Professional Documents
Culture Documents
Project Scheduling
PERT/CPM
PERT and CPM can be used to plan, schedule, and control a wide variety of
projects:
1. Research and development of new products and processes.
2. Construction of plants, buildings, and highways.
3. Maintenance of large and complex equipment.
4. Design and installation of new systems
A path is a sequence of connected nodes that leads from the Start node to
the Finish node.
One path for the network in Figure is dened by the sequence of nodes A
EFGI.
Other possible paths are ADGI, ACHI, and BHI.
All paths in the network must be traversed in order to complete the project.
So we will look for the path that requires the most time (Critical time).
Because all other paths are shorter in duration, this longest path (Critical
path) determines the total time required to complete the project.
If activities on the longest path are delayed, the entire project will be
delayed.
Thus, the longest path is the critical path.
Activities on the critical path are referred to as the critical activities for the
project.
After we complete the forward and backward passes, we can determine the
amount of slack associated with each activity. Slack is the length of time an
activity can be delayed without increasing the project completion time. The
amount of slack for an activity is computed as follows:
Calculate the slack time for each activity by:
Slack = (Latest Start) - (Earliest Start), or
= (Latest Finish) - (Earliest Finish).
Immediate Completion
Activity Description Predecessors Time (days)
A Initial Paperwork --- 3
B Build Body A 3
C Build Frame A 2
D Finish Body B 3
E Finish Frame C 7
F Final Paperwork B,C 3
G Mount Body to Frame D,E 6
H Install Skirt on Frame C 2
Activity ES EF LS LF Slack
A 0 3 0 3 0 (crit.)
B 3 6 6 9 3
C 3 5 3 5 0 (crit.)
D 6 9 9 12 3
E 5 12 5 12 0 (crit.)
F 6 9 15 18 9
G 12 18 12 18 0 (crit.)
H 5 7 16 18 11