APARTMENT HOUSES CHN

Author of the slides: Ing. Miroslav Jindrk


RD Rmaov s.r.o.
Case study no. 5

Leonardo da Vinci project


no. CZ/06/B/F/PP-168007

WP6 Case Studies


PC 3 A set of case studies
Content of slides
Apartment houses Chn
The basic version in two designs
Profile of the external wall
Profile of the ceiling construction
The ground plan
Technical parameters
Building Assembly
Increase of fire resistance for bearing external walls
Construction time of key delivery
Apartment houses Chn

Locality construction
of 32 timber-based
multistoried detached
and terrace houses.
Turn-key delivery
including
groundwork, house
connections, ground
completion and
fencing.
The basic version in two designs

The houses have two 6 dwelling units:


stories with two studio - 6 dwelling units 69,03 m2
apartments.
The basic version is 10 dwelling units:
delivered with a saddle
roof with a roof inclination
- 4 dwelling units 35,15 m2,
of 38. - 4 dwelling units 37,50 m2,
RD 180/38 apartment - 2 dwelling units 69,03 m2
houses are offered in the
basic version in two
designs:
Profile of the external wall

1. contact thermo facade


2. gypsum wood-fibre board
15 mm
3. mineral insulation
120 mm
4. gypsum wood-fibre board
12,5 mm
5. gypsum plasterboard
12,5 mm
6. frame construction
120 mm
Profile of the ceiling construction

1. anhydrite compound
55 mm
2. Rotaflex 25/20 TSPS 02
3. Mirelon 5 mm
4. particle board 22 mm
5. mineral insulation ORSIL
120 mm
6. Lathing 30x60
7. 2x gypsum plasterboard
12,5 mm
The ground plan
Technical parameters
Ground plan size 16,96 x 10, 63 m
Number of above-ground stories 2
Number of dwelling units 6 (10)
Type of roof construction purlin system 38
Construction of external walls framework
Thermal resistance for external walls R = 4,195 m 2K W-1
Coef. of thermal transmittance for external walls U = 0,229W m -2K-1
External wall fire resistance REI 90, REW 60
External wall airbone sound insulation R w 44 dB
Impact sound insulation for ceiling with Ln,w = 52 dB
covering
Airbone sound insulation for flat to flat walls R w = 59 dB
Building Assembly
Increase of fire resistance for bearing
external walls
REI 60 was required for wall exposed to external heat
stress
Walls were lined with boards MULTIPOR 600x390x80
firm product Xella, having increased the external wall
fire resistance to REI 90
Increase of fire resistance for bearing
external walls
Construction time of key delivery

Groundwork: 14 days
Upper timberwork:
67 days
-> with a technological
interval of 28 days for
anhydride maturing
Total costs
for construction:
7,1 mil. CZK
Thank you for your attention!