Professional Documents
Culture Documents
(made up of several tasks) should have only a single start activity and a
single finish activity.
Develop the relationships among the activities. Decide which activities
must precede and which must follow others.
Draw the "Network" connecting all the activities. Each Activity should
have unique event numbers. Dummy arrows are used where required to
avoid giving the same numbering to two activities.
Assign time and/or cost estimates to each activity
Compute the longest time path through the network. This is called the
critical path.
Use the Network to help plan, schedule, and monitor and control the
project
Objectives
Stay on budget
Finish on time
Stay in scope
Triple Constraint Model
Create Quality
Introduction to our
project
Kmart
We are running a mart by the name of K-mart. We are
providing local as well as international brands products. Our
mart is divided into different sections. Grocery, Crockery
items, Cosmetics, Toys and many other products.
We have finalized to start the construction of new floor
within few days and it will be the activity of 32 weeks. In 32
weeks the 1st floor will be completely constructed.
Activity
Description
Architecture
None
Walls
Beam for
windows and
doors
Lantern
Stairs
Sewerage &
wiring of
electricity
D,E
Plastering
E,F
Wood work
Electricity
equipment fitting
G,H
Floor design
Paints
Total
Time in weeks
32
Predecessor
E
I
Star
t
G
B
D
End
H
Activity
EST
EFT
LST
LFT
LST-EST
Critical
path
Yes
Yes
Yes
12
12
Yes
12
14
12
14
Yes
14
16
14
16
Yes
16
19
16
19
Yes
19
23
19
23
Yes
23
25
23
25
Yes
25
28
25
28
Yes
28
32
28
32
Yes
14yes
Activity
T
=a+4m+b
/6
Variation(
b-a/6)^2
0.44
0.44
0.44
0.11
0.44
0.11
0.44
0.11
0.44
A = optimistic time
Means everything is according to the plan.
B = pessimistic time
Means all things are going into negative.
M = Most realistic time
Project variance T=
T T=3.97
A-B-C-D-E-F-G-H-I-J
Project Variance =
1.99 weeks
Z = Z is the number of standard deviation the due date or target date lies from the means or expected
date.
Z=
P(project<=35) =
=(1.507)
0.93319 100
93%
There is a approximately 93% chance that the project will
complete in 35weeks.
=0.99
=2.33
=
= 2.33
36weeks
We are sure that our project will complete 99% if we get 36weeks.
Budgeted process
Four steps of the budgeting process
Identify all costs associated with each of the activity. Then add these
costs together to get one estimated cost or budget for each activity.
If you are dealing in a large project, several activities can be
should be spent during each week or month to finish the project by the
date desired.