You are on page 1of 21

BACHELOR OF QUANTITY SURVEYING (HONS)

BLD 60204 CONSTRUCTION TECHNOLOGY II

TUTORIAL PRESENTATION
Q8

SECTION 3 | GROUP 1
1
Differences between end bearing & friction
pile
DIFFERENCES BETWEEN END BEARING & FRICTION PILE
compare
End Bearing Pile Friction Pile
DIFFERENCES BETWEEN END BEARING & FRICTION PILE

End Bearing Pile Friction Pile


These piles are used to transfer load through water or soft These piles are used to transfer loads to a depth of a
soil to a suitable bearing stratum. friction load carrying material by skin friction along the
length of pile.

Known as floating pile where the toes of the pile do not


The bottom end of the pile rests or penetrate on a layer of rest or penetrate into the firm layer of high bearing
strong soil or rock. (Supported by hard strata) capacity soil which is too deep inside the ground. (Not
supported by hard strata)

The load of the building is transferred to the adjoining


The load of the building is transferred through the pile soil by skin friction between the surface of the pile and
onto the hard strata, and also receive lateral restraint soil, which in effect lowers the bulb of pressure. In other
from subsoil. In a sense, this pile acts like a column. words, the entire surface of the pile is works for
transferring the forces to the soil.
DIFFERENCES BETWEEN END BEARING & FRICTION PILE

End Bearing Pile Friction Pile


Load Bearing Resistance derived mainly from base.
Load Bearing Resistance derived mainly from skin friction.

Develop most of their friction at the toe of the pile, bearing on Develop most of the pile bearing capacity from the shear
a firm layer. stresses along the sides of pile, and are suitable where harder
layer are too deep.
2
Process of precast
piles
PROCESS OF PRECAST PILES

Precast construction is considered quick compared to cast in situ


construction as it can be installed immediately and there is no waiting for
it to gain strength.
Driven precast piles are constructed by hammering the pile into the
ground by pile driving plant.
Piles of timber, pre-stressed concrete and steel are also used in this
method.

Shoe to ease
driving
PROCESS OF PRECAST PILES
1
Positioning of the prefabricated
pile

2
The pile is driven into the soil
with an impact pile driving
hammer (diesel hammer or
hydraulic drop hammer).
Special timber packing or a
synthetic cushion block lends
adequate protection to the pile
during driving.

3 & 4
With control of driving achieved
by measuring the set, the pile is
driven into the resistive soil
layer to a depth equal to one
time the pile diameter.
PROCESS OF PRECAST PILES

Sectional Precast Concrete Piles

Different founding levels

Reduce the section length

Ensuring minimum waste and a


safer working environment
3
Advantages of Continuous Flight
Auger
ADVANTAGES OF CFA

Low Vibrations and noise


Quick installation
Economical
Can see soil conditions
Casing not required
Can be installed in a batter
Can be installed in low headroom
4
Manufacturing process of
reinforced concrete piles
MANUFACTURING PROCESS OF REINFORCED CONCRETE PILES
1. Raw material preparing
- steel bar & wire
2. Steel bar cage making
3. Concrete feeding
- the specially formulated high strength concrete is placed into the bottom half of the mold
4. Case covering & Bolt tightening
- the mold is bolted closed
5. Steel bar tensioning
6. Rotary molding
- level 1-7 for 11 minutes
- the mold is spun at a high rate, the centrifugal force compresses the concrete against the
inner wall of the mold
7. Steam chamber
- curing for 12 hours
8. Demolding case

Video :
https://www.youtube.com/watch?v=yOhgMpk9Zu4
5
Precaution measure when
placing concrete through
tremie pipe
PRECAUTIONS WHEN PLACING CONCRETE THROUGH TREMIE PIPE

The pile should be concreted wholly by tremie and the method of


deposition should not be changed part way up the pile
to prevent laitance from being entrapped within the pile

Concrete should be placed in sufficient quantity


to ensure that during withdrawal of the tube, a sufficient head
of concrete is maintained to prevent the in-flow of soil and
water or bentonite slurry.

The top of the concrete in a pile shall be brought above the cut-off level
to allow removal of all laitance and weak concrete before
capping
to ensure good concrete at the cut off level for proper
embedment into the pile cap
PRECAUTIONS WHEN PLACING CONCRETE THROUGH TREMIE PIPE

When concreting is carried out under water, a temporary casing should be


installed to the full depth of the bore hole so that fragments of ground cannot
drop from sides of the hole into concrete as it is placed. When concreting
under bentonite slurry, temporary casing is required only near the top

The tremie pipe and hopper should be a closed system to prevent penetration
of water to prevent laitance

All tremie tubes should be scrupulously cleaned after use

*Definition of laitance: an accumulation of fine particles on the surface of fresh


concrete due to an upward movement of water (as when excessive mixing water is
used)
6
Sectional view sketch of pile
cap, stump & reinforcement
SECTIONAL VIEW OF A PILECAP
ANY QUESTIONS?
THANK YOU !

STOP
THE END!
DR MYZATUL AISHAH LECTURER
KAMARAZALY

DAPHNE TAN 0329055


KAREN LIM 0329431
LAU WAN YEE 0328947
LIM XIAO SHI 0324410
LOH WEI TING 0328314
LOW WAN JING 0329214
NGEOW YEE LING 0329178
SAHIL GUNESH 0328569

SECTION 3 | GROUP 1

You might also like