Project management plan presented by:

Hipolito, John Vincent


Nangit, Estarla Mae
Oriel, Regine Elizabeth
Relova, Mary Grace
Teves, Hillary Grace
VIDEO
• It is a perennial problem of the
college.
• It is incapable to obtain its function as
a comfort room.
• It cause hassle to students by waiting a
long queue before able to use it.
• Unhygienic and inconvenient to use.
• Can be a medium of transmissible
diseases because of uncleanliness.
• To obtain maximum sanitation and
perfect its function as comfort room.
• To promote hygiene and prevention of
transmissible infection.
• To lessen congestion and long queue
of students.
• To have a presentable comfort room
for general use.
Chapter 6 – “School
Sanitation and
Health Services” on
the Code on
Sanitation of the
Philippines
Chapter 6 – “School
Sanitation and
Health Services” on
the Code on
Sanitation of the
Philippines
Chapter 6 – “School
Sanitation and
Health Services” on
the Code on
Sanitation of the
Philippines
Pipelines fixed and
tiles replaced.

New urinals, sink,


toilet bowls installed.
Pipelines fixed and
tiles replaced.

New sink, toilet bowls


installed.
1. Siphoning of the Septic Tank
2. Declogging of pipelines in lavatories
3. Procurement and installation of toilet fixtures
including faucets, water closets and repair
doors of cubicles
4. Repair of ceiling
5. Repainting of walls and ceiling
6. Rewiring and repair of electrical installation
7. Replacement of old tiles
8. Cleaning and maintenance of comfort
rooms
• Replacing mirrors
• Replacing doors (cubicles)
• Procurement and Installation of vending
machines
ITEM SCO PE O F WO RK / DESCRIPTIO N Q TY UNIT UNIT CO ST TO TAL AMO UNT

1 WATER CLOSET,LAVATORY,URINALS & PIPELINE INSTALLATION


1.1 Materials: P P
PVC Solvent-atlanta 2.0 qrts @ 160.00 320.00
PVC pipe4"dia.x10ft s 600 -atlanta orange 10.0 pcs @ 300.00 3,000.00
PVC pipe2"dia.x10ft s 600 -atlanta orange 4.0 pcs @ 140.00 560.00
St. Coupling 1/2" dia.(brass) 8.0 pcs @ 200.00 1,600.00
PVC wye 4" dia.x2"dia atlanta orange 2.0 pcs @ 150.00 300.00
PVC wye 4"dia.-atlanta orange 6.0 pcs @ 155.00 930.00
PVC tee 4"diax2".atlanta orange 8.0 pcs @ 150.00 1,200.00
PVC tee 4"dia.atlanta orange 7.0 pcs @ 75.00 525.00
G.I. Tee 1/2" dia. shed.40 4.0 pcs @ 55.00 220.00
PVC p-trap 2' dia.atlanta orange 8.0 pcs @ 183.00 1,464.00
PVC plug 4"dia.atlanta orange 4.0 pcs @ 70.00 280.00
PVC wye 4"dia.x2"dia.atlanta orange 8.0 pcs @ 145.00 1,160.00
PVC elbow 2"dia. 90 deg.atlanta orange 2.0 pcs @ 60.00 120.00
PVC elbow 2"dia. 45 deg.atlanta orange 6.0 pcs @ 65.00 390.00
PVC elbow 4" dia.45deg atlanta orange 12.0 pcs @ 160.00 1,920.00
PVC elbow 4" dia.90 deg atlanta orange 10.0 pcs @ 160.00 1,600.00
Teflon 3/4" 10.0 pcs @ 40.00 400.00
Eslon blue tee 1/2' dia.plane moldex 16.0 pcs @ 52.00 832.00
Eslon blue elbow 1/2' dia.plane moldex 20.0 pcs @ 50.00 1,000.00
Eslon blue pipe 1/2"dia. x10 ft moldex 8.0 pcs @ 105.00 840.00
Eslon blue male adaptor 1/2'dia.moldex 16.0 pcs @ 45.00 720.00
Gate valve 1/2' dia. falcon 4.0 pcs @ 625.00 2,500.00
G.I. Elbow 1/2"dia. sched.40 16.0 pcs @ 145.00 2,320.00
Shower valve 1/2"dia. 2.0 pcs @ 450.00 900.00
Lavatory HCG white oval shape w/ complete accessories 4.0 sets @ 2,500.00 10,000.00
Water Closet HCG White w/ complete accessories 8.0 sets @ 3,000.00 24,000.00
Urinal whie 2.0 sets @ 2,000.00 4,000.00
PVC Solvent 2.0 qrt @ 125.00 250.00
concrete nail #2 1.0 kg @ 124.00 124.00
Material Cost……. 63,475.00
1.2 Labor: Labor Cost………. 25,390.00
Direct Cost…… 88,865.00
ITEM SCO PE O F WO RK / DESCRIPTIO N Q TY UNIT UNIT CO ST TO TAL AMO UNT
2 PAINTING WORKS OF WALL:
2.1 Materials:
Latex paint semi-gloss White 3.0 gal @ 575.00 1,725.00
Latex paint flat White 3.0 gal @ 580.00 1,740.00
Roller brush w/ tray 1.0 set @ 90.00 90.00
Enamel paint-caramel brown 1.0 gal @ 600.00 600.00
Paint Brush # 2 1.0 pc @ 40.00 40.00
Paint Thinner 1.0 Gal @ 499.00 499.00
Painters pallette 1.0 pair 34.00 68.00
Spatula 1.0 pc 40.00 80.00
Material Cost……. 4,842.00
2.2 Labor: Labor Cost………. 1,936.80
Direct Cost…… 6,778.80
3 TILE WORKS REPLACEMENT:
3.1 Materials:
Glaze tiles .40x.40 m. white 375 pcs @ 85.00 31,875.00
4"Ǿ Circular Diamond Cutter 2 pc. @ 380.00 760.00
Masonry Trowel 2 pcs @ 150.00 300.00
Portland Cement 10 bags @ 285.00 2,850.00
Fined Sand 2 cum. @ 1,655.00 3,310.00
Screened sand 2 cum. @ 1,500.00 3,000.00
Material Cost……. 42,095.00
3.2 Labor: Labor Cost………. 16,838.00
Direct Cost…… 58,933.00
4 ELECTRICAL WORKS
4.1 Materials:
Flourescent bulb w/ complete accessories 4.0 sets @ 600.00 2,400.00
Electrical tape-big 1.0 roll @ 45.00 45.00
Material Cost……. 2,445.00
4.2 Labor: Labor Cost………. 978.00
Direct Cost…… 3,423.00
ITEM SCO PE O F WO RK / DESCRIPTIO N Q TY UNIT UNIT CO ST TO TAL AMO UNT
5 REPAIR & PAINTING WORKS OF
5.1 Materials:
1/4" marine plywood 10.0 pcs @ 520.00 5,200.00
cwn # 1 1.0 kg @ 85.00 85.00
Glazing putty 1.0 gal @ 645.00 645.00
Sanding Paper # 100 1.0 pcs @ 95.00 95.00
Enamel Paint flat white 3.0 gal @ 595.00 1,785.00
Enamel Paint semi-gloss white 3.0 gal @ 600.00 1,800.00
Roller brush w/ tray 1.0 set @ 90.00 90.00
Paint brush # 3 2.0 pcs @ 85.00 170.00
Material Cost……. 9,870.00
5.2 Labor: Labor Cost………. 3,948.00
Direct Cost…… 13,818.00

Total Material Cost 122,727.00


Total Labor Cost 49,090.80
Total Direct Cost 171,817.80