TRANSFORMER

OLEH
MOHD ZHAHIR B OTHMAN

Program Kejuruteraan Elektrik

10/25/2018 ITiDi 1
APA ITU TRANSFORMER
Sebuah alat elektrik yang boleh menaikkan
atau menurunkan voltan arus ulangalik atau
memindahkan kuasa dari satu litar ke satu
litar lain tanpa ada perubahan kepada
frekuensi

10/25/2018 ITiDi 2
PRINSIP ASAS
Energy can be efficiently transferred by
magnetic induction from one set of coils to
another set of coils by means of a varying
magnetic flux produced by an alternating
current

10/25/2018 ITiDi 3
CORE

P S

Vertical portion of the core is called LIMBS


Top and bottom portions are called the YOKES

10/25/2018 ITiDi 4
HOW IT WORKS
Coil P is primary winding connected to the
supply. Coil S is secondary winding and is
connected to the load. The AC voltage
applied to P circulate an alternating current
through the winding, and this current
produces an alternating flux in the core. If
the whole of the flux passes through S, the
emf induced in each turn is the same for P
and S
10/25/2018 ITiDi 5
10/25/2018 ITiDi 6
10/25/2018 ITiDi 7
Input = Output

V1 x I1 = V2 x I2

I2 = V1
I1 V2

10/25/2018 ITiDi 8
TRANSFORMER LOSS
• No Load Loss – histerisis loss and eddy
current loss, constant loss once voltage is
applied irrespective of load
• Load loss – copper loss or I²R loss (heat
loss), the amount of loss depend on the load
of the transformer

10/25/2018 ITiDi 9
TRANSFORMER EFFICIENCY
• It is expressed in percentage and equal to (output
in watts x 100) x (output in watts + total losses in
watts)
• Total losses consist of a fixed loss in the iron and
the copper loss which is proportional to I²
• The maximum efficiency is obtained when the
copper and iron losses are equal
• As copper loss at full load is typically equal to
four times the iron loss, then the maximum
efficiency is usually obtained at half load
10/25/2018 ITiDi 10
EFFICIENCY TABLE
kVA 1000 750 500 1000 750 500
P.F 1.0 1.0 1.0 0.8 0.8 0.8
Load (kW) 1000 750 500 800 600 400
Iron Loss 3.515 3.515 3.515 3.515 3.515 3.515
Cu Loss 11.6 6.52 2.9 11.6 6.52 2.9
Tot. Loss 15.11 10.03 6.415 15.11 10.03 6.415
Eff (%) 98.51 98.68 98.73 98.14 98.36 98.42
10/25/2018 ITiDi 11
KVA RATING
The power capacity of the Power
Transformer e.g 300kVA, 1000kVA,
2MVA etc.

10/25/2018 ITiDi 12
RATED VOLTAGE
Voltage between line terminals at the high
voltage side or the low voltage side such as
11,000/433 volt

10/25/2018 ITiDi 13
RATED CURRENT
Current flowing through a line terminal of a
winding, derived by dividing the rated
power of the winding and by an appropriate
power factor

10/25/2018 ITiDi 14
FREQUENCY

50Hz
60Hz

10/25/2018 ITiDi 15
TYPES OF COOLING
• AN (air natural) – dry type transformer
• ONAN (Oil Natural Air Natural)
• ONAF (Oil Natural Air Forced)
• OFAF (Oil Forced Air Forced)
• OFAN (Oil Forced Air Natural)

10/25/2018 ITiDi 16
IMPEDANCE VOLT %
The difference between the rated voltage of
a winding and the voltage developed at a
specified load and power factor, the voltage
supplied to the other winding being at its
rated value

10/25/2018 ITiDi 17
WINDING

Delta connected windings or Star connected


windings

10/25/2018 ITiDi 18
10/25/2018 ITiDi 19
VECTOR GROUP
• Dyn 11 (lagging by 30 degrees)
• Dyn 1 (leading by 30 degrees)

10/25/2018 ITiDi 20
CORE AND WINDING
WEIGHT

In kg or metric ton

10/25/2018 ITiDi 21
TRANSFORMER OIL
• Act as an insulant and thermal transfer
agent
• Mineral hydrocarbon oil to BS 148
• Sometimes synthetic liquids, called askarels
(pyroclor) are used instead of oil as they are
non-inflammable and non-explosive but
very expensive

10/25/2018 ITiDi 22
OIL WEIGHT

In kg

10/25/2018 ITiDi 23
OIL CAPACITY

In litre or gallon

10/25/2018 ITiDi 24
MAX TEMPERATURE RISE

The difference between the temperature of


part under consideration and the
temperature of cooling air – in degrees C

10/25/2018 ITiDi 25
SEALED TYPE TRANSFORMER

10/25/2018 ITiDi 26
SEALED TYPE TRANSFORMER

10/25/2018 ITiDi 27
TEMPERATURE
INDICATOR

10/25/2018 ITiDi 28
OIL IMMERSED
TRANSFORMER

10/25/2018 ITiDi 29
10/25/2018 ITiDi 30
FEEDER PILLAR OF COMPACT SUBSTATION

10/25/2018 ITiDi 31
TOP VIEW

10/25/2018 ITiDi 32
FEEDER PILLAR

10/25/2018 ITiDi 33
HERMETICALLY SEALED TRANSFORMER

10/25/2018 ITiDi 34
SEALED TYPE TRANSFORMER

10/25/2018 ITiDi 35
10/25/2018 ITiDi 36
TECHNICAL DATA 11/0.433kV Dyn 11

10/25/2018 ITiDi 37
TECHNICAL DATA 22/0.433kV Dyn 11

10/25/2018 ITiDi 38
TECHNICAL DATA 33/0.433kv Dyn 11

10/25/2018 ITiDi 39
TECHNICAL DATA 33/11KV

10/25/2018 ITiDi 40
TECHNICAL DATA 132/11KV

10/25/2018 ITiDi 41
TECHNICAL DATA OF EARTHING TRANSFORMER

10/25/2018 ITiDi 42
LARGE
TRANSFORMER

10/25/2018 ITiDi 43
10/25/2018 ITiDi 44
10/25/2018 ITiDi 45
EARTHING TRANSFORMER

10/25/2018 ITiDi 46
33/11KV TRANSFORMER

10/25/2018 ITiDi 47
33/11KV TRANSFORMER

10/25/2018 ITiDi 48
132/11KV TRANSFORMER

10/25/2018 ITiDi 49
132/11KV TRANSFORMER

10/25/2018 ITiDi 50
WINDING

10/25/2018 ITiDi 51
DRY TYPE TRANSFORMER

10/25/2018 ITiDi 52
DRY TYPE TRANSFORMER WITH
HOUSING

10/25/2018 ITiDi 53
10/25/2018 ITiDi 54
RING MAIN UNIT

TRANSFORMER

10/25/2018 ITiDi 55
COMPACT SUBSTATION

10/25/2018 ITiDi 56
COMPACT SUB-STATION

10/25/2018 ITiDi 57
10/25/2018 ITiDi 58
FEEDER PILLAR &
DISTRIBUTION BOARD
• 1600A, 10 fuseways
• 800A, 6 fuseways
• 400A outdoor mini feeder pillar, 6 nos
outgoing
• Transformer from 300 kVA to 1000 kVA

10/25/2018 ITiDi 59
STREET LIGHTING FEEDER
PILLAR
• 100A up to 6 ways 60A outgoing
• 50A single phase panel box/Meter

10/25/2018 ITiDi 60
NAME PLATE

Displays the transformer model specifications


for safe operation and maintenance of the
unit

10/25/2018 ITiDi 61
NAME
PLATE

10/25/2018 ITiDi 62
NAME PLATE
• kVA rating – 1000kVA
• Rated voltage, Rated current – 11/.433kV, 1600A
• Frequency – 50Hz
• Phase – 3 phase
• Winding – star or delta connected
• Type of cooling – ONAN
• Impedance volt (%) – 4%
• Vector group – Dyn 11
• Oil capacity – in liters
• Oil weight – in kilogram
• Max temperature rise – 40 degrees
• Tap changer – 5 taps or more
10/25/2018 ITiDi 63
10/25/2018 ITiDi 64
10/25/2018 ITiDi 65
RELIEVE
VALVE

10/25/2018 ITiDi 66
MAIN TANK

Metallic tanks to house the transformer


windings and transformer oil

10/25/2018 ITiDi 67
CONSERVATOR TANK
Smaller tank on top of the transformer
partially filled with transformer oil and the
rest filled with air. It is as an expansion area
for the oil when it is hot and also as a place
where oil level indicator and temperature
indicators are located – Hermetically sealed
transformers are without conservator tank

10/25/2018 ITiDi 68
CONSERVATOR TANK

COOLING FIN
10/25/2018 ITiDi 69
RADIATORS/COOLING FIN

Part of the transformer tank with a number of


small tubes where hot oil is passed through
for heat dissipation to the surrounding air

10/25/2018 ITiDi 70
COOLING
FIN

10/25/2018 ITiDi 71
CABLE TERMINATION/BOX
Where H.T and L.V cable are terminated
and closed for the purpose of safety and to
avoid enviromental disturbants, however
thesedays for indoor transformer some of
them are without cable box instead cable
termination are used

10/25/2018 ITiDi 72
10/25/2018 ITiDi 73
10/25/2018 ITiDi 74
LV & HV BUSHING

Insulating materials made of porcelain to


provide insulation between cable and cable
and also body of the transformer

10/25/2018 ITiDi 75
HV BUSHING

10/25/2018 ITiDi 76
LV BUSHING

10/25/2018 ITiDi 77
10/25/2018 ITiDi 78
HT
BUSHING
AND
SPARK
GAP

10/25/2018 ITiDi 79
DEHYDRATING BREATHER
To provide a passage for the flow of air in
and out of the transformer when the process
of expansion and contraction of transformer
oil and also to contain silica gel that absorb
moisture

10/25/2018 ITiDi 80
BREATHER

10/25/2018 ITiDi 81
CABLE BOX

BREATHER

OUTLET

10/25/2018 ITiDi 82
BREATHER

10/25/2018 ITiDi 83
TAP CHANGER
To increase and decrease output voltage. It is
on the high voltage side. Standard tap
changer consists of 5 tapping positions
(+5%, +2.5%, 0, -2.5%, -5% ) and can be
more than 5 tappings
Off load tap changer
On load tap changer (>33kV)

10/25/2018 ITiDi 84
TAP
CHANGER

10/25/2018 ITiDi 85
10/25/2018 ITiDi 86
10/25/2018 ITiDi 87
TAP CHANGER

10/25/2018 ITiDi 88
10/25/2018 ITiDi 89
WINDINGS
• Primary winding (inner side)
• Secondary winding (outer side)
• LV winding is in the form of copper plate
• Voltage/turn
• Ampere/turn

10/25/2018 ITiDi 90
OIL LEVEL GAUGE

To indicate the level of transformer oil


The level low when oil is cool
And high when the oil is hot

10/25/2018 ITiDi 91
OIL LEVEL
GAUGE

10/25/2018 ITiDi 92
TEMPERATURE GAUGE

To indicate the temperature of the winding

10/25/2018 ITiDi 93
TEMPERATURE
INDICATOR

10/25/2018 ITiDi 94
OIL TEMP GAUGE

To indicate the temperature of the oil

10/25/2018 ITiDi 95
THERMOMETER

10/25/2018 ITiDi 96
PRESSURE RELIEF VALVE
Safety pressure relief valve, the valve will
open when the pressure inside the
transformer tank exceed certain limit

10/25/2018 ITiDi 97
10/25/2018 ITiDi 98
BUCHHOLZ RELAY
A mechanical relay connected through pipe
and situated between main tank and
conservator tank of a transformer. Only
certain kVA transformer need to be installed
with one, normally above 1MVA. It will be
connected to the trip coil of the circuit
breaker controlling the transformer or the
installation
10/25/2018 ITiDi 99
BUCHHOLZ RELAY

10/25/2018 ITiDi 100


10/25/2018 ITiDi 101
COOLING FAN
For big transformers the natural air cooling no
more adequate especially during peak load.
The fan will force air to the cooling fin of
the transformer to expedite the removal of
heat from it

10/25/2018 ITiDi 102


OIL MOTOR PUMP
For oil force cooling method (OFAF), the
oil need a pump to make it circulate faster.
The electric pump normally getting single
phase supply from LV source

10/25/2018 ITiDi 103


COOLING SYSTEM
• AN – air natural
• ONAN – oil natural air natural
• ONAF – oil natural air force
• OFAF – oil force air force

10/25/2018 ITiDi 104


TRANSFORMER EARTHING
• Body/frame earth
• Star point earth
• Neutral earth

10/25/2018 ITiDi 105


10/25/2018 ITiDi 106
HIGH
VOLTAGE
BUSHING

10/25/2018 ITiDi 107


LOW
VOLTAGE
BUSHING

10/25/2018 ITiDi 108


HIGH
VOLTAGE
CABLE

10/25/2018 ITiDi 109


LOW
VOLTAGE
CABLE

10/25/2018 ITiDi 110


PARALLELLING OF
TRANSFORMER
• Same voltage ratio
• Same phase angle / Vector group
• Same percentage impedance
• Same polarity
• Same phase sequence

10/25/2018 ITiDi 111


10/25/2018 ITiDi 112
10/25/2018 ITiDi 113
10/25/2018 ITiDi 114
10/25/2018 ITiDi 115
10/25/2018 ITiDi 116
10/25/2018 ITiDi 117
10/25/2018 ITiDi 118
10/25/2018 ITiDi 119
10/25/2018 ITiDi 120
MAINTENANCE
If a transformer is to give a long and trouble
free service, it should receive a reasonable
amount of attention and maintenance. The
principle objective is to maintain the
insulation in good condition. Moisture, dirt
and excessive heat are the main causes of
insulation deterioration

10/25/2018 ITiDi 121


OIL
• General physical check for any sign of oil
leakage at gasket, radiator, tank,
conservator, pipes and valves
• If minor leakage, tighten bolts and nuts
• If leakage persist, have the leakage part of
the gasket replaced
• Oil in conservator tank should always be
kept at its maximum level indicated
10/25/2018 ITiDi 122
OIL TEST
• Dielectric test, should exceed 30kV average
• Acidity in oil is 0.5mg of KOH per gram of
oil, exceeding 1.00mg of KOH oil should be
changed immediately, 0.5 – 1.00mg is to
test again after a period of 3 months
• Or when chloroform – soluble sludge is
produced

10/25/2018 ITiDi 123


TEMPERATURE
• Normally a receptacle located at the
transformer main tank top is provided for a
thermometer to be placed into it. A period of
5 to 10 minutes should be allowed to
elapsed before reading is taken
• The maximum normal operating
temperature of the winding is 90 degrees C

10/25/2018 ITiDi 124


BUSHING

• Check for cleaniness and crack


• Check for leak at the bushing gasket
• Tighten nuts around bushing gasket if
necessary

10/25/2018 ITiDi 125


BREATHER
• Check the colour of the silica gel,
dehydrated silica gel is blue in colour, it
turns pink when hydrated, change new one
or heat it in an oven to dehydrated it
• Clean the breather if necessary
• Check the rubber of cork sheet gasket of the
breather
• Check the oil seal is kept at the correct level

10/25/2018 ITiDi 126


CONSERVATOR TANK

• Check the oil level, top up if necessary


• Oil gauge glass should be cleaned to enable
oil level to be seen clearly
• Check for any oil leakage

10/25/2018 ITiDi 127


OTHERS
• Clean name plate
• Repaint if necessary
• Check numbering if more than one
transformer in a room or sub-station
• Check both HT and LV cable termination
and support are good
• Clean transformer room, door, exhaust fan

10/25/2018 ITiDi 128


TESTING
• Ratio test
• Pressure test (HT side)
• Insulation test (HT and LV)
• Polarity test
• Open circuit test
• Short circuit test

10/25/2018 ITiDi 129


10/25/2018 ITiDi 130
10/25/2018 ITiDi 131
10/25/2018 ITiDi 132
10/25/2018 ITiDi 133
10/25/2018 ITiDi 134
TEST
RESULT

10/25/2018 ITiDi 135