Professional Documents
Culture Documents
Assessment
Turbine Cycle
Performance Assessment
Slide No.1
Topics Covered
Turbine Cycle
Performance Assessment
Slide No.2
Turbine Cycle
Performance Assessment
Slide No.3
Turbine Cycle
Performance Assessment
Slide No.4
Turbine Cycle
Performance Assessment
Slide No.5
Turbine Cycle
Performance Assessment
Slide No.6
Turbine Cycle
Performance Assessment
Slide No.7
Turbine Cycle
Performance Assessment
Slide No.8
Turbine Cycle
Performance Assessment
Slide No.9
Load
Turbine Cycle
Performance Assessment
Slide No.10
Turbine Cycle
Performance Assessment
Slide No.11
Basis of PG Testing
Agreed procedure
PG Test Code (ASME-PTC 6 etc.)
Instrumentation Scheme
Heat Balance Diagram
All Guarantees are valid for brand new
condition
Turbine Cycle
Performance Assessment
Slide No.12
Turbine Cycle
Performance Assessment
Slide No.13
SIGNIFICANCE
Prime Customer Requirement
Fulfils The Contractual commitment
Financial Ramification
Reputation Of The Product
Design Validation Of Steam Turbine
Feed Back For Further Improvements In New Tenders
Identification Of Grey Areas
Closure Of Site Office
Strengthening Of Customers Confidence
Maximum Capability Under varied Operating Modes
Validation Of Plant Instrumentation
Turbine Cycle
Performance Assessment
Slide No.14
Turbine Cycle
Performance Assessment
Slide No.15
Performance Benchmarking
Best achievable performance of Unit
Unit Specific
Original HBDs are valid for brand new original condition
Actual Cycle conditions may differ from design condition
Terminal steam parameters
Reheat Circuit Pressure Drop
Extraction Line Pressure Drop
Cooling water inlet temperature/Condenser Vacuum
Regenerative Feed heater out of service
Turbine Cycle
Performance Assessment
Slide No.16
Turbine Cycle
Performance Assessment
Slide No.17
Turbine Cycle
Performance Assessment
Slide No.18
Stages of PG Testing
Pre PG Test Stage
Activities involved are
Checking of Unit Healthiness
Shutdown for PG Test Preparation
Attending the Valves Leaking /Passing
To install Flow Nozzle
Making the unit ready for Test
Turbine Cycle
Performance Assessment
Slide No.19
Stages of PG Testing
Preliminary Activities involved before
commencement of PG Test are
Mock Test to ascertain the availability &
correctness of required Instrumentation.
Rectification if any required
Preliminary PG Test preferably at full load
Calculation & Analysis of Heatrate & output
based on preliminary PG Test
Discussion with customer/consultant for
proceeding further for Final PG Test
17th January 2014
Turbine Cycle
Performance Assessment
Slide No.20
Stages of PG Testing
Pre Final PG Test activities
Ensure Closing of Valve as per Valve Isolation List at least 1/2
hour prior to start of test.
Terminal Parameters nearer to rated as indicated in the
corresponding HBDs
Steady load condition at least three hours prior to test
Steady Terminal Parameters. Fluctuations within specified limits
TG Regenerative Feedheating Cycle corresponding to HBDs &
Steady.
Alternate drain lines to HP/LP Heaters should be closed
Steam from & to Common Auxiliary header should be closed
Makeup supply to Deaerator feedstorage Tank & Condenser
hotwell closed
Turbine Cycle
Performance Assessment
Slide No.21
Stages of PG Testing
Final PG Test activities
Ensure the steadiness & consistency of Load & all
parameters for next two to three hours
Ensure Data Capturing of all instrumentation in
Datalogger at regular interval.
Ensure completeness of all readings.
Data capturing of all tank levels & other supplementary
control room reading.
Measurement/Estimate of all external leakage in the
TG/SG Cycle during the test
Repeat the Test at the same load in the same setting
17th January 2014
Turbine Cycle
Performance Assessment
Slide No.22
Major Issues
Turbine Cycle
Performance Assessment
Slide No.23
Malfunctioning of equipments
Major factors affecting the performance
1. Steam Turbine
Worn-out Glands of HP/IP & LP Front
Rear shaft sealing
&
Turbine Cycle
Performance Assessment
Slide No.24
Malfunctioning of equipments
Major factors affecting the performance
1. Steam Turbine
Steam leakage through parting plane,
bellows, hoses
Leakage through MAL Valves
Poor cylinder internal efficiency
Variation in First stage pressure
characteristic
17th January 2014
Turbine Cycle
Performance Assessment
Slide No.25
Malfunctioning of equipments
Major factors affecting the performance
2. Regenerative Feed Heating Cycle
Level variation in heaters
Improper cascading of drains
HP/LP Bypass in operation/passing
Higher system leakage & Makeup
Superheater & Reheater spray
Poor efficiency of CEP/ BFP/ BFPT
17th January 2014
Turbine Cycle
Performance Assessment
Slide No.26
Malfunctioning of equipments
Major factors affecting the performance
2. Regenerative Feed Heating Cycle
Cleanliness of condenser
Turbine Cycle
Performance Assessment
Slide No.27
Turbine Cycle
Performance Assessment
Slide No.28
Turbine Cycle
Performance Assessment
Slide No.29
Turbine Cycle
Performance Assessment
Slide No.30
VWO Philosophy
VWO margin is kept by the designer over and above Name plate
rating so as to
Ensure guaranteed power output of the set.
Machine should generate name plate rating throughout the
entire life of the set.
It is designers margin to accommodate manufacturing / Erection
/ Commissioning & Ageing tolerance
VWO margin of 5% is based on Siemens design practice
It comprises of 2.5% ageing tolerance plus 2.5% manufacturing
tolerance.
All manufacturing drawings have +/- tolerance on the
dimensions.
It can be reduced but can not be made Zero.
Ageing of the machine is a physical unavoidable phenomenon.
Interval between two overhaul is decided based on limiting the
ageing to 2.5% maximum.
After Overhaul part of the performance deterioration is restored.
17th January 2014
Turbine Cycle
Slide No.31
Performance Assessment
VWO Philosophy
There is no time restriction to run the unit at VWO
continuously.
But
VWO Output & Steam Flow can not be guaranteed.
None of the international standard recommend it
As per Customer Specification
Power Output is guaranteed at 100% Maximum Continuous
Rating (MCR), 3% Makeup & worst Vacuum
Intent of this requirement is to ensure Name Plate Rating
even with worst Back Pressure & makeup.
Turbine Cycle
Performance Assessment
Slide No.32
RH/SH Spray
Use of SH /RH Spray is made to control
SH/RH outlet temperature.
Normally it is sourced from BFP discharge
Thermodynamically it is loss to the cycle.
Not only does it deteriorate the Unit
Heatrate but also affects the TG Cycle
performance.
Therefore it is best avoided.
Turbine Cycle
Performance Assessment
Slide No.33
How?
RH Spray is the quantity of Feedwater not doing any work in HP Turbine but
joining in IP & LP Turbine.
This results change in the internal power distribution between HPT & IP/LPT.
Turbine Cycle
Performance Assessment
Slide No.34
Turbine Cycle
Performance Assessment
Slide No.35
Turbine Cycle
Performance Assessment
Slide No.36
Ageing Trends
Turbine Cycle
Performance Assessment
Slide No.37
Turbine Cycle
Performance Assessment
Slide No.38
System Leakages-1
Higher cycle leakage implies enhanced DM
water requirement.
System losses is generally found to be around
0.8 to 1.5 % of the main stream flow while as per
international practice it should be within 0.1 %.
Conduction of PG Test just after
synchronization may resolve this problem to
some extent .
Delay in testing may also result more repair
/replacement of valves passing /leaking.
Generally Unit healthiness is carried out jointly
to identify leaking/passing valves.
17th January 2014
Turbine Cycle
Performance Assessment
Slide No.39
System Leakages
These valves are also attended in the shutdown
arranged by the customer.
By the time PG Test starts many new leakages
develops resulting to enhanced system leakages.
It may not be practical for the customer to provide
another Shutdown and incur generation loss.
It has also observed that System leakage quantity is
independent of Load as it is directly proportional to
fluid pressure.
Customer may take shutdown at their convenience
clubbing other activities.
Turbine Cycle
Performance Assessment
Slide No.40
Turbine Cycle
Performance Assessment
Slide No.41
THANK YOU
17th January 2014
Turbine Cycle
Performance Assessment
Slide No.42