Professional Documents
Culture Documents
Richard Molloy
Segment Sales Renewable Energy
25th June 2014
Presentation overview
Introduction
Electrical BOS a
definition
Component overview
typical SLD
Design considerations
Examples
G59/3 update
Future trends
AC Switchgear &
transformer
Building / Grid
connection & metering
Decision to be made at
early stage of system
design between using a
few central inverters or
multiple string inverters
Each type has BOS
design differences in
downstream element but
basic premise is the same
Design considerations
General:
Space / location
Access for installation and maintenance
UV stability
Cable routing
Ongoing production processes
Security
Electrical:
AC switchgear loading must use 0% diversity factor
Cable volt drop <1% increases cable size
Ensure terminal capacities can accept large cables
Lead times
Many BOS items can be on extended lead times
10
11
12
EREC G59/3
Released Sept. 13 mandatory w.e.f. 1st Dec. 14
Many minor revisions over G59/2 plus some
substantial ones
New performance requirements for type tested
generator units (inverters)
Type testing of inverters now accepted for a wider
range of applications (versus requirement for
dedicated additional protection and witness testing)
Changes to testing & commissioning requirements
Section 12 all very substantially revised and much of this section is new
13
Future trends
On-going reductions in cost
Standardisation of site electrical design
Increase in DC voltage
Increase in AC connection voltage
Introduction of grid stability requirements
Real-time reactive power control
Variable export power limits
Large scale energy storage solutions
14
15