VELIGONDA PROJECT

1. Teegalem Canal (48.15 km) 62,000 Ac


2. EMC (199 km) 2,45,000 Ac
3. Udayagiri Canal 52,000 Ac
In fall 4. West Branch Canal 51,000 Ac
Regulator 5. Supplementation 27,500 Ac
Nallamalasagar TOTAL 4,38,000 Ac
FRL +244.00m
Approach Cap. 53.85 TMC
Channel
100 m
PACKAGE-2 Teegaleru Canal Peddi Reddipally
(27.33 cumecs) Reservoir
Foreshore of Flood Flow Canal 48.15 km FRL +188m
Srisailam Tunnel Sunkesula Gap62000 Ac Cap. 2.023 TMC
Reservoir 328 Cumecs Gottipadia Gap(PACKAGE-
MDDL +834 ft 18.80 km 3)
FRL +885 ft 23.20 km Kakarla GapEastern Main Canal
BL +842 ft
Link km 24.45 2,45,500 Ac Udayagiri
PACKAGE-1
Channel Branch Canal
9.6 km PACKAGE-4 199 km 17.5 km
Lift I
Turimella Reservoir0.00 52000 Ac
FRL +235 m
GB Reservoir Cap. 2.453 TMC
FRL +254.5 m Lift II
Cap. 0.415 TMC Western
Branch Canal
Lift III (51,000 Ac)
Under progress

Racherls Tank Western


FRL +237.3 m Canal
22.70 km
VELIGONDA PROJECT
Project Profile: Kollamvagu foreshore on Right bank of Srisailam Reservoir near Markapur,
1
Prakasam District
2 Administrative Sanction : G. O. Ms No. 120, Dt: 9-7-04 for Rs. 765 Crs.
and G. O. Ms. No. 164, Dt: 8-10-2004 for
Rs. 469.49 Crs for Sunkesula & Gottipadiya
Gaps.
3 No. of EPC Packages : 4 No
4 Agreement value of 4 packages : Rs.1465.90 Crs.
5 Budget provision for 2006-07 : Rs.289.50 Crs.
6 Expenditure of the project
2004 05 : Rs. 41.77 Crs.
2005 06 : Rs. 175.80 Crs.
Cum. Exp. : Rs. 217.57 Crs
7 Utilisation :
Ultimate
Utilisation : 43.50 TMC
Ayacut : 4,38,000 acres
Phase I
Utilisation : 14 TMC
Drinking Water : 4 lakh population
8 Ayacut Ayacut : 1,19,000 acres
9 Land Acquisition
Required : 11,453 acres
Requisitioned : 11,195 acres
Acquired : 2,920 acres
10 Forest land : 3621 acres of land identified and handed over
to forest department for compensatory
afforestation.
11 Area under Submergence of : Stage I Ultimate stage
the project (in acres)
Forest : 3621 6426
Govt. : 4673 9953
Patta : 6780 29990
Total : 15074 46369
No. of families likely to be Stage I Ultimate stage
:
displaced
: 2504 2848
Estimated Cost of LA (Phase
12 : Rs.112.00 Crs.
I)
13 Estimated Cost of R & R : Rs. 332.62 Crs.
14 Clearances : Site clearance accorded.
Environmental clearance proposal
15 Mob. Advance (Rs. in Crores) : Paid Recovered
2004-05 : 31.66 --
2005-06 : 72.90 8.38
Total : 104.56 8.38
16 Target date of completion : 8/2008
VELIGONDA PROJECT

CATEGORY-I

PK Bid Agreemen
Amount Period of
GN Description Name of Contractor t
completion
O Rs. in Crs. concluded
Tunnel,
M/s Sabir-SEW-Prasad
1 Approach 624.60 20-08-2005 36 Months
(JV)
channel
Feeder channel,
M/s. Gayatri-
2 Sunkesula Dam, 254.50 09-11-2004 30 Months
Jayaprakash (JV)
tegaleru canal
Gottipadia gap, M/s Lareson & Turbo
3 380.00 08-11-2004 30 months
Gottipadia canal Ltd
Kakarla Dam,
4 Eastern Main M/s SCL-BSCPL (JV) 206.80 20-08-2005 36 Months
Canal

TOTAL 1465.90
VELIGONDA PROJECT

Pkg.No. 1 : Construction of Tunnel from Name of the Contractor : M/s.


SABIR,SEW&PRASAD(JV)
TBM from Kollamvagu in the foreshore of
Agreement Amount : Rs. 624.60 Crs.
Srisailam Reservoir up to Guntur Kurnool
road including construction of head regulator, Agreement Date : 20-08-2005
approach channel, exit channel. Period of completion : 36 Months (12 milestone
Target date of completion : 8/2008

Investigation : in progress

Designs : yet to be started

Execution : Yet to be started

Expenditure : 2005-2006 - Rs. 31.45 Crs. (Inc. Mob. Advance)

Land Acquisition : Required 65.86 Acres, Acquired 45.86 Acres

Bottlenecks : Forest clearance is awaited


VELIGONDA PROJECT

Pkg.No. 2 : Closing of Sunkesula Gap, Name of the Contractor : M/s. Gayatri-Jayaprakash (J


excavation of feeder channel and Agreement Amount : Rs. 254.50 Crs.
Teegaleru canal including construction of Agreement Date : 09-11-2004
CM & CD works and distributary system Period of completion : 30 Months (10 milestone
for 62,000 Ac.
Target date of completion : 8/2007

Investigation : Completed

Designs : yet to be started

Execution : in progress

Qty. of earth work done : 55,000 cum against 61,10,000 cum.

Expenditure : 2004-2005 - Rs. 12.73


Crs.
2005-2006 - Rs. 42.76 Crs.
Cum. Exp. Inc. Mob. Adv. only - Rs. 55.49 Crs.

Land Acquisition : Required 6317 Acres, Acquired 378 Acres


VELIGONDA PROJECT

Pkg.No. 3 : Closing of Gottipadia Gap Name of the Contractor : M/s. Larsen & Toubro
Ltd.,
and excavation of Gottipadia canal
including construction of CM & CD Agreement Amount : Rs. 380.00 Crs.
works and distributary system for 9500 Agreement Date : 08-11-2004
Ac. Period of completion : 30 Months (10 milestone
Target date of completion : 8/2007
Investigation : Completed

Designs : in progress

Execution : in progress

Qty. of EW done : 369829.22 cum against 326250 cum

Qty. of concrete work done : 52,653 CuM against 108958 CuM.

Expenditure : 2004-2005 - Rs. 18.93 Crs.

2005-2006 - Rs. 55.30 Crs.

Cum. Exp. Inc. Mob. Adv. only - Rs. 74.23 Crs.

Land Acquisition : Required 3899.02 Acres, Acquired 1303.28 Acres


VELIGONDA PROJECT
Pkg.No. 4 : Closing of Kakarla Gap by Name of the Contractor : M/s. SCL BSCPL (JV)
Agreement Amount : Rs. 206.80 Crs.
construction of NOF dam, excavation of Agreement Date : 20-08-2005
link canal and part of eastern canal Period of completion : 36 Months (12 milestone
together with distributary system Target date of completion : 8/2008
including CM & CD works for 47,500
Ac.
Investigation : 18.90 Km length against 53.26 Km

Designs : in progress

Execution : Yet to be started

Qty. of earth work done : 35,000 cum against 86,350 cum

Expenditure : 2005-2006 - Rs. 17.80 Crs. (Inc. Mob.


Advance)

Land Acquisition : Required 2716.56 Ac., Acquired 171.45 Ac.

Tunnel : Decision has to be taken for the ultimate stage i.e, 2nd tunnel
of 9.2 M dia are increasing the existing tunnel of 7
M dia to 11 M dia.