Professional Documents
Culture Documents
3. The Contractor shall be responsible for the safety of all activities on the
Site.
4. The Contractor shall carry out all instructions of the Procuring Entity’s
Representative that comply with the applicable laws where the Site is
located.
8. The Contractor shall submit to the Procuring Entity for consent the name and
particulars of the person authorized to receive instructions on behalf of the
Contractor.
9. The Contractor shall cooperate and share the Site with other contractors,
public authorities, utilities, and the Procuring Entity between the dates given in
the schedule of other contractors particularly when they shall require access to
the Site.
FORM AMOUNT
CASH OR MANAGER’S CHECK 10 % of Contract Amount
BANK DRAFT/GUARANTEE 10 % of Contract Amount
SAMPLE COMPUTATION
AMOUNT OF UNFINSIHED WORK x 0.001 x NO. OF DAYS
Php 150,000.00 x 0.001 x 12 Days = Php 1800.00
SECTION 12. Contractor’s Risk and Warranty Security
1. The Contractor shall assume full responsibility for the Works from the
time project construction commenced up to final acceptance by the
Procuring Entity and shall be held responsible for any damage or
destruction of the Works except those occasioned by force majeure.
The Contractor may terminate this Contract with the Procuring Entity if the
works are completely stopped for a continuous period of at least sixty (60)
calendar days, due to the following;
2. Change Order
4. Variation Order beyond 10% but not more than 20% shall be subject of
another contract.
SECTION 43. SUSPENSION OF WORK
2. Contractor may suspend work 15 days after giving notice due to;
a. Right-of-Way problems
b. Adjusted Plans are not furnished by Implementing Agency.
c. Peace and Order conditions
d. failure of PE to furnished materials and equipment if any.
e. Delay in payment of Contractor 45 days after receipt/certified by
PE’s representative.
SECTION 47. EXTENSION OF CONTRACT TIME
50.TAKING OVER
The Procuring Entity shall take over the Site and the Works within seven (7)
days from the date the Procuring Entity’s Representative issues a
certificate of Completion
-END-