Professional Documents
Culture Documents
MANAGEMENT
M. Tech. (PLE)
SEM II
10 February, 2017
Project Management - Modules
2
1 4
2 Project 3 Project
Foundation Life Cycle Initiation
Stakeholder
Concepts Management
5 7 Project 10 Project
6 Project Quality
Organization Scope
Planning Management
Structures Management
8 Project 12 Project
11 Project 9 Project
Time Executing,
Risk Cost
Management Monitoring &
Management Management
Control
14
13 Communicatio 15
16 Project
Procurement Behavioural
ns Closing
Management Management Competencies
RKM 2013 11/29/2017 7:42 AM
TIME MANAGEMENT
3
After the WBS has been developed, the work packages have to
be further decomposed into all the activities necessary to
complete the work package.
Define activities
Sequence activities
Estimate activity resources
Estimate activity durations
Develop schedule
What is an activity:
Past records
Expert judgment
Analogous estimates
Quantitative estimates
IDENTIFICATION - ID
DESCRIPTION / NAME
DURATION
INTERRELATIONSHIPS
Finish to Start
from task to task
A B
Finish Start
Start to Start
A
from task
Start
B to task
Start
Finish to Finish
A
from task
Finish
B to task
Finish
In a FS relationship B has a
Lead of 1 day
B
Time Units
Time Units
Time Units
26
Start
B
4
1 A 3 C
2 7 G
D
F
E
5 6 8
Finish
A B C
Start Finish
D E F
The early start and early finish times for each activity
The earliest time of completion of the project
The late start and late finish times for each activity
The float available for each activity
The critical path and the critical activities.
Perform the forward pass and calculate the early start and
early finish time for all activities
Perform the backward pass and calculate the late start and
late finish for all activities
Calculate the total float for all activities
Highlight the path from start to finish connecting activities
with zero float.
1. Draw the Network, determine the project duration, and the critical
path
2. List out all activities with total float, free float and their values
RKM 2013 36 11/29/2017 7:42 AM
NETWORK EXERCISE - 1 Answer
MOST
ACTIVITY OPTIMISTIC LIKELY PESSIMISTIC MEAN STD. DEV. VARIANCE
A 27 30 33
B 24 30 72
C 12 30 36
A 12 15 30 17 3 9
(12+60+30)/6 (30-12)/6
B 15 30 45 30 5 25
C 45 60 69 59 4 16
106 7 (approx) 50
A+B+C (Sq. Rt of
50)