Professional Documents
Culture Documents
Construction Projects
RAJPUT
Overview
Definition of Risk
FTA Mandate
Risk Assessment
What does it mean for the grantee/owner
Looking at the “Big Picture”
Types of Risk
2
Overview cont…
Mitigating Risk…using Quality Management Techniques
Recommendations
3
FTA Mandate / Guidance
4
Dear Colleague Letter
“As part of its ongoing effort to make the New Starts evaluation and rating process as
transparent as possible, FTA has revamped the format and content of the project
profiles to more clearly indicate the reasons for each rating. In addition, we have
included more specific information about the New Starts evaluation criteria and FTA’s
rating system in the body of the report.”
5
Elements of a Construction Project
Design Plans
• Required to identify costs
• Drives implementation of project
6
Risk Assessment
Definition:
The process used to qualify the significance of a project by identifying
and analyzing uncertainties and constraints in terms of the likelihood
that an occurrence will happen and the probable consequences.
NEW STARTS
DESIGN/BUILD
TURNKEY
7
Risk Assessment
What Does Risk Assessment Mean To A Grantee/Owner?
Provides basis for communicating level of confidence that the project can be carried out successfully, on time and within
budget
• Local/State Government
• Board Members
• Funding Agency
• Community
8
Risk Assessment
Looking At The “BIG” Picture
9
Types of Risks
Real Estate
Property acquisition Environmental
Relocation Environmental impact studies
Condemn
Eminent Domain
Historical Significance
Protected Lands
Public Utilities Archaeological
Analysis & coordination Structures
Agreements
Relocation
Contract phasing and packaging
Scope of work
Shared Right- of-Way (ROW) Track Bid process / Labor
Memorandum of Understanding (MOU) Integrating Construction Packages
Insurance costs/requirements
Public hearing
Politics Marketing/Communication
Internal/external Safety & security
10
Criteria for Evaluating Risk
Funding
• Capital cost
• Operating and Maintenance (Life Cycle) costs
• Financing costs
• Contingencies
Schedule (the greater the number of years, the higher the risk)
• Limitations
• Compatible with method of construction
Ridership
• Operations
Safety/Security
• Project (safety and security certification)
• Contractors
• Laborers / Employees
11
Risk Assessment Methods and Strategies
Design Plans
Client/owner/grantee requirements
Deterministic
Probabilistic
12
RISK ASSESSMENT TOOLS
@Risk
PERTMaster
Crystal Ball
13
Mitigating Risk…using Quality Management
Techniques…
14
CASE STUDIES
15
Case Study #1
Tren Urbano
San Juan, Puerto Rico
Rapid Rail Project: A high-capacity third rail system, with a mixture of at-grade,
above grade and underground sections spanning 10-miles (17.2 km) and 16-
stations with a construction value of $2.5 billion.
Challenge: Dealing with the complexity of managing multiple contracts and contractors
tasked with the design, construction and operation of a new transit system
16
Tren Urbano
Lessons Learned:
17
Case Study #2
Washington Metropolitan Area Transit Authority
(WMATA), Washington, DC
18
Washington Metro (WMATA)
Lessons Learned:
• A QAP can be an effective tool to ensure that quality work is performed, but
the key to having a successful quality control program is its integration into
the work plan
• The Quality Manager should be properly trained and have experience in the
industry
• The Contractor must accept the Quality Manager as an integral part of his
team and implement the quality control program as part of his regime
• The Owner, Quality Manager and Contractor must work together as a team
and effectively communicate so that project goals will be achieved and
project risk will be minimized or eliminated.
19
A Modern Day Risk Challenge
Southeastern Pennsylvania Transportation Authority (SEPTA)
Philadelphia, PA
Construction Plan
Design Elements: A Single Column “T” Bent vs. Double Column Structure (Basic Layout); State-of-the-Art Passenger
Stations; Utility Work; Operations and Maintenance. (The completed utility work will create a modern infra-structure for
redeveloping the West Philadelphia corridor)
Challenge: Construction never done by SEPTA before, consisting of a system of weekend and 9-day outages (a high
risk plan), managing, coordinating/integrating schedules for five construction packages.
20
SEPTA - MSE
Project Risks
Unique construction
Utility construction
Acquiring permits
Environmental issues
Public issues
Bid protests
21
SEPTA – MSE
22
A Modern Day Risk Challenge
Middle Branch
Maryland Transit Administration, MTA/Light Rail ,Double Track Bridge
Project
Management Approach:
Develop staging plan in advance multiple priorities must be met and project must strike
a balance
Develop understanding that construction under operation requires a different mind-set
and rules
Start small with achievable goals
Build Budget Contingency into approach for risk
Provide flexibility in shutdown durations and milestones dates to give some breathing
room 23
Effective Risk
Management
Skill Mix
Accountability
Integration of systems
24
RECOMMENDATIONS
25
Summary
COMMENTS????