Professional Documents
Culture Documents
QUIZ # 3
SUPERSTRUCTURES
State the difference between
QUESTION pre-tensioned and post-tensioned
#1 - #2 concrete.
Most joint of this type utilize a neoprene
QUESTION gland as the sealant.
#3
It protects the superstructure and
QUESTION structure elements from associated
#4 deterioration.
Designed to prevent cross sectional
QUESTION deformation of the superstructure
#5 frame.
The most popular material for
____________________ is extruded
QUESTION neoprene with an open cell cross
#6 section.
Type of deck that can be left open or
QUESTION filled with concrete, useful when light
#7 deck are desired.
From a design standpoint, this means
that a portion of the top of the slab is
QUESTION neglected for section properties
resisting loads.
#8
TRUE OR FALSE:
1 Pre-tensioned concrete:
The tendons are tensioned prior to pouring of concrete
2
Post-tensioned concrete:
Tendons are tensioned after the concrete has cured
3 Strip Seal Joint
ANSWERS 4
5
Wearing Surface
Secondary Members
6 Compression Seals
7 Steel Grid
9 True
10 1 in. or 25.4mm