You are on page 1of 16

 Brickworks is an important part of construction and

modern building practice. Usually brick wall is built


totally on site. More workers and materials need in
completing the brick wall on site.
 In calculation, brick work shall be measured in square
metre and stating the thickness of the wall, type of
brick, type of bond and composition and proportion of
mortar. The unit price per square metre of brick wall is
calculated based on the following:
 Materials cost which is brick and mortar. Also brick
reinforcement (normally for half brick wall)
 Labour cost
 Overhead cost and profit
 Standard brick size – 215 mm length x 102.5 mm width x
65 mm thick
 Brick is bonding with mortar
 There are two type of brick :
• Clay brick
• Cement brick
 Calculation of quantities of brick for 1 m2 half brick wall :
No. of brick/m2 wall = 1000 mm x 1000 mm = 59.26
= 60no.
225 mm x 75 mm
(+) 5 % wastage = 3 no.
Total = 63 no.
Description Mortar (m3) Number of brick
(No.)

½ Brick wall 0.025 63


1 Brick wall 0.050 125
1 ½ Brick wall 0.075 188
BRICK REINFORCEMENT
 The composite material of mortar is cement,
fine aggregate (sand) and water.
 Mortar proportion of cement and sand (1:3),
(1:4) and (1:6)
 Some additive such as lime is use as a retarded
agent.
 Mortar proportion of cement, lime and sand is
1:1: 6
 Shrinkage, Wastage and Consolidation for
mortar – 33.33% or 1/3 of materials shall be
added
Description Bricklayer Worker
(hour/m2) (hour/m2)

½ Brick wall in common 1.00 0.35


brick
1 Brick wall in common brick 1.75 0.70
½ Brick wall in facing brick 2.00 0.50
1 Brick wall in facing brick 3.50 1.00

Labour output/labour constant


Cement, lime and sand mortar (1:1:6). – m3
Data :
 Lime cost = RM3.50/bag (10 kg)
 1 m3 lime = 400 kg = 40 bag
 Labour wages = RM 40/day
 Labour constant =2 hours/m3
a. Material cost
1 m3 cement = 28 bag x RM10.50 RM 294.00
1 m3 lime = 40 bag x RM3.50 RM 140.00
6 m3 sand = 6 x RM30.00 RM 180.00
+) shrinkage, consolidation & wastage RM 614.00
1/3 x RM614.00 RM 204.67
Material Cost for 8m3 RM 818.67
Material cost/m3 = RM 818.67 RM 102.33
8 m3
b. Labour cost
Labour = 2 hour x RM 40.00 RM 10.00
8 hour
Price Rate/m3 Mortar RM 112.33
 Half
brickwork in common bricks in cement lime
and sand mortar (1:1:6) in Stretcher bond with
brick reinforcement at every forth course, non-
load bearing. – m2

Assumption :
Common brick cost - RM0.24/No.
Brick Reinforcement - 3.50 m/m2 brick wall ; RM0.60/m
Labour output :
Bricklayer - 1.00 h/m2
Worker - 0.35 h/m2
Profit & overhead cost- 15 %
a. Material cost
Brick = 63 nos. x RM0.24 RM 15.12
Mortar = 0.025 m3 x RM112.33 RM 2.81
Brick reinforcement =
3.50 m x RM0.60 RM 2.10 RM 20.03
b. Labour cost
Bricklayer = 1.00 hr x RM 60.00 RM 7.50
8 hour
Worker = 0.35 hr x RM 40.00 RM 1.75 RM 9.25
8 hour RM 29.28
c. Profit & Overhead cost
15 % x RM 29.28 RM 4.39
Price Rate/m2 RM 33.67
One brickwork in common bricks in cement mortar (1:3) in English
bond, load bearing. – m2
Data:
 Cement cost = RM12.50/bag
 Sand cost = RM45/m3
 Labour wages = RM 40/day
 Labour output for mixing mortar = 2 hours/m3
 Common brick cost - RM0.24/No.

Labour output :
 Bricklayer - 2.50 h/m2 ; RM70 / day
 Worker - 0.45 h/m2
 Profit & overhead cost - 15 %
Price Rate / m3 = RM72.12
One brickwork in clay bricks in cement mortar (1:4) in English bond,
load bearing. – m2
Data:
 Cement cost = RM17.50/bag
 Sand cost = RM45/m3
 Labour wages = RM 45/day
 Labour output for mixing mortar = 2 hours/m3
 Clay brick cost - RM0.50/No.
 No.of bricks - 125/m2
 Quantity of mortar - 0.05m3/m2

Labour output :
 Bricklayer - 2.50 h/m2 ; RM70 / day
 Worker - 0.70 h/m2
 Profit & overhead cost - 15 %

You might also like