Professional Documents
Culture Documents
Chapter 3 Construction
Management Functions
Purpose of operating a business is
to earn a profit!
Chapter 3 Construction
Management Functions
To be successful a construction
company must:
Estimate the cost of construction
projects accurately
Predict the schedule of the work
Control the progress and
expenditures during construction
Complete projects safely and on time
Construction Management
Functions
Responsibility to construct the project:
in accordance with the plans and
specifications
to satisfy the customers cost, quality,
and time expectations
The project team is organized for the
purpose of accomplishing those
missions!
Owner Functions
Construction Management
Functions
Company level
Selecting the right jobs to bid
Preparing the cost estimate
Submitting the bid
Procuring the payment and
performance bonds
Scheduling the work
Securing project operating capital
Construction Management
Functions
Construction site level
Setting the standards for quality
and safety
Construction Management
Functions
Construction site level
Planning phase
Influence on Construction
Quality
Influence on Construction
Project Cost
Planning Phase
Select the designer
Define the project goals
Ensure the availability of sufficient
funds to complete the project
Select and purchase the project site,
Determine construction
procurement system and the form
of construction contract to be used.
Design Phase
Primary requirement for any facility
is that it must be safe!!
Building codes
Owner and A/E schedule design
reviews
schematic drawings
preliminary drawings
working drawings
Bid Phase
First step is to decide whether or not
to bid the job. Contractors are
generally limited in their ability to bid
by two factors:
their bonding capacity and
the policies of management
Policies of Management
Factors contractors consider in
deciding whether or not to bid a
particular project include:
Location of the work
personnel
Bid Preparation
Bid preparation is expensive!
In preparing a bid, contractors
must consider the costs of:
Equipment
Labor
Materials
Subcontractors
Bid Preparation
Consider the costs of:
Job and company overhead,
contingency, and profit
Should also consider the
Award Phase
Owner provides:
Builders Risk insurance
Successful bidder must provide:
Payment and performance bonds
Workers compensation insurance
Liability insurance
List of subcontractors
Detailed project schedule
Notice to Proceed
Contractor cannot begin the work
until the Notice to Proceed is
received so
Use the time between bid opening and
contract award for detailed pre-
project planning.
Pre-project planning
Planning how the work will
proceed and in what sequence
Construction procedures
Type of equipment to be used
Job access
Location of the field office and
storage areas
Final selection of subcontractors
and suppliers
Pre-project planning
Cash flow analysis should be
completed to determine if the
company needs to borrow money
Detailed project schedule is
prepared
Work break down (WBS) and
pay schedule are planned
Construction Phase
Size of the contractors on-site
project management organization
is a function of the size and
G e n e ra l
C o n tr a c to r
M e c h a n ic a l
E le c t r i c a l
P lu m b i n g
C o n c r e te
HVAC
S tr u c tu r a l
O th e r
T ra d e s
Construction Company
Team Functions
critical
Critical Activities
Critical activities are those that could
impact the cost of the work by at least
one half of one percent of the bid price:
For example, on a $1,000,000
project, any activity with a potential
for cost over-run or under-run of
$5,000 or more is by definition a
critical activity.
carefully
The other 80% will average
out
Project Control
Cost control
Cash Flow Analysis
Schedule Control
Material
Management
Cost Control
Possible corrective actions could include:
Adding additional trade workers or
crews
Adding or removing equipment
Working overtime
Bringing in additional subcontractors
Cost Control
Possible corrective actions could
include:
Making the job more efficient
Productivity
Q
Let R = Production rate T
R
Where: T is total time, Q is the
total quantity to be installed
The total cost is determined by the
equation:
C t = Ch T
Where Ct = total cost and Ch = cost
per hour, or
Ct = Ch (Q/R)
Cost
Time
Cost
Time
Cash Flow
Schematic
Diagram
Example 3.2
Schedule Control
Chapter 4
Critical path - By definition, activities
on the critical path will delay the
entire project if they are delayed
Physical progress can be compared
with the financial progress to
determine if the project is:
on schedule or late
over budget or under budget
Materials Management
Ensure that materials are delivered
in a timely manner to the site in the
quantity and quality required. When
materials arrive they are:
Counted
Inspected
if necessary, Tested
Materials Management
Must determine the latest order date
accounting for the:
shop drawing
Preparation
submission and
approval time
Materials Management
Too many materials stored on the site
can lead to problem of:
space allocation
weather damage
theft
Risk Management
Risks are inherent in construction
Industry is moving toward allocating
risks to the party most able to
control the specific risk
Managing risks means:
minimizing risks
insuring against risks
and sharing risks
Risk Management
Construction risks - inability of a
subcontractor to perform
Economic risks - cost escalation
Risk Management
Contractual and legal risks risks assigned by contract over
which the contractor has no control
Risk Management
Worker injured or killed
A job accident that injures the public
A construction vehicle is involved in
an accident off the project
Risk Management
Risks are best assumed by the
party with the ability to best
control the risk
The best way to manage risks is to
avoid them, but the construction
industry is characterized by risks!
Risk Management
Contractors manage risks by
purchasing insurance
Examining the contract language
addressing changed conditions
Assignment
Due next class
Chapter 3 Review Questions
3.5
3.10
3.15