UMM LULU PHASE II FULL FIELD DEVELOPMENT PROJECT

PACKAGE 2 – UMM LULU SUPER COMPLEX AND SUBSEA


COMPOSITE POWER CABLES

START-UP SEQUENCE
05-December-2016
TECHNIP ABU DHABI
05-DEC-2016 AL BUSTAN TOWER
UMM LULU PHASE II FULL FIELD DEVELOPMENT PROJECT
PACKAGE 2 – UMM LULU SUPER COMPLEX AND SUBSEA
COMPOSITE POWER CABLES

Agenda

1. OBJECTIVES
2. START-UP SEQUENCE
3. PRE-REQUISITES
4. STEP 1 - BRINGING MAIN POWER GENERATOR (GTG) ONLINE
5. STEP 2 - PREPARING FOR WELL FLUID INTRODUCTION
6. STEP 3 - WELL FLUID INTRODUCTION
7. STEP 4 - SWITCHING TURBINES TO FUEL GAS FIRING
8. STEP 5 - START UP OF GAS INJECTION COMPRESSORS
9. STEP 6 - START-UP OF REMAINING FACILITIES

TECHNIP ABU DHABI


2 05-DEC-2016 AL BUSTAN TOWER
UMM LULU PHASE II FULL FIELD DEVELOPMENT PROJECT
PACKAGE 2 – UMM LULU SUPER COMPLEX AND SUBSEA
COMPOSITE POWER CABLES
1. OBJECTIVES

• TO ENSURE THAT ALL HARDWARE ARE PROVIDED TO HAVE A


PROPER START-UP SEQUENCE

• REVIEW MAIN STAGE OF START-UP SEQUENCE

TECHNIP ABU DHABI


3 05-DEC-2016 AL BUSTAN TOWER
UMM LULU PHASE II FULL FIELD DEVELOPMENT PROJECT
PACKAGE 2 – UMM LULU SUPER COMPLEX AND SUBSEA
COMPOSITE POWER CABLES
2. START-UP SEQUENCE

Step 1
• BRINGING MAIN POWER GENERATOR (GTG) ONLINE

Step 2
• PREPARING FOR WELL FLUID INTRODUCTION

Step 3
• WELL FLUID INTRODUCTION

Step 4
• SWITCHING TURBINES TO FUEL GAS FIRING

Step 5
• START UP OF GAS INJECTION COMPRESSOR

Step 6
• START-UP OF REMAINING FACILITIES

TECHNIP ABU DHABI


4 05-DEC-2016 AL BUSTAN TOWER
UMM LULU PHASE II FULL FIELD DEVELOPMENT PROJECT
PACKAGE 2 – UMM LULU SUPER COMPLEX AND SUBSEA
COMPOSITE POWER CABLES

Legend
• Step 1
• Step 2
• Step 3
• Step 4
• Step 5

TECHNIP ABU DHABI


5 05-DEC-2016 AL BUSTAN TOWER
UMM LULU PHASE II FULL FIELD DEVELOPMENT PROJECT
PACKAGE 2 – UMM LULU SUPER COMPLEX AND SUBSEA
COMPOSITE POWER CABLES
3. PRE-REQUISITE
1) Make sure that Main Diesel Storage Tank and the diesel day tanks of the Emergency Diesel
Generators are filled with diesel.

2) EDG DC power available from EDG Charger/Batteries.

TECHNIP ABU DHABI


6 05-DEC-2016 AL BUSTAN TOWER
UMM LULU PHASE II FULL FIELD DEVELOPMENT PROJECT
PACKAGE 2 – UMM LULU SUPER COMPLEX AND SUBSEA
COMPOSITE POWER CABLES
4. STEP 1 - BRINGING MAIN POWER GENERATOR (GTG) ONLINE
1) Start LQ Emergency Diesel Generator (564-GEN-2028) using EDG Charger/Batteries to
supply power to ULAP facilities.
a) Start and make all LQ essential / support systems operational
b) Start and make all control and safety systems operational

2) Start UTP Emergency Power Generator (566-GEN-2029/2030) on diesel using EDG


Charger/Batteries to supply power to required users in ULSC:
a) Start the Start-up Air Compressor Package to supply instrument to critical users and
valves located in ULAP and ULUTP (Flare line & Diesel line).
b) Start and make all remaining essential utilities and support systems (lighting, HVAC …)
in Utility Platform operational. (see note a)
c) Start and make all control and safety systems operational
d) Supply emergency power to essential users at WHTs.
e) Start Diesel Transfer Pumps and make diesel supply available at the B/L of Gas
Turbine Generators (566-GEN-2031/2032/2033). (see note b)
f) Ensure auxiliaries of one selected GTG (e.g. lube oil system, fans …) are ready to start,
which is supplied from emergency switchboard
TECHNIP ABU DHABI
7 05-DEC-2016 AL BUSTAN TOWER
UMM LULU PHASE II FULL FIELD DEVELOPMENT PROJECT
PACKAGE 2 – UMM LULU SUPER COMPLEX AND SUBSEA
COMPOSITE POWER CABLES

4) Start selected GTGs on diesel to supply power to all the normal load of the complex and
essential/auxiliaries loads of the selected Gas Lift Compressor / Turbine driver.

5) Stop ULUTP Emergency Power Generators and LQ Emergency Diesel Generator.

At this stage, one main Power Generator (GTG) is online and supplying to all
electrical
consumers in the ULSC and WHTs.

Note :
a) Valves at closed drain pump discharges up to MOL pipeline are provided with volume
bottles which can be used to empty closed drain drum inventory.
b) Valves on diesel supply lines to Fire water pumps and EDG are provided with Volume
tanks which ensure diesel supply to critical items.

TECHNIP ABU DHABI


8 05-DEC-2016 AL BUSTAN TOWER
UMM LULU PHASE II FULL FIELD DEVELOPMENT PROJECT
PACKAGE 2 – UMM LULU SUPER COMPLEX AND SUBSEA
COMPOSITE POWER CABLES
5. STEP 2 - PREPARING FOR WELL FLUID INTRODUCTION
1) Start one main Air Compressor Package and one Instrument Air Dryer Package to generate
dry compressed air, and stop the Start-Up Compressor.

2) Start Nitrogen Generation Package and line up the supply of nitrogen to the main users, e.g.
compressor seals, purge of flare system and ensure removal of Oxygen.

3) Light up the flare using propane cylinders.

4) The drain system in RP / SP / GTP to be ready.

5) Ensure auxiliaries of MOL Pumps and GLC Compressor and turbine driver are Ready to be
started

6) Pressurization of GLC Compressor


a) Line up N2 connection to 3rd stage Suction of one GLC train and start pressurizing 3rd
and 4th stage with Nitrogen

7) Start hot oil circulation pump through the WHRU of selected GLC train and through the
controllability bypass. ( FV1052 – PID 16598)
TECHNIP ABU DHABI
9 05-DEC-2016 AL BUSTAN TOWER
UMM LULU PHASE II FULL FIELD DEVELOPMENT PROJECT
PACKAGE 2 – UMM LULU SUPER COMPLEX AND SUBSEA
COMPOSITE POWER CABLES
6. STEP 3 - WELL FLUID INTRODUCTION
1) Line up one Production Separator train.

2) Start selected production wells (preferably sweet wells) at WHTs and gradually pressurize
the system up to inlet of Production Separator (bypass MOV 2101 – PID 12505).

3) Gradually introduce well fluid into one Production Separator.


Pressure and level will build up in the Separator and Produced Gas Scrubber.
There will be continuous flaring from the Production separator (PV2004 – PID 12507).

4) Once level is built-up, start one MOL pump in full recycle, line up the system to
route crude oil to Zirku and start sending crude oil to MOL.

5) Produced water system connected to MOL pump suction also to be lined-up.

TECHNIP ABU DHABI


10 05-DEC-2016 AL BUSTAN TOWER
UMM LULU PHASE II FULL FIELD DEVELOPMENT PROJECT
PACKAGE 2 – UMM LULU SUPER COMPLEX AND SUBSEA
COMPOSITE POWER CABLES
6) Pressurize up to MOV 2051 –PID 16507 and flare through PV-1244 ½, and then close
PV2004 –PID 12507

7) Pressurize GLC 1st/2nd stage using gas through bypass of MOV2051.

8) Start Gas Lift Compressor and turbine driver:


a) Start GLC turbine on diesel firing
b) Start GLC Compressor at minimum speed and in full recycle on all stages (all anti-
surge valves open)

9) Start warming up of hot oil through the WHRU of selected GLC train and through the
controllability bypass. ( FV1052 – PID 16598)

10) Start glycol circulation across GDU Contactor bypass


When hot oil is warm enough (T=165 °C), start circulating hot oil through GDU
reboiler. Open ESDV 2021 – PID 16567.

TECHNIP ABU DHABI


11 05-DEC-2016 AL BUSTAN TOWER
UMM LULU PHASE II FULL FIELD DEVELOPMENT PROJECT
PACKAGE 2 – UMM LULU SUPER COMPLEX AND SUBSEA
COMPOSITE POWER CABLES
11) Introduce gas to GDU – Open MOV2051 and line up wet gas to GDU keeping PV2900
open to Flare.
Increase GT speed manually and pressurize GLC following Compressor and GDU vendor
recommendations such as ramp-up rate ( At low speed maximum pressure reached during
this step is around 28 barg).
Keep PV2900 open until GDU dry gas specification is reach.

12) Introduced Dry gas to GLC 3rd and 4th stage using bypass of MOV-2054and displace
nitrogen through PV-2042-1/2 keeping ESDV-2012 PID 16506 closed.

13) Master Performance Controller of the Compressor can now be put in auto mode.

14) Pressurization of Gas Lift pipeline (including bridge line from ULGTP downstream 576-
ESDV-2012) to be carried out in advance by utilizing gas from outlet of GDU contactor.
Through the kicker line up to GDU pressure (62 Barg).

TECHNIP ABU DHABI


12 05-DEC-2016 AL BUSTAN TOWER
UMM LULU PHASE II FULL FIELD DEVELOPMENT PROJECT
PACKAGE 2 – UMM LULU SUPER COMPLEX AND SUBSEA
COMPOSITE POWER CABLES

15) Pressurization of Gas Lift pipeline (including bridge line from ULGTP downstream
576-ESDV-2012) to be carried out in advance by utilizing gas from outlet of GDU
contactor. Through the kicker line up to GDU pressure (62 Barg) using bypass MOV-
2058.

16) Open 576-ESDV-2012 when :


a) pressure is equalized between upstream & downstream of ESDV-2012.
Pressure control using PV-2042/1&2,
b) WHT’s are ready to receive Gas Lift.

17) Bypass of GSU to feed Flare Pilot & Flare Header purging

TECHNIP ABU DHABI


13 05-DEC-2016 AL BUSTAN TOWER
UMM LULU PHASE II FULL FIELD DEVELOPMENT PROJECT
PACKAGE 2 – UMM LULU SUPER COMPLEX AND SUBSEA
COMPOSITE POWER CABLES
7. STEP 4 - SWITCHING TURBINES TO FUEL GAS FIRING
1) Start the Gas Sweetening Unit (start Lean Amine Pumps to allow amine circulation across the
GSU Absorber.)

2) Start circulating hot oil through GSU – ESDV1004 –PID 16557

3) Route part of the gas from 2nd Stage of GLC to GSU Inlet Scrubber FV1001/1&2 in manual
mode.

4) Start pressurizing GSU Absorber with gas from GLC. Depending on the wells lined-up (sweet or
sour wells), gas may be required to be flared until on spec. using 3” vent line or DBV after H2S
analyzer.
a) The manual valves at the GSU outlet to FGCU-UTP and FGCU-GTP needs to be closed.

5) Once the gas is on-spec, pass it through the fuel gas electric heater by pressurizing the gas
flowing to UTP and GTP FGCUs.
a) Pressurization will be by means of bypass across manual valve for the line going to UTP
FGCU. Start warming up of the gas by keeping the warm-up line open XV2283 at the inlet of
Gas Turbine.
b) Once the set temperature is reached, initiate change-over from diesel to fuel gas of the
turbine. 05-DEC-2016
TECHNIP ABU DHABI
14 AL BUSTAN TOWER
UMM LULU PHASE II FULL FIELD DEVELOPMENT PROJECT
PACKAGE 2 – UMM LULU SUPER COMPLEX AND SUBSEA
COMPOSITE POWER CABLES
8. STEP 5 - START UP OF GAS INJECTION COMPRESSORS
1) Increase platform throughput by increasing well production at WHT or lining up additional wells

2) Stonewall protection valve (FV2006/2 PID 16546) shall be closed and in manual mode.

3) Start pressurization of GI pipeline using Dry gas from GDU up to GDU pressure (62 barg) using
bypass MOV2058.
MOV-1184 & ESDV-1024 PID 11522 – shall be closed.

4) Start pressurizing Gas Injection Compressor up to Gas Lift Compressor 4th stage discharge
pressure using bypass XV2175 PID 16544 and start GIC on full recycle.

5) Once WHTs are ready to receive injection gas, line up the discharge of GIC to the Gas Injection
Pipeline by slowly opening the Stonewall protection valve FV 2006/2 to pressurize up to MOV-
1184, and when pressure equalize open MOV-1184 and then ESDV-1024 .

6) Once the pressures on pipeline side and compressor discharge are almost equalized, switch
the compressor control to auto mode.
TECHNIP ABU DHABI
15 05-DEC-2016 AL BUSTAN TOWER
UMM LULU PHASE II FULL FIELD DEVELOPMENT PROJECT
PACKAGE 2 – UMM LULU SUPER COMPLEX AND SUBSEA
COMPOSITE POWER CABLES
9. STEP 6 - START-UP OF REMAINING FACILITIES

Once main power generation is operating on fuel gas firing, the remaining facilities,
i.e. fresh water making, water injection systems can be started.

Sequence of startup for these systems will be provided in a dedicated startup procedure and
Operating Manuals, once more data are available from Vendors.

TECHNIP ABU DHABI


16 05-DEC-2016 AL BUSTAN TOWER
UMM LULU PHASE II FULL FIELD DEVELOPMENT PROJECT
PACKAGE 2 – UMM LULU SUPER COMPLEX AND SUBSEA
COMPOSITE POWER CABLES

Thank you….

TECHNIP ABU DHABI