You are on page 1of 43

1

 OUTLINE
 Site Features
 Site Preparation
 Setting out

BUILDING CONSTRUCTION , BY MELAKU M. 1/2/2018


2

 Construction site work includes clearing, grading, and


preparing the site for built features like roads, utilities,
buildings, parking lots, and the site drainage system.
 Initial clearing and grading work on a site requires
attention to a fairly common set of general goals
 Planning the clearing, grubbing, and site preparation
work is necessary, especially for larger sites.
 Written plans even very basic one help to ensure that
everyone understands where the active work zones
are,various activity phases, and the schedule
BUILDING CONSTRUCTION , BY MELAKU M. 1/2/2018
3

 Physical features: these are permanent objects or


features existing with in the site or adjoining sites which
are used for referencing or identification of the site.
 Ex. Existing buildings, trees, roads, fences, etc.
 Elevations: these are the different heights on the
surface of the site in relation to a standard reference
point known as the bench mark (BM) Locations which
have equal elevations are joined together using contour
lines.
 These lines help to define the topography of the land
within a site.
BUILDING CONSTRUCTION , BY MELAKU M. 1/2/2018
Cont’d…
4

 Site orientation: these refers to a system of


defining the site in terms of its direction to the north,
south, east and west.
 Orientation is important in planning the building
area to make into consideration such factors as the
direction of rain, wind and sun within the site.

BUILDING CONSTRUCTION , BY MELAKU M. 1/2/2018


5

 Minimize site disturbance to preserve and maintain


existing vegetative cover.
 Limit the number of access points to the site to
control off-site mud tracking
 Phase and sequence construction activities by
dividing the project into logical work zones

BUILDING CONSTRUCTION , BY MELAKU M. 1/2/2018


6

 Locate temporary and permanent soil disposal


areas, haul roads, and construction staging areas to
minimize erosion, sediment transport, and
disturbance to existing vegetation

BUILDING CONSTRUCTION , BY MELAKU M. 1/2/2018


7

 Operations that remove vegetation such as clearing


and grubbing and reshape the surface of the land
through excavation or placement of fill material.

 Land grading serves to construct designed site


drainage features, achieve site grades necessary
for construction of roads, buildings, parking lots,
and other site features.
BUILDING CONSTRUCTION , BY MELAKU M. 1/2/2018
8

 :
To build up the proposed building at the exact
place/spot and also as a guide for excavation
and building construction.

BUILDING CONSTRUCTION , BY MELAKU M. 1/2/2018


9

 The main aim of setting out is to ensure that the


various elements of the scheme are positioned
correctly in all three dimensions.

BUILDING CONSTRUCTION , BY MELAKU M. 1/2/2018


10

 In order that the design of the scheme can be


correctly fixed in position, it is necessary to establish points
on the site which the E, N coordinates are known.
 These are horizontal control points and, once they have been
located they can be used with a positioning technique to set out
E, N coordinates of the design points.
 Two factors need to be taken into account when establishing
horizontal control points.
 The control points should be located throughout the site in order
that all the design points can be fixed from at least two or three
of them so that the work can be independently checked.
 The design points must be set out to the accuracy stated in the
specifications

BUILDING CONSTRUCTION , BY MELAKU M. 1/2/2018


CONT’D…
11

 The accuracy must be obtained throughout the whole network


and this can be achieved by establishing different levels of
control based on one of the fundamental tenets of surveying:
working from the
 In practice, this normally involves starting with a small number
of very accurately measured control points (known as first level
or primary control) which enclose the area in question and then
using these to establish second level or secondary control
points near the site.
 When establishing the control network care needs to be taken
that the tolerances specified are met.

BUILDING CONSTRUCTION , BY MELAKU M. 1/2/2018


CONT’D…
12

 An example if working from the whole to the part


using two different levels of control are shown in the
next diagram. In this, the first level of control is
provided by a traverse which is run through the site
in question to provide a number of well positioned
primary control points.
 These in turn are used to establish a second level of
control, in this case secondary site points at each of
a series of baselines which define important
elements of the scheme.

BUILDING CONSTRUCTION , BY MELAKU M. 1/2/2018


13

BUILDING CONSTRUCTION , BY MELAKU M. 1/2/2018


CONT’D…
14

 Horizontal control points should be located as near


as possible to the site in open positions for ease of
working, but well away from the construction area
and traffic routes to avoid them being disturbed.
 The construction and protection of control points is
very important.
 Wooden pegs are often used for non-permanent
stations.
 For permanent control points it is recommended that
they be constructed with concrete – as shown below.
BUILDING CONSTRUCTION , BY MELAKU M. 1/2/2018
15

BUILDING CONSTRUCTION , BY MELAKU M. 1/2/2018


Baselines
16

 A baseline is a line running between two points of a


known position. Any baselines required to set out a
project should be specified on the setting out plan
by the designer and included in the contract.
 Baselines can take many forms: they can be simply
two specified points joined, they can run between
two buildings, they can mark the boundary with an
existing building/development or they can mark the
centre line for a new road.

BUILDING CONSTRUCTION , BY MELAKU M. 1/2/2018


17

 Baselines can be used in a number of different


ways:
 Where a baseline is specified to run between two
points then once the points have been established
on site, the design points can be set out from the
baseline by offsetting using tapes (as seen below).

BUILDING CONSTRUCTION , BY MELAKU M. 1/2/2018


18

BUILDING CONSTRUCTION , BY MELAKU M. 1/2/2018


19

 A design point D is to be set out at right angles to a


baseline AB from point C which lies at a distance y
from point A. The required offset distance from C to
D is x. Distances x and y will be given by the designer
and will usually be horizontal distances.
 Primary site control points, such as traverse stations
E & F in the figure below can be use to establish a
baseline AB by angle and distance l values.

BUILDING CONSTRUCTION , BY MELAKU M. 1/2/2018


20

BUILDING CONSTRUCTION , BY MELAKU M. 1/2/2018


21

 Subsidiary offset lines can then be set off at right


angles from each end of the baseline to fix two corners
R and S of building Z.
 Once R and S have been pegged out, the horizontal
length of RS is measured and checked against its
designed value. If it is within the required tolerance,
points R and S can be used as a baseline to set out the
corners T and U.
 Design points can be set out by taping known as
distances from each end of a baseline as shown below
BUILDING CONSTRUCTION , BY MELAKU M. 1/2/2018
22

BUILDING CONSTRUCTION , BY MELAKU M. 1/2/2018


23

 At point A on building X is set out by taping


dimensions 1 and 2 from the baseline and point B
by taping dimensions 3 and 4.
 As before, the set out lengths of AB is then checked
against its designed value and within tolerance, it
can be used as a baseline to set out corners C and
D.

BUILDING CONSTRUCTION , BY MELAKU M. 1/2/2018


24

 Outline
 Introduction
 Functions Of Foundation
 Essential Requirements Of Foundation
 Types Of Foundation
 Shallow Foundation
 Deep Foundation
 Excavation For Foundation

BUILDING CONSTRUCTION , BY MELAKU M. 1/2/2018


25

 A foundation should be sufficiently strong to prevent


excessive settlement as well as unequal settlement.
 Unequal settlement or differential settlement may
be caused by:
 Weak sub-soils, such as made up ground,
 Shrinkable and expansive soil (such as clay),
 Frost action,

BUILDING CONSTRUCTION , BY MELAKU M. 1/2/2018


26

 Movement of ground water, and uplift pressure


 Excessive vibrations, due to traffic, machinery etc.,
 Slow consolidation of saturated clays, and
 Slipping of strata on sloping sites.

BUILDING CONSTRUCTION , BY MELAKU M. 1/2/2018


27

BUILDING CONSTRUCTION , BY MELAKU M. 1/2/2018


28

BUILDING CONSTRUCTION , BY MELAKU M. 1/2/2018


29

BUILDING CONSTRUCTION , BY MELAKU M. 1/2/2018


30

BUILDING CONSTRUCTION , BY MELAKU M. 1/2/2018


31

BUILDING CONSTRUCTION , BY MELAKU M. 1/2/2018


32

BUILDING CONSTRUCTION , BY MELAKU M. 1/2/2018


33

BUILDING CONSTRUCTION , BY MELAKU M. 1/2/2018


34

BUILDING CONSTRUCTION , BY MELAKU M. 1/2/2018


35

BUILDING CONSTRUCTION , BY MELAKU M. 1/2/2018


36

BUILDING CONSTRUCTION , BY MELAKU M. 1/2/2018


37

BUILDING CONSTRUCTION , BY MELAKU M. 1/2/2018


38

BUILDING CONSTRUCTION , BY MELAKU M. 1/2/2018


39

BUILDING CONSTRUCTION , BY MELAKU M. 1/2/2018


40

BUILDING CONSTRUCTION , BY MELAKU M. 1/2/2018


41

BUILDING CONSTRUCTION , BY MELAKU M. 1/2/2018


42

BUILDING CONSTRUCTION , BY MELAKU M. 1/2/2018


43

BUILDING CONSTRUCTION , BY MELAKU M. 1/2/2018

You might also like