Professional Documents
Culture Documents
COMPONENTS OF COFFERDAM
Presented by
1304081- Swagata Dasgupta
1304085 - Samiha Rabbani
1304090 - Obaidul Islam
1304104 - Shams Razzak Rothe
Cofferdam
Temporary Structure
Excludes earth and water
2
Material Stresses
1. Overall Stability
Risk occurs in –
Sloping ground
Riverfront cofferdam
Where the differential height is greater
Where cohesive soils extend to considerable depths on sloping sites
Material Stresses
To prevent-
The cofferdam should be tied
Adequate sluices with safe locations for operating locations
Material Stresses
c) Scour Protection
Circular Cofferdams
General Layout of the Cofferdam
Sheeting
Waling
Struts
12
Principle Reasons for Failure
Poor Inadequate
workmanship strut section
Inadequate Allowance of
embedment surcharge
13
Ground Anchors
Soil strengths
Wall and soil stiffness
Anchor spacing
Anchor yield
Prestress locked into the anchors
Ground Anchors
Type A
Type B
Type C
Type D
Type E
Ground Anchors
Overall stability
Depth of embedment
Fixed anchor dimensions
Group effects
Components of Braced Cofferdam
Sheet pile
Bracing
1. Waling
2. Passive Anchorage
3. Struts
18
Figure 4
Sheet Piling
19
Bracing
Waling
Necessity
Load Transfer:
Continuity
• Diaphragm Walls
• Secant Piles
20
Waling (cont.)
Connections Waling
Special Considerations
• For inclined struts
• For anchors
• For diagonal struts
Figure 5
21
Size of Walling
22
Size of Walling (cont.)
23
Passive Anchors
Design Principal
Net available passive pressure= passive pressure-active pressure
Special Considerations
i) Surcharge ii) Friction
Materials
i) Mild steel - 111N/mm2
ii) High yield steel -140 N/mm2
Passive Anchors (cont.)
Protection:
To avoid effect of fill settlement
To avoid corrosion
Struts
A strut is a component designed to resist
longitudinal compression.
Importance
The most likely collapse
mechanism of a braced
cofferdam is the buckling of
it’s strutting.
Struts cont.
Reasons of Failure:
Passive failure below formation level
Extreme loading
Poor workmanship
Positioning the strut
Struts should be supported by
welding steel location angles to
end plate prior to bolting.
Struts are square to the wallings
in plan to avoid eccentric loading.
As precaution check 10% of strut
width or depth in each direction.
Spacing
The vertical spacing of the struts depend on both the strut capacity and the
flexural strength of the walling.
Spacing (cont.)
The minimum frame spacing must be sufficient to allow mechanical
excavation plant to pass under the frame prior to placing the next lowest
frame.
Final stages of construction
Several means-
Cellular cofferdam for new construction
Raking struts to the dock floor to exclude water from
the existing dock
Driving sheet piles to a circular arc in plan for the
existing entrance
Cost of temporary cofferdams
Design curves
Gravity structure
Consists of twin parallel
lines of sheeters
Driven below dredge line
Tied together by steel tie
Filled with material
Usual height to width
ratio 0.8
Berm inside for drainage
and stability
36
Factors Affecting Stability
37
Modes of Failure Considered in Design of Double
Wall Cofferdam
38
Sliding:
Resistance to sliding provided by
Passive resistance of soil
Shear strength of sheeters
Frictional resistance of filler
material
39
Overall stability
40
Alternative method:
A minimum factor of safety( ratio of overturning and
resisting moment) 1.5
41
Measures to protect scouring on outside
face
Placing rock or precast concrete blocks against outer
face
Laying grouter mattresses on the river bed
Lateral deformation at the head of cofferdam is
eliminated by using strongpoints
42
THE END