RUNNING PREVENTIVE MAINTENANCE

OF HT MOTORS-DRI-SMP-E&I-1-03

SPM OF HT MOTORS-DRI-SMP-E&I-1-04
SAFETY PRECAUTION & OHS RISK-
RPMI
 No loose clothing
 Do not touch any rotating part of the
equipment.

OHS Risk-Personal Injury


SAFETY PRECAUTION & OHS RISK-
SPMI
 Electrical Shock because of static charge.
 Personal injury due to mishandling of
parts.

OHS Risk
 Ensure Positive isolation by
operations
 Take Electrical isolation of motor.
 Obtain Safe work permit
Maintenance Procedure-RPMI
Pre-Requisite

 work permit

 Clean motor body (Don’t overreach for cleaning)


Maintenance Procedure-RPMI
INSPECTION CHECKS

 Motor, Power JB, LCS earthing

 Abnormal sound

 Abnormal Vibration
Maintenance Procedure-RPMI
TEMPERATURE CHECKS

 DE/NDE side bearing

 Motor Body

 Cables
Maintenance Procedure-RPMI
ADDITIONAL CHECKS

 Monsoon protection

 water flow and leakage of radiator


(Where Applicable)

 lube oil flow and leakage (Where Applicable)


Maintenance Procedure-RPMI
JOB CLOSURE

 House keeping of Area

 Work Permit Closure


Maintenance Procedure-SPMI
Pre-Requisite

 work permit

 LOTOTO - Lock out-Tag out-Try out

 ROTOR StandStill

 Clean motor body (Don’t overreach for


cleaning)
Maintenance Procedure-SPMI
INSPECTION CHECKS

 Start -> Activate local emergency

 Inspect for Crack/Damages

 Grease nipples & its cleanliness


Maintenance Procedure-SPMI
INSPECTION CHECKS

 Bearing lube oil system-


1) Flow
2) Leakage
3) Cleanliness
Maintenance Procedure-SPMI
INSPECTION CHECKS

 Cooling water system-


1) Flow
2) Leakage
3) Cleanliness
Maintenance Procedure-SPMI
INSPECTION CHECKS

 Cooling Fan & Fan Cover

Remove Dust, Rust, Oil, Grease


Maintenance Procedure-SPMI
INSPECTION CHECKS

ELECTRICAL
Maintenance Procedure-SPMI
INSPECTION CHECKS – Electrical

CACA
Maintenance Procedure-SPMI
INSPECTION CHECKS – Electrical

TEFC
Maintenance Procedure-SPMI
INSPECTION CHECKS – Electrical

CACW
Maintenance Procedure-SPMI
INSPECTION CHECKS – Electrical

Discharge Rod Rubber Gloves Insulated shoes


Maintenance Procedure-SPMI
INSPECTION CHECKS – Electrical

PSTB Spaced Terminal Box


Maintenance Procedure-SPMI
INSPECTION CHECKS – Electrical

 Cable & Motor to be discharged

 Check the terminal studs & terminal connectors


(TB & star point )

 Terminal bushing/bushing plate for damage due


to cracks, excessive carbonization etc.
Maintenance Procedure-SPMI
INSPECTION CHECKS – Electrical

 Signs of moisture
 Loose connection
 Space heater cable
 RTD/BTD cable
Maintenance Procedure-SPMI
INSPECTION CHECKS – Records

 Winding resistance
 Inductance
Maintenance Procedure-SPMI
ADDITIONAL CHECKS

Monsoon protection

1. Space Heater Terminal Box


2. RTD/BTS Terminal Box
3. Local Control Box
4. Power JB
5. Cable glands having top & side cable
entry.
Maintenance Procedure-SPMI
JOB CLOSURE

 House keeping of Area

 Work Permit Closure

 Return of Isolation Permit


Maintenance Procedure-Panel
Maintenance Procedure-Panel
Maintenance Procedure-Panel
Maintenance Procedure-Panel
Maintenance Procedure-Panel