You are on page 1of 31

GLAST LAT Project

Managers F2F 5/11/05

GLAST Large Area Telescope:


Face to Face Managers Meeting
Gamma-ray Large
Area Space Telescope

LAT Integration & Test


April 13, 2005 2:00 PM
Integration and Test
2 towers and next six month
Elliott Bloom
I&T Manager
Ken Fouts
I&T Engineering Manager
SLAC

Eduardo do Couto e Silva


SVAC Manager
4.1.9 - Integration and Test

GLAST LAT Project

Managers F2F 5/11/05

Last Month's Accomplishments (1 of 2)

Management
Tracking hardware shortages for LAT integration.
Supported Environmental Test Planning at NRL
Procedure Status
65 of 69 released or submitted for sign-off

IFCT
Validated EGSE in the grid with EM TEMs prior to
connection to flight HW.
Developed and demonstrated with the 1x4 a process for TPS
replacement in the grid.
Installed Kapton tape on TKR cables.
Two tower tests underway (ECD 5/11)

4.1.9 - Integration and Test

GLAST LAT Project

Managers F2F 5/11/05

Last Month's Accomplishments (2 of 2)


Online
Beyond 2 towers
Housekeeping multi-pen strip chart GUI
Parallelizing INT scripts
Trying to move some LATTE 5 features into production
earlier (e.g., HSK, LATc)

E-logbook
Added ability to search shift logbook with Google Desktop
Implementing requested improvements

Continued supported of CAL, TKR, INT and test suites.


Supported data taking, trigger and E2E script development.
Problem assessment and fixes a large part of online
workload
NCRs, support for clean room operations, support of
subsystems scripts.

CCB activity and JIRA maintenance

4.1.9 - Integration and Test

GLAST LAT Project

Managers F2F 5/11/05

I&T MGSE/Grid Activities

Tower A & B in the Grid

Mass simulators installed

EM PDU and GASU

EGSE shelf and cable


service loop

EGSE harness routing

Harness service loop

4.1.9 - Integration and Test

GLAST LAT Project

Managers F2F 5/11/05

Procedure Status

69 documents total
65 latest versions submitted for sign-off
59 are released

4.1.9 - Integration and Test

GLAST LAT Project

Managers F2F 5/11/05

Procedure Status (1 of 6) Management

4.1.9 - Integration and Test

GLAST LAT Project

Managers F2F 5/11/05

Procedure Status (4 of 6) IFCT Electrical

4.1.9 - Integration and Test

GLAST LAT Project

Managers F2F 5/11/05

Procedure Status (6 of 6) Particle & SVAC

4.1.9 - Integration and Test

GLAST LAT Project

Managers F2F 5/11/05

I&T NCRs by Month Open/Closed Status

Last Month

Current
Status

As of May 10th

Month NCR Opened


4.1.9 - Integration and Test

GLAST LAT Project

Managers F2F 5/11/05

Online progress

LATTE 4.9.0
CCB JIRA number 34
GPIB support for Agilent power supply (Brian)
RS-485 support for BPU Simpson meters (Brian)
ACD GASU problem (Jim provided work-around and a
fix for LATTE)
LTE-254: SW verification passes, but in elog, the SW
shows red. Fix this inconsistency (Brian)
LTE-251: If rcReport generation fails, wrong rcReport
line is extracted from rcReport.out during export
LTE-257: Message logger does not launch

4.1.9 - Integration and Test

10

GLAST LAT Project

Managers F2F 5/11/05

LATTE 5 overview (updated)


S/C
VSC

LATTE 4-5
Run Control

Script

Loading of
Scripts

XML
Schema
Config

LATc
LATc
file

CMD
Raw
Arch

C&T
database
Mnemonics

MySQL

UN-CCSDS

Reset
1 PPS

Monitoring

Raw Arch

UNCOMPRESS
UN-CCSDS

Etc

GPS

Commanding

Discretes

Analysis
Consumer

1553

CCSDS

HSK

Display
Client

Flight Software
(Vx Works)

LDF

Science
Data

Science Data

Raw Arch
SC/Tlm

?
4.1.9 - Integration and Test

Raw Arch

11

GLAST LAT Project

Managers F2F 5/11/05

Two Tower Test Status as of 5/11/05

4.1.9 - Integration and Test

12

GLAST LAT Project

Managers F2F 5/11/05

I&T Detail Schedule (1 of 2)


ID
601

Task Name

% Complete

Finish

Apr '05
4/10

3/22/05

97%

5/12/05

Two Tower Test Prep

3/22/05

100%

4/21/05

621

Two Tower Test Pre-test review

4/12/05

100%

4/12/05

622

Two Tower Test EGSE Ready

4/25/05

100%

4/25/05

623

Two Tower CPT

4/18/05

100%

4/29/05

635

Two Tower Trigger tests

4/22/05

100%

5/3/05

643

Two Tower Calibration

4/22/05

100%

5/6/05

658

CSPT (STR)

5/5/05

100%

5/5/05

659

602

Two Tower Test

Start

E2E Data Collection

5/6/05

70%

5/9/05

660

E2E basic cosmics

5/6/05

100%

5/6/05

661

E2E S/C Power Margin

5/6/05

100%

5/6/05

662

E2E External pulser

5/6/05

50%

5/9/05

663

SVAC data collection

5/10/05

0%

5/11/05

664

Two Tower Post Test Review

5/12/05

0%

5/12/05

12/6/04

71%

5/20/05

665

Tower 1 - Bay 5

666

FM103 Post ship test and receiving test

12/6/04

100%

1/14/05

674

Tracker 2 post ship test & receiving test

4/4/05

97%

5/13/05

4/4/05

97%

5/13/05

675

TKR-2 Post-Ship Test

May '05
Jun '05
Jul '05
5/1
5/22
6/12
7/3

4/25

5/16

687

TEM/TPS 1 Flight Readiness w/rework

5/16/05

0%

5/16/05

688

STM Bay 5 TEM/TPS

5/16/05

0%

5/16/05

689

Bays 4&5 TEM-GASU Flight cables ready

5/16/05

0%

5/16/05

5/16

690

Bays 4&5 TPS-PDU flight cables ready

5/16/05

100%

5/16/05

5/16

691

Receive purge groove cables

4/25/05

100%

4/25/05

692

Pull test Purge Groove (Thermistor) cables (non-flight)

5/6/05

50%

5/11/05

693

install purge groove cables Bay 5

5/12/05

0%

5/13/05

4.1.9 - Integration and Test

13

GLAST LAT Project

Managers F2F 5/11/05

I&T Detail Schedule (2 of 2)


ID

Task Name

Start

% Complete

Finish

Apr '05
4/10

694

TEM/TPS-1 to CAL FM102 Shimming

5/16/05

0%

5/17/05

699

Tower-1 Grid Bay 5 I&T

4/27/05

0%

5/20/05

700

Finish NCR 420 disposition

4/27/05

100%

4/27/05

701

TKR-2 installation into grid bay

5/13/05

0%

5/16/05

706

FM102 installation into grid bay

5/16/05

0%

5/17/05

709

Tower-1 Grid Bay 5 Test

5/17/05

0%

5/20/05

12/6/04

42%

6/2/05

719

Tower 2 - Bay 1

720

FM103 Post ship test and receiving test

12/6/04

100%

1/14/05

728

Tracker 1 post ship test & receiving test

4/27/05

100%

5/10/05

736

Sell TKR-1 to I&T

5/10/05

100%

5/10/05

737

I&T TKR-1 Receiving Test (LAT-PS-3290)

5/13/05

0%

5/13/05

738

TEM/TPS 2 Flight Readiness

5/16/05

0%

5/16/05

739

STM Bay 1 TEM/TPS

5/16/05

0%

5/16/05

740

TEM/TPS-2 to FM103 Shimming

5/16/05

0%

5/18/05

746

Tower-2 Grid Bay 1 I&T

5/9/05

0%

6/2/05

747

FM1 installation into grid bay

5/20/05

0%

5/24/05

752

FM103 installation into grid bay

5/24/05

0%

5/25/05

755

Tower-2 Grid Bay 1 Test

5/25/05

0%

5/26/05

760

Four Tower Test

5/9/05

0%

6/2/05

5/9/05

0%

5/13/05

761

Write multi-tower test scripts

762

validate multi-tower test scripts

5/16/05

0%

5/20/05

763

INT Tag release

5/23/05

0%

5/23/05

764

Receive Bays 0,1 TEM-GASU cables

5/18/05

0%

5/18/05

765

Receive Bays 0,1 TPS-PDU cables

5/18/05

0%

5/18/05

766

Install Bay 0,1 cables

5/27/05

0%

5/27/05

767

Four Tower Test Pre-test review

5/27/05

0%

5/27/05

768

Execute four tower test

5/27/05

0%

6/2/05

4.1.9 - Integration and Test

May '05
Jun '05
Jul '05
5/1
5/22
6/12
7/3

4/27

5/16

14

GLAST LAT Project

Managers F2F 5/11/05

Issues & Concerns


ISSUES
Availability of flight assembly hardware.
Shortages identified by I&T and being worked with
Subsystems.
TEM/TPS Deliveries
Flight Cables
CONCERNS
Continued support from subsystems for NCR closure.
TPS rework and replacement, availability for future tower
installations.
Need firm delivery dates for third layer ELX boxes
LATTE 5.0 ready Oct. 1 for use in LAT Functional testing due to
start 10/14. E2E tests start 11/1.

4.1.9 - Integration and Test

15

GLAST LAT Project

Managers F2F 5/11/05

Last Month's Accomplishments


SVAC
Successful turn around for calibration of two tower data
ready before data taking started !
Joint effort TKR/CAL/SAS/SVAC

Offline data processing system under CCB and working


well
Thanks to Richard Dubois

So far no major problems seen with single tower data


See next slide

4.1.9 - Integration and Test

16

GLAST LAT Project

Managers F2F 5/11/05

Issues for single tower tests: offline analysis


Closed

Under investigation
CAL_HI and CAL_LO fired without any crystal hits
Investigation has not started

Most likely due to direct deposition in diodes


CAL_HI trigger fired without high energy deposition

Most likely due to direct deposition in diodes


Discrepancy between TKR occupancy on top GTRCs between DATA and MC in electronics space (generated STRXX)

Most likely due to the differences in particle composition between DATA and MC

Maybe a small fraction could be from CC FIFO buffers filled up in data (this is a feature not a bug)
Discrepancy between Data and MC for TKR dead channel list

Partially disconnected channels are not simulated


Discrepancy calculated and measured event size (generated STR3)

Miscalculations based on wrong assumptions for event multiplicities


Discrepancy between GEM and TriggerAlg for trigger types

Analysis software (TriggeAlg) is not a realistic representation of GEM since it does not address threshold/calibration
differences
Discrepancy in trigger rates for 1,5,10 and 20 KHz runs, underestimated for low rates and overestimated for high rates at a few
% level

Rates from generator were not known to better than a few %, so it is consistent with measurements

overestimation had to do with deadtime since some events did not make into the stream
Compared events that triggered BOTH the TKR and EXT pulse generator running at 20KHz with events that trigger TKR only,
former had lower hit multiplicity (generated STR8)

Reason was that when a trigger window was opened (on raising edge) by EXT the TKR signal was already on for some
time which means some of the hits already died away by the time we looked at. Expect this to be more frequent a higher
rates
Distribution for TKR trigger arrival times was not flat

Needed to select EXT trigger to open the window and then make the same plot and naturally the spike disappears
There is consistently 10-15% more triggers seen during the 5 and 10kHz runs than expected as measured by the exponential fit
to the delta event time register of the GEM.
TKR only triggers is around 85% (TBR) of the time when the muon telescope triggers

4.1.9 - Integration and Test

17

GLAST LAT Project

Managers F2F 5/11/05

The Oscar goes to

4.1.9 - Integration and Test

18

GLAST LAT Project

Managers F2F 5/11/05

Anders Borgland !

4.1.9 - Integration and Test

19

GLAST LAT Project

Managers F2F 5/11/05

Two Tower Tests Baseline Run : Flight Configuration

Reconstructed
positions

79% single track events


14% two-track events

4.1.9 - Integration and Test

Calibrated Energy Spectrum


Expected to peak at 100 MeV

There are 234664 triggers


There are 0 events with Trigger Parity errors
There are 0 events with Packet errors
There are 20 events with TEM errors
Time of first trigger: Thu May 5 20:48:41 2005 (GMT)
Time of last trigger: Thu May 5 21:48:42 2005 (GMT)
Duration: 3601 seconds
Rate: 82 hz

20

GLAST LAT Project

Managers F2F 5/11/05

Two Tower Tests Baseline Run : Flight Configuration

Average TKR multiplicity per plane ~ 2

Average CAL multiplicity per layer ~ 1.4

Average CAL Energy/layer ~ 18-20 MeV


Multiplicities are consistent with expectations

4.1.9 - Integration and Test

21

GLAST LAT Project

Managers F2F 5/11/05

Time Between Events: Baseline Run

4.1.9 - Integration and Test

22

GLAST LAT Project

Managers F2F 5/11/05

Time Between Events: Non-Zero Suppr.

4.1.9 - Integration and Test

23

GLAST LAT Project

Managers F2F 5/11/05

Two Tower Tests Baseline Run : Reconstructed Z Direction


From Anders

Tracks passing through


1 tower only

Maximum trigger acceptance is reduced


and is consistent with expectations based on
geometrical calculations

Tracks passing through


both towers
Tracks coming from top of the tower
Cos = -1
Selection cuts:
Single track events
Ratio between predicted and
measured MIP > 0.7 and < 1.3
4.1.9 - Integration and Test

24

GLAST LAT Project

Managers F2F 5/11/05

Two Tower Tests Baseline Run : Sum of Crystal Energies in the CAL

Tracks passing through


1 tower only

Energy in MeV

Energy calibrations work within a


tower and across towers

Tracks passing through


both towers

Selection cuts:
Single track events
Ratio between predicted and
measured MIP > 0.7 and < 1.3

4.1.9 - Integration and Test

Energy in MeV

25

GLAST LAT Project

Managers F2F 5/11/05

Two Tower Tests Baseline Run : Total Radiation Length

Expect 10 radiation lengths!


Tracks passing through
1 tower only

Number of Radiation Lengths

Tracks passing through


both towers

Selection cuts:
Single track events
Ratio between predicted and
measured MIP > 0.7 and < 1.3
4.1.9 - Integration and Test

Number of Radiation Lengths

26

GLAST LAT Project

Managers F2F 5/11/05

Two Tower Tests Baseline Run : CAL Energy per Layer


From Dave

Selection cuts
1 track
Difference in predicted
track precision and
measured CAL position
< 20 mm in x and y

4.1.9 - Integration and Test

27

GLAST LAT Project

Managers F2F 5/11/05

Two Tower Tests Baseline Run : MC vs DATA


Tower 0

4.1.9 - Integration and Test

Tower 4

28

GLAST LAT Project

Managers F2F 5/11/05

Science Data vs. Housekeeping Data

Tower 0, bottom layer

Temperature

Hit multiplicity

Temperature

Hit multiplicity

From Xin

Tower 0, top layer

Tower 4, bottom layer

4.1.9 - Integration and Test

Hit multiplicity

Temperature

Time
Temperature

Hit multiplicity

Time

Tower 4, top layer

Time

Time
29

GLAST LAT Project

Managers F2F 5/11/05

Priorities for Data Analysis for 2 towers

We proposed to the Collaboration to analyze these runs first


We are identifying names to be attached to the list below

1/1 baseline
Check trigger types and rates, event sizes , raw and recon distributions for tracks within
one tower and across towers
Monte Carlo comparison

2/1,2/2 baseline and change PDU PS values


First time we have a Power Distribution Unit. Could it be a source of noise? If so, can the
raw distributions tells us?

2/6, 2/7 read TKR from Left or Right only


Cable lengths are different between odd and even numbered towers, but the DAQ takes that
into account. Lets check it by comparing raw and recon distributions from both towers.
Select events that triggered at the center and at the edges

4/1 to 4/4 baseline with pulse generator @ 1,5,10,20 kHz


Muon distributions should not be affected by high rates from pulse generator
Do we understand the deadtime?

B2 nominal settings TEM diagnostics enabled


It is just like 1/1 but with TEM diagnostics ON

B10 CAL HE muon gain, 4 range readout, TEM diagnostics enabled


Calibrate TOT
measure dead strips
Calibrate edges of crystals

B13 CAL HE muon gain, 4 range readout, Zero Suppression disabled


Check pedestals in the CAL
Trend pedestals, muon peaks, log ratios, what else?

4.1.9 - Integration and Test

30

GLAST LAT Project

Managers F2F 5/11/05

Wrapping up

Single tower data analysis


No show stoppers yet
Generated few special test requests

Good start with two tower data


Runs finished this morning
Will distribute data to Collaboration today

More to come
Join us in the Instrument Analysis Weekly Meetings
Friday 8 am PDT (VRVS)

Still looking for more people


Our web site
http://www-glast.slac.stanford.edu/IntegrationTest/SVAC/Instrument
_Analysis/Instrument_Analysis.html