Substation 1 Energization

SUBSTATION -SS 1

Energization of Substation include the power up of :

5.5KV MV Switch Board 141A-SB-301

400V LV Essential Switch Board 141A-SB-321

Definition 400V LV Normal Switch Board 141A-SB-311

400V LV GTG Auxiliary Switch Board 141A-SB-341


SUBSTATION -SS 1

Layout
SUBSTATION -SS 1

SLD
SUBSTATION -SS 1

Activity Description Duration Start Finish


Foundations ready for Module Support Erection 31-May-16
Module Support Erection (including alignment & bolt tightening) 15 1-Jun-16 16-Jun-16
Cable Tray Support Erection 8 9-Jun-16 16-Jun-16
Cable Tray Erection 5 16-Jun-16 21-Jun-16
Module Erection & Alignment 8 21-Jun-16 29-Jun-16
Module Interconnection (Gasket & bolting of modules) 19 30-Jun-16 19-Jul-16
HVAC Duct Interconnection including scaffolding 12 19-Jul-16 31-Jul-16
E&I Inter-module Cables (coiled & one side terminated by
Renco) /Bus bars Interconnection (Pull back, laying on cable tray,
Schedule for dressing & termination) Renco (LV-396 runs & 20953 m) 20 19-Jul-16 7-Aug-16
FM 200 Inter-modular Piping Interconnection 12 28-Jul-16 9-Aug-16
Installation VESDA Inter-modular Piping Interconnection 12 28-Jul-16 9-Aug-16
Bust Duct Installation (TR to SWGR) Total 44 m 20 19-Jul-16 7-Aug-16
Installation of Loose supplied mandatory modules/panels plus
available phase 2 panels (refer slide 9) 9 23-Jul-16 1-Aug-16
Panel to Panel External Interconnection Cabling Works not laid &
terminated by Renco (MV 53 runs 2325 m, LV 168 runs & 8475 m) 31 23-Jul-16 22-Aug-16
Casting of foundations & Installation of 4 nos. of Air Condenser
Unit (HVAC) along with Piping/Cabling works 46 21-Jun-16 5-Aug-16
Earth Pit (10 nos., 3.6 m each) Installation & Drilling works
including NER of EDG 8 25-May-16 2-Jun-16
Grounding cable works (Approx. 350m) 8 17-Jul-16 25-Jul-16
SUBSTATION -SS 1
Additional Activities for Phase1 ( Using EDG ) Duration Start Finish
Foundations for Auxiliaries (Diesel Day Tank, NER, Air
Compressor & Receiver) 37 13-May-16 18-Jun-16
Installation of Auxiliaries (Diesel Day Tank, NER, Air
Compressor & Receiver, Batteries, F&G Panel, CO2 Bottle
Panel, Muffler & Handrails, Beacon/Sounder) 28 28-May-16 24-Jun-16
UG Piping works Completion 12 20-May-16 1-Jun-16
EDG associated Piping (Fuel & Air) works Completion 26 1-Jun-16 26-Jun-16
E&I Trenching works Completion (Buried & RCC) -
Substation 1 to EDG (25m Buried trench from SS1 to ERC-
003 & 35m RCC trench from ERC-003 to EDG) 20 25-Jun-16 14-Jul-16
Schedule for E&I Cabling works including termination (MV 6 runs, 1.08
Installation km, LV 41 runs, 7.29 km) 19 15-Jul-16 3-Aug-16
SUBSTATION -SS 1

EQUIPMENT TAG EQUIPMENT DESCRIPTION VENDOR Supplier Phase ETA @ Site


NO.
141A-CP-302 Emergency Diesel Generator Control Panel ENERCON Cummins 1 At Site

1419-K-101A-TR MV VSD Transformer for Export ABB MDT 2 30-Jun


Compressor-A (1419-K-101A)
1419-K-101B-TR MV VSD Transformer for Export ABB MDT 2 30-Jun
Compressor-A (1419-K-101B)

Loose 141A-VSD-101A MV Variable Speed Drive (VSD) for Export


Compressor-A (1419-K-101A)
ABB MDT 2 30-Jun
Supplied 141A-VSD-101B MV Variable Speed Drive (VSD) for Export ABB MDT 2 30-Jun
Modules/ Compressor-B (1419-K-101B)
Panels to be 141A-SB-313A Motor Control Center (MCC) for Export Kohl MDT 2 30-Sep
Compressor-A (1419-K-101A) Auxiliary
Installed Loads
141A-SB-313B Motor Control Center (MCC) for Export Kohl MDT 2 30-Sep
Compressor-B (1419-K-101B) Auxiliary
Loads

141A-SB-314A Motor Control Center (MCC) for Kohl MDT 2 30-Sep


Re-generation Compressor-A (1414-
K101B) Auxiliary Loads

141A-SB-314B Motor Control Center (MCC) for Kohl MDT 2 30-Sep


Re-generation Compressor-A (1414-
K101B) Auxiliary Loads

141B0-T-TE-DTN-007 Telecom Cabinet Commtel Commtel 2 15-Aug

Phase 1 Power up of Substation


Phase 2 Field Equipment Energization (Utility & Off sites)
SUBSTATION -SS 1

Expedite delivery of Electrical Cable Gland Materials (Delivery by 30-Jul-


2016) - Ashok
Temporary Generators with Diesel Tank (To be mobilized from ISG by
15-Jul-2016) Romen/Ramesh
Gland Plate Drilling - LEAD
Pre- Certified MV Cable Jointers LEAD by 01-Aug-2016
Requisites &
Supports Foundation for ACU of HVAC - LEAD
Expedite delivery of Refrigerant for HVAC (Delivery by 15-Aug-2016 with
ARH Approval) - Ashok
ARH Pre-requisite documents Paresh / Ashok / Abraham
Precast of earth pit encasement, Earthing Pit Installation & Grounding
works LEAD (Including Marconite procurement)
SUBSTATION -SS 1

Eyewash Facility - Ashok


FM200 Dump Test (ARH Witness) - Paresh
MV Cables & Transformers Tests (ARH Witness) Paresh / Abraham
MV SWGR Test (ARH Witness) Paresh
Pre-requisites /Identification & Actions required for ARH Approval
Pre- Paresh/Ashok/Abraham
Requisites &
Supports Vendor mobilization prior to Power Up Ashok /Abraham
Renco/HVAC
Renco/FM 200
Schneider/SWGR
ETACOM/Bus duct
Cummins/EDG (For option 1)
Fence for Transformer
Construction A ITR closure Construction/QC
SUBSTATION -SS 1

Mounting Support bolt holes to be physically checked wrt to casted


foundation : Issam Jbara/ Ricardo
No: of inter-module termination including laying & dressing (Time to be
assessed) Ashok/Kale
Assess the manpower requirement for concluding the time period for
Pre- activities Ramesh/Suresh
Requisites &
Supports John Hajjar & Nadar Joseph to be mobilized by 30-Jun-2016 Ashok
Bus duct support details (design, procurement, fabrication)
Kale/Ashok
Technical Workshop at SHJ with Electrical & Commissioning
Kale/Ashok & Romen Shah
Check resources & equipment required for installation of panels &
erection of other items Ramesh
SUBSTATION -SS 1

Scope and availability of temporary Gensets (500 KVA x 2) for phase 2 to


be checked with LEAD Ashok

Pre-
Requisites &
Supports