Professional Documents
Culture Documents
Explained
Keith Klesner
Senior Vice President North America
Uptime Institute
1
The Global Data Center Authority
2
Summary
• What is the Tier Certification Process?
• The vast majority of data centers do not
perform as designed on day one.
• What are the common mistakes or
deficiencies that lead to project failures?
• How can companies prepare for project
success when considering a Tier and
Operations Certification?
3
Tier Classification System vs Tier Certification
5
Why Tier Certification?
With multiple vendors,
subcontractors, and typically
more than 50 different
disciplines involved in any
data center project—
structural, electrical, HVAC,
plumbing, fuel pumps,
networking, and more—it
would be remarkable if there
were no errors introduced or
corner cut during the
construction process.
6
Tier Certification: How it Works, Part 1
Data Center Owner Defines Tier
Requirement
Uptime Institute reviews design
documents, ensuring that each
and every electrical, mechanical,
monitoring, and automation
subsystem meets the Tier
objective requirements.
Uptime Institute reports findings to
the owner, noting any deficiencies.
The owner’s team revises the
drawings to address any
deficiencies.
7
Tier Certification: How it Works, Part 2
8
Benefits of Tier and Operations Certification
• Ensures data center facilities investment meets
business requirements
• Enterprise—Recognizes organizational
accomplishment
• Service Providers – Use for competitive
differentiation and supporting tenant due
diligence
• Operations certification addresses the human
factor and drive continuous improvement
9
1000+ Certifications in over 80 Countries
10
New data from surveys and field reports
Outages and errors are still rampant
12
Recent Analysis of 200+ Tier Certifications:
• Uptime Institute Consultants found system
faults in nearly every Tier Certification site visit.
• The vast majority of data center sites do not
operate as designed/installed on day one.
• Data center owners comment that the Tier
Certification demonstrations were more rigorous
than their commissioning program.
• Tier Certification is a failsafe against a data
center that doesn’t work day 1, or worse in year
5.
13
There is a data center somewhere…
14
What goes wrong
Avoiding common points of project failure
16
Ensure adequate commissioning
• Time and budget must be dedicated to a full
commissioning program
• Representative load banks should be installed
in the data center for the design IT load
• Test power and cooling together to ensure that the data
center operates as designed in all specified maintenance and
failure scenarios.
• All equipment and systems should be functioning as
specified, and changes from the design intent should be
minimal and insignificant.
17
Operation focus is key to long-term success
• Integrate operations concept as part of the project
planning and design process
• Involve operations staff to influence design and
learn from commissioning
• Follow industry Operational Sustainability model
• Don’t underestimate value of regular assessment
and certification to acknowledge operations drive
continuous improvement
18
Conclusions
• There are more ongoing Tier Certifications
today than at any point in history.
• The vast majority of even the world’s most
elite data center sites do not operate as
designed/installed on day one.
• Tier Certification is achievable if you follow
Uptime Institute’s guidance.
19
Thank you
20