THE CONSTRUCTION INDUSTRY IN GENERAL
CHAPTER 2
THE TENDER PROCEDURE
CHAPTER 3
THE CONTRACT PROCEDURE
CHAPTER 4
THE STANDARD FORM OF CONTRACT (P.W.D
FORM 203/203A)
CHAPTER 5
THE PRELIMINARY ESTIMATING METHOD
CHAPTER 6
THE BUILD-UP METHOD
CHAPTER 7
THE QUANTITY MEASUREMENT
CHAPTER 1
THE CONSTRUCTION INDUSTRY IN
GENERAL
Construction industry;
• Industries includes building work and civil
engineering works.
• The main objectives is to get maximum
profit upon the investment.
• will require collaborate with others.
Works in Construction
Industry
• Building Work
– Eg; construction of houses
Owner/Client (Design)
• Owner of the project/ client
• Appoints consultants & contractors
Architect (Design)
• Will materialize the owner’s / clients need
• Prepare preliminary design & detailed
design according to the client’s need &
cost
Civil/Structure Engineer/ Electric/ Machines (Design)
• Play as same role with the architects but within their designated
fields
• Will always communicate with the architects about the project
Contractor (Builders)
• Must build & complete the project based on the
specification in the contract document
• Must bear the cost of all the works on site during
construction & after completion
• Must work efficiently to complete the project by
due date
• Must obey & follow local legislation
• Must provide insurance coverage for the project
& workers
Architect (Builders)
• To control & supervise construction project
according to the original design
• Team leader among the consultants
• To communicate with the contractor
Civil/Structure Engineer/Electric/ Machines
(Builders)
• To supervise during the construction
• As an advisor on site according to their
designated fields
Quantity Surveyor (Builders)
• Will evaluate the work at site according to
schedule to prepare progress payment
• Will evaluate corrected defect work
• Will make sure that all defects have been
repaired during the defects liability period
• Will prepare final account/cost
Contractor Organization Chart
Depends on Management
small @ big the Highest
project are
Supervisor /
Depends on
Medium technical
power and
firms
Lowest
Labors
Jurisdiction in Contractor Firm
Managing Director
Project Manager
Project Coordinator
Workers Workers
Example of contractor
Organization Chart
MANAGER
ADMINISTRATION TECHNICAL
PURCHASING PROJECT
GENERAL FINANCIAL
CONTRACTOR REGISTRATION
PROCEDURE AT CONSTRUCTION
INDUSTRY DEVELOPMENT BOARD
MALAYSIA (CIDB)
Category Expertise
CE Civil Engineering Works
B Building construction
ME Mechanical and Electrical
Contractor Service Centre
Pusat Khidmat Kontraktor (PKK)
A Exceeding RM10,000,000.00
HEAD SYSTEM (PKK)
TYPE JURISDICTION
HEAD I Civil Engineering Works
( Kerja Kejuruteraan Awam)
HEAD II Building Works
(Kerja Bangunan)
HEAD III Mechanical, Sanitary and Water Engineering Works
(Kerja Kejuruteraan Mekanikal, Kejuruteraan Pembersihan dan Kejuruteraan Air)
HEAD IV Other Specialist, Civil Engineering Works
(Lain-lain Kerja Kejuruteraan ‘Specialist’)