You are on page 1of 23

SUNWAY GANDARIA BANGI

PROJECT CODE : SB179

01 – 30 APRIL 2018

WIRA SYUKUR (M) SDN BHD


PELAN LOKASI

BANDAR BARU BANGI SEKSYEN 9


PELAN LOGISTIK
WORK PROGRESS

MARCH 2018 APRIL 2018


ITEM
Physical Physical
Time Elapsed ( Days ) 498 526
Schedule (%) 38.00 43.00
Actual (%) 36.00 41.00
Variance (%) -2.00 -2.00
Ahead / Delay ( Day/s ) -12.22 -12.00

Main delay is due to incomplete schedule structure work at Zone 3 (Level 9 onwards).
Architecture and M&E trade at Tower will commence earlier than schedule (Catch up Rev 02) in
order to catch up the overall delays.
SUMMARY OF WORK
PROGRESS
SUMMARY WORK PROGRESS PERCENTAGE BY MONTH

percentage progress %
16.00

14.45
14.00

12.00

10.00

8.00
percentage progress %
6.00

4.00 4.00
4.00

2.67 2.00 2.00 2.00


2.00
1.15 1.03 1.26 1.26 1.19
0.77 1.08 0.77 0.60 0.69
0.00 0.34
0.00

Month Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18
Progress
Percentage 0.00 0.77 1.08 1.15 1.03 0.77 2.67 1.26 1.19 0.69 0.34 14.45 2.00 2.00 2.00 4.00 4.00

NOTE: November 2017 work progress percentage is based on Catch up Work Program Rev 02
SUMMARY CONCRETE BY MONTH

2,500.00

2,002.50
1,854.50
2,000.00 1,813.50
1,830.00
1,789.00

1,454.50
1,500.00
1,305.48 1,454.00
1,224.00
1,470.00 1,408.50
1,307.00
Series1
1,000.00 1,100.00
634.00 650.50
851.50
623.00
500.00

171.00
0.00

MONTH
Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18

VOLUME
171.00 634.00 650.50 623.00 1,224.00 1,100.00 1,305.48 851.50 1,854.50 1,470.00 1,454.50 1,830.00 1,408.50 2,002.50 1,307.00 1,454.00 1,789.00 1,813.50
PROGRESS CLAIM

ACT.CLAIM
RM4,000,000.00

RM3,603,569.47
RM3,500,000.00

RM3,000,000.00

RM2,596,877.71
RM2,500,000.00 RM2,397,290.62 RM2,463,206.73

RM2,189,289.38
RM2,105,189.92
RM2,000,000.00 RM1,943,554.49
RM1,855,180.98

RM1,500,000.00
RM1,403,831.08 RM1,174,071.65
RM1,634,220.50 RM1,216,705.19
RM1,327,821.62
RM1,000,000.00
RM998,396.93
RM844,200.00
RM500,000.00 RM820,483.15
RM273,516.67

RM0.00
Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18
Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18
ACT.CLAIM RM844,2RM1,327RM1,403RM998,3RM273,5RM1,634RM2,189RM820,4RM2,397RM2,463RM1,216RM1,174RM1,943RM2,105RM3,603RM1,855RM2,596
S-CURVE
70.00

60.00
58.00

51.25
50.00

44.50
40.00 41.00
38.35
36.00
32.20 32.00
30.00 30.00 SCH PHY %
27.80 28.00
26.00 ACT PHY %
23.40
20.00 20.45
17.50
15.50
13.50
10.00
11.45 10.52 11.21 11.55
8.77 8.73 9.33
6.91 7.47
4.20 4.80
3.20 3.00 4.03
1.20
0.77 1.85
0.00 0.00

MONTH Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18
SCH PHY
0.00 1.20 3.20 4.20 6.91 8.77 11.45 13.50 15.50 17.50 20.45 23.40 27.80 32.20 38.35 44.50 51.25 58.00
%
ACT PHY
0.00 0.77 1.85 3.00 4.03 4.80 7.47 8.73 9.33 10.52 11.21 11.55 26.00 28.00 30.00 32.00 36.00 41.00
%
SECTION 1
Level Description
Zone 1 Zone 2 Zone 3
RC Canopy
RC plinth 11/08/2018 – 31/08/2018
Upper Roof Structure
Lower Roof slab, L38 04/08/2018 - 20/08/2018
37 Finish 03/08/2018 08/08/2018 13/08/2018
36 Finish 27/07/2018 01/08/2018 06/08/2018
35 Finish 20/07/2018 25/07/2018 30/07/2018
34 Finish 13/07/2018 18/07/2018 23/07/2018
33 Finish 06/07/2018 11/07/2018 16/07/2018
32 Finish 29/06/2018 04/07/2018 09/07/2018
31 Finish 22/06/2018 27/06/2018 02/07/2018
30 Finish 14/06/2018 20/06/2018 25/06/2018
29 Finish 08/06/2018 13/06/2018 18/06/2018
28 Finish 01/06/2018 06/06/2018 11/06/2018
27 Finish 25/05/2018 30/05/2018 04/06/2018
26 Finish 18/05/2018 23/05/2018 28/05/2018
25 Finish 11/05/2018 16/05/2018 21/05/2018
24 Finish 04/05/2018 09/05/2018 14/05/2018
23 Finish 02/05/2018 07/05/2018
22 Finish 30/04/2018
21 Finish
20 Finish
19 Finish
18 Finish
17 Finish
16 Finish
15 Finish
14 Finish
13 Finish
12 Finish
11 Finish
10 Finish
Z3 Z2 Z1
LAPORAN KEMAJUAN BERGAMBAR
VIEW A

Level 8 Level 8
swimming Swimming
pool slab pool slab and
casted and wall casted
wall in
progress

30.03.2018 26.04.2018

PREVIOUS CURRENT
VIEW B

Level 19 Slab
Level 23 Slab
Casted (Zone 1)
Casted (Zone 1)

30..03.2018 26.04.2018

PREVIOUS CURRENT
VIEW C

Level 18 Slab Level 22 Slab


Casted (Zone 2) Casted (Zone 2)

30.03.2018 26.4.2018

PREVIOUS CURRENT
VIEW D

Level 17 Slab Level 21 Slab


Casted (Zone 3) Casted (Zone 3)

30.03.2018 26..04.2018

PREVIOUS CURRENT
VIEW E

Level 8
Wading pool Level 8 Wading
slab casted pool slab and
and wall in wall casted
progress

30.03.2018 26.04.2018

PREVIOUS CURRENT