Professional Documents
Culture Documents
Costs
FIGURE 8.1
Resource-Constrained Scheduling
resources are not adequate
Physical Constraints
Activities that cannot occur in parallel or are affected
by contractual or environmental conditions.
Resource Constraints
The absence, shortage, or unique interrelationship and
interaction characteristics of resources that require a
particular sequencing of project activities
Constraint Examples
materials
For example, chemicals for a scientific project,
concrete for a road project, survey data for a
marketing project.
equipment
For example, Earth moving tractor, a test rig
Copyright 2011 The McGrawHill Companies, Inc.
Classification of a scheduling
problem
Time-Constrained Project
Resource-Constrained Project
Is one in which the level of resources
available cannot be exceeded.
Resources are fixed, time is flexible:
inadequate resources will delay the project.
Botanical
Garden
FIGURE 8.3
Disadvantages
Loss of flexibility
that
occurs
Copyright
2011 The
McGraw- from reducing
Hill Companies, Inc.
slack.
Example 1
Risk Assumptions
Activities with the most slack pose the least
risk.
Reduction of flexibility does not increase
risk.
The nature of an activity (easy, complex)
doesnt increase risk.
Copyright 2011 The McGrawHill Companies, Inc.
Splitting
Splitting
A scheduling technique use to get a better
project schedule and/or increase resource
utilization.
Involves interrupting work on an activity to
employ the resource on another activity, then
returning the resource to finish the interrupted
work.
Is feasible when startup and shutdown costs are
low.
Is considered the major reason why projects fail
to meet schedule.
Copyright 2011 The McGrawHill Companies, Inc.
Splitting Activities
FIGURE 8.11
3. Resource bottlenecks
Shortages of critical resources required for multiple
projects cause delays and schedule extensions.
Types of costs
Direct Costs
Costs that are clearly chargeable to a specific
work package.
Labor, materials, equipment, and other
Project CostDuration
Graph
FIGURE 9.1
Time-Phased Budgets
A cost estimate is not a budget unless it is
time-phased.
Time phasing begins with the time estimate
for a project.
Time-phased budgets mirror how the
projects cash needs (costs) will occur or
when cash flows from the project can be
expected.
Budget variances occur when actual and
forecast events do not coincide.
Copyright 2011 The McGrawHill Companies, Inc.
Accelerating Project
Completion
When resources are constrained
Fast-Tracking/ concurrent activities
Critical-Chain- longest technical dependency
path
Reducing project scope
Compromise quality
Accelerating Project
Completion
Cost-time solutions focus on reducing
(crashing) activities on the critical path to
shorten overall duration of the project.
Reducing the time of a critical activity usually
incurs additional direct costs.
Activity Graph
FIGURE 9.2
Practical Considerations
Using the project costDuration
Graph
Crash times
Linearity assumption
Choice of activities to crash revisited
Time reduction decisions and
sensitivity
Copyright 2011 The McGrawHill Companies, Inc.