Professional Documents
Culture Documents
Presentation Number 01
Identification and Coordination of M&E Building Services
Part 1 - Introduction to the M&E Services
Part 2 - Coordinated Services
GHG
What are the Key Mechanical & Electrical (M&E) building services?
Heating - Low temperature hot water (LTHW) supplied by boilers and pumps via pipe
work systems - feeding radiators, heaters, air conditioning systems (HVAC) and fan
coil units (FCUs)
Cooling - Chilled water (CHW) supplied by chillers and pumps via pipe work systems
- feeding air conditioning systems (HVAC) and fan coil units (FCUs) and cooling units
for electrical switch rooms
Gas Generally used to supply the boilers and fit out kitchens
Drainage - Soil & vent and rainwater draining into sumps and sewers controlled by
pumps via pipe work systems
Water services - Water supplies for domestic use and plant services stored in
tanks & supplied by pumps via pipe work systems
Fire Protection - Sprinklers and wet/dry risers stored in tanks & supplied by
pumps via pipe work systems (wet risers have pumps, dry risers do not have pumps
for fire service use)
Heating Ventilation & Air Conditioning (HVAC) - Supply & extract air supplied
& extracted by air handling units (AHUs) & fans via ductwork systems
High Voltage cables (HV) - Incoming supplies from electrical utility companies
High Voltage cables (HV) - Supplies from electrical HV switch rooms to electrical LV
switch rooms
Low Voltage cables (LV) - Supplies from electrical LV switch rooms to main mechanical
plant and main mechanical plant control panels
Low Voltage cables (LV) - Supplies from electrical LV switch rooms to electrical
distribution boards, equipment and control panels
Electrical Containment - Ladder rack, cable tray/basket, trunking and conduit for
installation of electrical services
Busbars Utilised to feed heavy duty plant items and multiple electrical supplies such
as electrical risers
Lighting & Small Power - Outgoing electrical circuits from distribution boards and
control panels
GHG
GHG
HV ladder rack
LV ladder rack/cable tray
Trunking & conduit
FA/VA primary cable tray/basket
BMS primary trunking/cable tray
Security primary trunking
Questions:
2. What would constitute a meaningful commencement for the M&E services?
3. What would constitute a plant or switch room release (Room Ready) for the M&E
services?
Answers:
4. Meaningful Commencement
.
The predetermined start on site date for M&E building services does not want to be over
ambitious.
The project build sequence and logistical plan will need careful consideration to
realistically identify what the site conditions are going to be at that future point in time.
It may be worthwhile deferring the M&E services commencement date and reducing the
overall duration in order to provide better access, more work faces and less concurrent
working with construction trades.
Starting piecemeal works in ad hoc areas will create confusion as to the meaningful
commencement date.
If there is only one notice to proceed the M&E contractors overall contract duration
commences from that date.
Typically the M&E services would follow the completed block work in agreed areas, with
builders work holes formed and plinths constructed (if required at that point)
hgh
Walls, floor slabs and soffit construction complete including the builders work holes
hgh
Questions:
1. What is a primary M&E services route?
2. Where are the primary M&E services routes?
3. What are the key M&E plant and switch rooms and where are they located?
4. GHG
2.
.
.
.
.
.
.
Typical basement mechanical plant and electrical switch rooms layout plus the
locations of vertical risers
gfgfbvbv
HGHhgh
HV Switch
Room
Mechanical
Risers
Mechanical Plant
Room
kfkf
Ventilation Plant
Room
Ventilati
on Risers
LV Switch
Room
Electric
al Riser
Ventilati
on Riser
Corridor
Corridor
Mechanical pipe
work
Electric
al Riser
Ventilation Plant
Room
Mechanical Plant
Room
Fire protection
pipe work
Water services
pipe work
Electrical
containment
Corridor
Ventilatio
n Riser
Ventilation duct
work
Ventilati
on Riser
LV Switch
Room
Mechanic
al Riser
Corridor
Location
Basement
Basement
Basement
Roof Level
Basement
A pipe work link between a chiller located in the basement and its cooling tower located
on the roof
A pipe work installation from a boiler room or a chilled water plant room feeding
numerous items that require heating & cooling properties
Ventilation duct work from a plant room connected to other duct work in a vertical riser
Ventilation duct work from a plant room supplying and extracting air to other plant rooms
Containment and cables installed between electrical switch rooms located in the
basement and upper floor levels
Containment and cables installed from electrical switch rooms to mechanical plant rooms
located in the basement and upper floor levels
hgh
The impact of M&E services installations on each other (who goes first what goes
where - and how)
The impact of the M&E services on the construction programme (key dates - site
logistical plan & access)
Implementing the above will achieve an accurate target programme and subsequent 4D
model.
2. The sequence in which the M&E services need to be installed will generally be from
the highest to the lowest (soffit downwards). This is likely to differ along the primary
routes due to:.
Summary details:
Achieve the shortest period of time to install the high level mechanical
services prior to release for electrical services containment
commencement. Typically this will be +/- 8 weeks.
ghg