Current situation - Technical Supervision 1/2

Tengiz there are 3 Technical Supervision Inspector positions,


hired by KPJV as an employer.
Fabrication - planned for ERSAI only.
- Construction activity in Tengiz require more recourses based
on the increase of the Infrastructure scope, roads, Orken,
early overhead and pipeline scope.
- Based on the nature of the work require the inspectors with
specific skills, structural, civil, mechanical.
- According the Technical Supervision run by c

Tengizchevroil 2011

Current situation - Technical Supervision 2/2


- Construction activity in Tengiz require more recourses
based on the increase of the Infrastructure scope,
roads, Orken, early overhead and pipeline scope.
- Based on the nature of the work require the inspectors
with specific skills, structural, civil, mechanical.
- According the RoK Legislation - Technical Supervision
run by client(TCO). At the moment, KPJV Technical
Supervision inspectors are executing this role under
old strategy ( Construction Management contractor),
changes in contracts between TCO and KPJV might
impact for this practice.

Tengizchevroil 2011

Technical Supervision on Fabrication Yards

Technical supervision. i.e. construction control is there for the Client to be


confident that construction and installation works are performed with good quality.

Considering that our project is a modularized construction, where majority of the


process/power/other facilities wrapped in module structure documentation of
Technical Supervision from Fab yards will key for Main plants turnover facility
acceptance.
Company need the ensure that Fabricator Contractor is strict compliance with
approved design /calculations and comply with requirements of executive documents
(such as Method Statements and procedures) defining execution of fabrication and
installation works.
Technical supervision Record from fabrication activity in the technical supervision log;

Tengizchevroil 2011

Technical Supervision Recourse flow


Number of position

Tengizchevroil 2011

Technical Supervision Execution Options


1. TCO direct hire the Technical Supervision Inspectors as part
of QA/QC team
2. TCO contract Company to provide Technical Supervision
service
3. Mixture of two previous option, split scope for Onshore
( Tengiz site) and Offshore (Fabrication) and select the
strategy for each one.
a) Tengiz - hire, Fabrication - Contractor
b) Tengiz hire( infrastructure), Fabrication (
offshore) & module hook up ( Tengiz)

Tengizchevroil 2011

Technical Supervision Execution Options


1. TCO direct hire the Technical Supervision Inspectors
as part of QA/QC team
Advantages: potential cheapest option, easy to
integrate the team.
Disadvantages: difficulties with manpower flexibility,
need different Inspectors for different scope ( Civil,
Mechanical)

Tengizchevroil 2011

Technical Supervision Execution Options


2. TCO contract Company to provide Technical
Supervision service
Advantages: great flexibility with a recourses and
share the liability with a contractor relating to the
technical supervision outcome.
Disadvantages: contracting processes are greatly
long.

Tengizchevroil 2011

Technical Supervision Execution Options


3. Mixture of two previous option, split scope for
Onshore (Tengiz site) and Offshore (Fabrication) and
select the strategy for each one.
a) Tengiz - hire, Fabrication - Contractor
Advantages: utilize existing recourses on site,
Disadvantages: problem with liability for the module
hook up scope on site.

Tengizchevroil 2011

Technical Supervision Execution Options


3. Mixture of two previous option, split scope for
Onshore ( Tengiz site) and Offshore (Fabrication)
and select the strategy for each one.
b) Tengiz hire( infrastructure), Fabrication (
offshore) & module hook up ( Tengiz).
Disadvantages: splitting the clear battery limit between the
team might be challenge.
Advantages: flexibility with recourses and no impact to the
current Tengiz infrastructure scope.

Tengizchevroil 2011

Plan for Technical Supervision on Fabrication


For the Fabrication scope is recommended to contract the
company(3) with similar experience, based on:
require enormous amount of the man-hours on the pick works spend
by Technical Supervision comply the RoK regulation and less in the end.
fabrication scope are require inspectors with specific skills and
experience.

To cover early stages of the GE scope I recommend to hire ( TCO


direct/CER) till new contractor mobilise to yard.
The vast majority of the Technical Supervision inspectors in
Kazakhstan is only Russian/kazakh speaking, therefore
recommended to integrate Technical Supervision team with Fab
RA.

Tengizchevroil 2011

10

RA Fabrication Plan
Documentation
FGP Regulatory Affairs Fabrication Execution Plan end of this year
FGP Fabrication Technical Supervision Procedure Q1 2016
GE Regulatory Affairs plan end of this year
ERSAI Regulatory Affairs Plan - under review
DSME Regulatory Affairs Plan Q1 2016
Systems & ITP
Define RA Fabrication deliverables in the the CMS and MsPlus -Q1 2016
Define RoK as built documentation for ITP end of this year
Staffing
Continue to interview the potential candidates for Fab team 2016
Prepare detail JD for each position - end of this year

Tengizchevroil 2011

11