GTG Modules Fabrication Workshop


As- Built Documentations & ITPs

Gulnaz Kulmanova

Tengizchevroil 2010

As- Built Documentations & ITPs


As-built documentation

During the course of the construction the contractors


shall compile the as-built documentation, reflecting
the actual implementation of the design solutions and
the actual position of the structures and their
elements, at all stages of the production as the
particular stages of the work are completed. The
obligatory nature of the compilation, the content and
the form of specific as-built documents shall be
stipulated by the requirements hereof, of other
effective normative documents, the agreement, design
and, where necessary, the instructions of the
representatives from state control and supervisory
authorities.
Tengizchevroil 2010

As- Built Documentations & ITPs


FABRICATION CONTRACTOR shall provide to
COMPANY all as-built documentation (acts, protocols,
special & general log books) required to be
maintained according to RoK requirements during the
fabrication and assembly process.

Tengizchevroil 2010

As- Built Documentations & ITPs


ITP- Inspection Test Plan
As built Documentation
The applicable Acts/ Logs & Protocols shall be substituted
into Inspection Test Plans.

Tengizchevroil 2010

As- Built Documentations & ITPs

Acts
Act Mandatory Certificate of which the content and
layout is extracted from the RoK norms and standards
which cannot be modified in any way or form. The
content and layout is allowed to be presented within
project specific template(s) as per agreed by COMPANY
(see Appendix 1)
Act Recommended - Certificate of which the content and
layout is based on RoK norms and standards and other
regulative guideline requirements. Outside of conforming
to the RoK norms and standards requirements content
modification is permitted to align with project
specification. The content and layout is allowed to be
presented within project specific template(s) as per
agreed by COMPANY.

Tengizchevroil 2010

As- Built Documentations & ITPs


Acts
Act of Hidden Works- works, hidden by the sequence of
following works , quality and accuracy of which can not be
determined after performing these subsequent
works.

Tengizchevroil 2010

As- Built Documentations & ITPs


Protocols
Protocol Mandatory - Verification documentation for
testing performed of which the content and layout is
extracted from the RoK norms and standards which
cannot be modified in any way or form. The content and
layout is allowed to be presented within project specific
template(s) as per agreed by COMPANY.
Protocol Recommended - Verification documentation for
testing performed of which the content and layout is based
on RoK norms and standards and other regulative guideline
requirements. Outside of conforming to the RoK norms and
standards requirements content modification is permitted to
align with project specification. The content and layout is
allowed to be presented within project specific template(s)
as per agreed by COMPANY.
Tengizchevroil 2010

As- Built Documentations & ITPs


Check sheets
Documentation used to define inspection criteria
for components forming the basis of formal record
documenting the results of testing utilized during the
construction execution phase of the project not based on
RoK norms and standards and other regulative guideline
requirements.

Tengizchevroil 2010

As- Built Documentations & ITPs


Logbook
The Logbook is to be maintained throughout the fabrication
and construction phases. Activities taken place during those
phases shall be accurately documented:
the dates of the most important aspects during construction
and fabrication; data on the quality of the materials used;
methods applied during fabrication and construction works;
weather conditions;
any deviations from the drawings; comments from the
Regulatory Authorities etc.;
Type of Logs:
Technical Supervision Log Book;
Author Supervision log Book;
General/Production Log Book;

Tengizchevroil 2010

As- Built Documentations & ITPs


Type of Special Log Books:
Log of Installation of Structural Steel;
Log of Controlled Bolt Tensioning;
Structural Welding Log;
Piping Welding Log;
Anticorrosive Protection Log;
Radiographic Control Log;
Magnetic Particles Control Log;
Ultrasonic Test Log;
Dye Penetrant Test Log;
Electrical Installation Production Log;
Cables Installation Log;

Tengizchevroil 2010

10

As- Built Documentations & ITPs


Type of Acts/Protocols (per discipline):

Act of Intermediate Acceptance of Main Structures


Document of Quality of Structures
Hidden Works Acts for Corrosion Protection
Hidden Works Acts for Insulation
Acts of the Acceptance of Painting
Acts of Acceptance of Insulation Activities
Acts of Electrical Equipment Acceptance
Record of Visual Inspection of Cables
Report on Cable Laying
Protocol of Cable Insulation Resistance Measuring
Protocol of Testing Cables above 1000V
Protocol of Phasing
Act of Power Transformer Acceptance
Record of Visual Inspection of Wired Equipment
List of Mounted Equipment
List of Technical Documentation Submitted Punch Lists
List of Installed Equipment
Act of Verification of Instrument & Automation Devices
Protocol of Mounted Panels & Automation
Act of Incoming Control
Protocol of Incoming Control of Length of FOC (Fiber Optic Cables)
Line Passport
Protocol of Attenuation Measurement of FOC (Fiber Optic Cables)
Tengizchevroil 2010

11

As- Built Documentations & ITPs


The as built documentation (Acts, Logs, & etc.)
execution process shall be completed as shown in the
following picture:

Tengizchevroil 2010

12

As- Built Documentations & ITPs


Reference to SN RK 1.03-00-2011
CONSTRUCTION INDUSTRY.
MANAGEMENT OF THE CONSTRUCTION OF
ENTERPRISES, BUILDINGS AND STRUCTURES
Item 6.8.5.9 The contractors holding of a certified quality system,
conforming to the requirements of ISO 9001-2008 (paragraph 5.5), enables
it to inspect concealed/hidden works and perform interim acceptance
without the involvement of the technical supervision in coordination with
them.