Professional Documents
Culture Documents
Week 22-1
(lecture 2)
What technical work should be done during each phase of the life cycle.
Cost and staffing levels are low at the start, higher toward the end, and
drop rapidly as the project draws to a conclusion.
In the next 3 slides, we will see three (3) possible views of the
stages a project goes through (eg for a butterfly pupae stage
to larvae stage & finally to butterfly stage)
Last Updated:8 September 7
2017
PROJECT LIFE CYCLE View 1
Inception Feasibility
Strategy
Pre-
construction
Construction
Engineering services
commissioning
Source : CIOB
Completion/handover,
client occupation &
Operation
Post-
completion
review
8 September 2017 8
Last Updated:8 September 2017 LMS SEGi education group
Not to Scale 8
TIME SCALE AND COST IN THE CONTEXT OF THE PROJECT LIFE CYCLE
Inception Feasibility
Before Construction
Phase
Strategy
Pre-
construction
Construction
Engineering services
commissioning
Construction
Phase Completion/handover,
client occupation &
Operation
Post-
completion
review
1) Project Conception
2) Project Development
3) Project Realisation
We use this view of the project life cycle to look at what are the
activities carried out in each of the stage.
project
development
realisation
termination
After Burke
Parties and Roles played in a Project
1.0 Parties in Project :
The Sponsor,
the Owner,
The Designers,
The Contractor,
Parties and Roles played in a Project
2.0 Project Roles :
The Sponsor as investors / financiers of
project,
The Owner as owner & operator of built
project,
The Designers Provision of design, supervision,
cost estimation, payment certification to
contractor and consulting services to the
owner/sponsor
The Contractor Build project according to
drawings by Designers
Project Sponsor/ Project Director
1) The Sponsor is, or is a Responsibilities
senior representative of, Approve business case
the investment decision Ensure that it remains valid
taker. throughout project life
2) The Sponsor ensures that To terminate the project if it
the basis of project does not remain valid
approval is consistent with
their organisations Appoint by Owner
business aims. Authorise funding allocation
3) The Sponsor represents Approve project definition
the commitment of senior
management to the
project - this is
demonstrated by the
provision of organisation
resources (money, people,
time, equipment etc)
The Sponsor allocates funds - but that funding might
originate from a number of sources
Project Manager representing the
Owner / Project Sponsor
Each project must have an Responsibilities
Project Manager. to produce the projects
The Project Manager business case (often the source
writes the project specification of the original idea), and seek
defines the result, the timing budget allocations from
and how project completion Sponsor
will be achieved. to ensure the project is defined
champions the project to the in sufficient detail to enable
Sponsor successful management
is accountable to the Sponsor to establish progress reporting
for the progress of the project
procedures
has day to day liaison with the
consultants and contractors to approve changes
can be a committee to accept the result
Project
Manager Project
The Project Mgr
Manager
doesnt exist in
People who
isolation contribute People who
to project contribute
to project
The accompanying
information should include
all necessary background
Information
Everything should be
written down or recorded,
even if the record states
things that appear obvious.
Project Scope or Scoping the Project
(More details on this topic can be found in the references available in the
library)
Using the WBS OBS link shown in the previous slide, we can then identify
the type of persons and skills required for the project.
WBS Work Breakdown Structure
OBS Organisation Breakdown Structure (eg project team organisation
structure)