You are on page 1of 15

Electrical BOS solutions for UK gridconnected PV systems

Richard Molloy
Segment Sales Renewable Energy
25th June 2014

2013 Eaton. All Rights Reserved.

Presentation overview
Introduction
Electrical BOS a
definition
Component overview
typical SLD
Design considerations
Examples
G59/3 update
Future trends

2013 Eaton. All Rights Reserved.

Electrical Balance Of System


The electrical
infrastructure required
to gather and combine
the DC power
generated by multiple
panels and provide a
single AC power feed
to the building and/or
the grid

2013 Eaton. All Rights Reserved.

Electrical SLD, 1.3MW Eaton Beaver Plant


Panels &
racking
DC combiners
DC cable
Inverters
AC cable

AC Switchgear &
transformer
Building / Grid
connection & metering

2013 Eaton. All Rights Reserved.

System design topology

Decision to be made at
early stage of system
design between using a
few central inverters or
multiple string inverters
Each type has BOS
design differences in
downstream element but
basic premise is the same

2013 Eaton. All Rights Reserved.

Design considerations
General:

Space / location
Access for installation and maintenance
UV stability
Cable routing
Ongoing production processes
Security

Electrical:
AC switchgear loading must use 0% diversity factor
Cable volt drop <1% increases cable size
Ensure terminal capacities can accept large cables

2013 Eaton. All Rights Reserved.

Design considerations large sites


Fault levels can be high
Ensure protective devices have sufficient fault current
breaking capacity
Especially problematic for string-inverter based sites

Inter-tripping requirements HV connected sites


The DNO is likely to have specific MV inter-tripping
requirements and this varies by DNO

Site earthing requirements


Ensure earthing is considered up-front

Lead times
Many BOS items can be on extended lead times

2013 Eaton. All Rights Reserved.

UK grid integration project locations

2013 Eaton. All Rights Reserved.

Complete containerised solution

2013 Eaton. All Rights Reserved.

1.5MW substation with t/x & POC

2013 Eaton. All Rights Reserved.

10

PV Distribution Board, 50 to 250kWp +


Includes lockable rotary
isolator, G59 protection
relay, contactor, MID
certified kWh meter with
RS485 comms and
commissioning socket
Available from 50kWp
up to 250kWp +
Options for number /
size / type of inverter
inputs

2013 Eaton. All Rights Reserved.

11

160kW PV-DB with 100mA Type A TP


RCBOs

2013 Eaton. All Rights Reserved.

12

EREC G59/3
Released Sept. 13 mandatory w.e.f. 1st Dec. 14
Many minor revisions over G59/2 plus some
substantial ones
New performance requirements for type tested
generator units (inverters)
Type testing of inverters now accepted for a wider
range of applications (versus requirement for
dedicated additional protection and witness testing)
Changes to testing & commissioning requirements

Section 12 all very substantially revised and much of this section is new

Changes to test sheet templates

2013 Eaton. All Rights Reserved.

13

Future trends
On-going reductions in cost
Standardisation of site electrical design
Increase in DC voltage
Increase in AC connection voltage
Introduction of grid stability requirements
Real-time reactive power control
Variable export power limits
Large scale energy storage solutions

2013 Eaton. All Rights Reserved.

14

2013 Eaton. All Rights Reserved.

15

You might also like