 75
Hours/Week

- Labor Productivity Phase II 30 INDEPENDENT PROJECT ANALYSIS


The Effect of Extended 50 Hour Weeks

1.4

55 hours pay for 40 hours of work equivalent


1.3
Productivity Index

55 hours pay for 46 hours of work


1.2
equivalent

1.1

Start with 8 percent loss


1.0

0.9
1 2 3 4 5 6
Months of 50-Hour Weeks
- Labor Productivity Phase II 31 INDEPENDENT PROJECT ANALYSIS
Outline

• Measuring labor productivity

• Review of first year’s work

• More Practices and Productivity

• Productivity in Europe v. North America


• Doing something about the weather

• Conclusions

Labor Productivity Phase II 32 INDEPENDENT PROJECT ANALYSIS


Europe v. North America

• Differences are generally not large

• The relationships between practices and productivity


results are virtually identical
– same effect of FEL

– same VIPs, etc.

• One interesting difference:


– Environmentally-driven projects on the USGC are
characterized by poor labor productivity (+12 percent)

– Such projects in Europe are characterized by excellent


productivity
Labor Productivity Phase II 33 INDEPENDENT PROJECT ANALYSIS
Productivity Over Time

1.4

1.3
Productivity Index

1.2

1.1

1.0

0.9

Indexed to USGC = 1
0.8
1986 1991 1996 2001
USGC Europe Southern UK

- Labor Productivity Phase II 34 INDEPENDENT PROJECT ANALYSIS


Regional Variation Within Europe

Region Effective Relative


Labor Cost Productivity

Northern UK 1.04 1.10+


Southern UK 1.05 1.12
Belgium 0.97 0.97+
France 1.12 1.13
West Germany 1.15 1.10++
East Germany 1.12 1.15++
Netherlands 1.06 0.96
Spain 0.89 1.16

At 1 March 2002 exchange rates

+ Result is driven by a performance of single company


++One company is influential
Labor Productivity Phase II 35 INDEPENDENT PROJECT ANALYSIS
Very Little Difference in Labor Productivity
US outside GC=1.074

Europe=1.084

USGC=1

.76 1 1.24
Labor Productivity Index
- Labor Productivity Phase II 36 INDEPENDENT PROJECT ANALYSIS
Outline

• Measuring labor productivity

• Review of first year’s work

• Productivity in Europe v. North America

• More Practices and Productivity

• Doing something about the weather


• Conclusions

Labor Productivity Phase II 37 INDEPENDENT PROJECT ANALYSIS


Why Worry About the Weather?

• The weather is a significant risk factor for many


projects

• The weather is an important estimating issue


between owners and contractors and is sometimes
used by contractors to “fatten” estimates on
reimbursable or negotiated lump-sum contracts

• Therefore, establishing some quantitative data


around the effects of specific weather on
productivity should be useful

Labor Productivity Phase II 38 INDEPENDENT PROJECT ANALYSIS


Weather data

• The US National Oceanographic and Atmospheric


Administration (NOAA) keeps very detailed
records of weather at most construction locations
in the USA

• We purchased daily weather information in


electronic form for the construction periods of
approximately 50 percent US projects in our
productivity database

• We then matched weather results to productivity

Labor Productivity Phase II 39 INDEPENDENT PROJECT ANALYSIS


Weather Variables

• Temperature Variables
– temp90 - Percent of construction days with the daily high
temperature above 90 degrees Fahrenheit (32 degrees C)
– coldxx - Percent of construction days with the “cooling degree
days” measure greater than 10, 15, 20, or 25. Cooling degree days
are measured as each degree of temperature of the daily mean above
65 degrees F (18 degrees C).
– Heatxx - Percent of construction days with the “heating degree
days” measure greater than 10, 15, 20, or 25. Heating degree days
are measured as each degree of temperature of the daily mean below
65 degrees Fahrenheit.

• Precipitation Variables
– snow - Percent of construction days with 1/2 inch or more of daily
snowfall

Labor Productivity Phase II 40 INDEPENDENT PROJECT ANALYSIS


Weather Variables (cont.)

• Wind
– windxx - Percent of construction days with resultant wind speed
greater than 15, 20, or 25 miles per hour. Resultant wind speed is
calculated as the vector sum of the wind’s speed divided by the
number of observations.

• Discomfort
– Caution - Percent of construction days where combination of heat
and humidity qualified as a “caution” condition by the National
Weather Service

– Danger - Percent of construction days where combination of heat


and humidity qualified as a “Danger” condition by the National
Weather Service

Labor Productivity Phase II 41 INDEPENDENT PROJECT ANALYSIS


General Effects of Weather on Productivity

60%

50%

40%

30%

20%

10%

0%
Wind15 Danger Cold15 Caution Temp90 Cold10

- Labor Productivity Phase II 42 INDEPENDENT PROJECT ANALYSIS


Weather Effects in Warmer Regions
25%

20%

15%

10%

5%

0%
Danger Caution Cold15

- Labor Productivity Phase II 43 INDEPENDENT PROJECT ANALYSIS


Weather Effects in Northern US
70%
65%
60%
55%
50%
45%
40%
35%
30%
Wind20 Snow Heat25 Heat20

- Labor Productivity Phase II 44 INDEPENDENT PROJECT ANALYSIS


Weather Conclusions

• High winds are most destructive of labor productivity

• The effects of rain are too small to detect except for


projects that involve large amounts of difficult
welding, e.g. hydroprocessing

• The effects of weather are quantifiable

• Data necessary to find averages are generally


available

• Owners might consider taking weather risks


whenever the contractor’s predicted effects are
higher than average
Labor Productivity Phase II 45 INDEPENDENT PROJECT ANALYSIS
Outline

• Measuring labor productivity

• Review of first year’s work

• Productivity in Europe v. North America

• More Practices and Productivity

• Doing something about the weather

• Conclusions

Labor Productivity Phase II 46 INDEPENDENT PROJECT ANALYSIS


Conclusions

• Overall project-to-project variation in labor


productivity is 24 percent on a single standard
deviation

• Even within highly homogeneous projects in the same


region, the variation is about 15 percent

• This means there is a substantial gain available in


improved labor productivity

• Good labor productivity does more than reduce cost


– Improves schedule
– Improves quality

Labor Productivity Phase II 47 INDEPENDENT PROJECT ANALYSIS


Keys to Better Productivity

• Detailed execution planning is the single most


important driver of better field productivity

• Execution planning has been progressively


outsourced to contractors

• But the data are clear: owner execution planning and


control are central to securing good labor productivity

• The principal role of the engineering contractor is to


provide timely, high-quality engineering documents to
construction; it is not to take the place of the owner in
the execution planning process

Labor Productivity Phase II 48 INDEPENDENT PROJECT ANALYSIS


Path Forward -- Phase III

• Work will continue on the collection of more


detailed practices in the field that may affect
productivity

• Regional focus for IBC 2003 will be Latin


America and Asia

• Main emphasis will be on low-wage, generally


lower skilled labor situations in which major
cost swings can be achieved

Labor Productivity Phase II 49 INDEPENDENT PROJECT ANALYSIS

You might also like