Professional Documents
Culture Documents
03/20/15
INTRODUCTION
THE ELECTRIC SUB STATION
03/20/15
M L SHESHADRI
INTRODUCTION
THE ELECTRIC SUB STATION
03/20/15
M L SHESHADRI
INTRODUCTION
THE ELECTRIC SUB STATION
03/20/15
M L SHESHADRI
INTRODUCTION
03/20/15
M L SHESHADRI
DESIGN CONSIDERATIONS
03/20/15
M L SHESHADRI
DESIGN
THECONSIDERATIONS
ELECTRIC SUB STATION
03/20/15
M L SHESHADRI
DESIGN CONSIDERATIONS
M L SHESHADRI
8
8
M L SHESHADRI
Since the major sub station costs are reflected in the power
transformers, circuit breakers and disconnecting switches, the bus
layout and switching arrangement selected will determine the
number of switches and power circuit breakers required.
A number of factors must be considered in the selection of bus
layouts and switching arrangements for a sub station to meet
system and station requirements.
A sub station must be reliable, economical, safe, and as
simple in design as possible.
9
9
10
10
M L SHESHADRI
03/20/15
11
11
M L SHESHADRI
03/20/15
12
12
03/20/15
M L SHESHADRI
Safety of personnel.
Protective zones for main and back up
protection.
Provision for bye pass facilities and for
extensions, space requirements.
Technical requirements such as ratings,
clearances, earth system, lightning protection.
Requirement for SCADA and communication.
Compatibility for local and ambient condition.
13
13
03/20/15
M L SHESHADRI
14
M L SHESHADRI
03/20/15
VARIOUS
BUS BARSUB
SCHEMES
THE ELECTRIC
STATION
ISOLATO
R
M L SHESHADRI
BUS
03/20/15
BREAKE
R
CURRENT TRANSFORMER
POWER TRANSFORMER
16
16
Disadvantage:
M L SHESHADRI
Advantage
03/20/15
17
17
BUS SECTION-2
SECTIONALISER
ISOLATO
R
BREAKE
R
CURRENT
M L SHESHADRI
BUS SECTION-1
03/20/15
TRANSFORMER
POWER TRANSFORMER
18
18
M L SHESHADRI
19
19
M L SHESHADRI
BUS-2
03/20/15
BUS-1
BUS COUPLER
BREAKER
BREAKER
POWER TRANSFORMER
20
20
M L SHESHADRI
03/20/15
21
21
22
22
BAY1
BAY2
T/F-2
BAY6
BAY4
BUS COUPLER
BUS-1
BAY7
BUS-2
BAY3
FEEDER1
FEEDER2
BAY5
FEEDER3
FEEDER4
23
BREAKER
M L SHESHADRI
TIE
BREAKER
TRANSFER BUS
LINE
LINE
24
24
03/20/15
M L SHESHADRI
25
Wherever maintenance is required on any breaker, the circuit is changed over to the
transfer bus and controlled through the bus coupler breaker.
Potential devices may be used on the main bus for relaying.
M L SHESHADRI
03/20/15
The cost is increased due to use of an extra isolator for each circuit and providing
interlock for bus coupler and circuit isolators.
Relaying sensitivity decreases as the same bus coupler is used to energize the
concerned circuit for all the circuit breakers whenever they are taken out for maintenance.
Failure of bus or any circuit breaker results in shut down of entire sub station.
26
26
T/F-2
BUS-2
BAY3
BAY1
BAY2
FEEDER1 FEEDER2
BAY4
TRANSFER BUS
BAY5
TRANSFER BUS
COUPLER
BUS COUPLER
BUS-1
BAY6
BAY7
BAY8
FEEDER3 FEEDER4
27
BREAKER
M L SHESHADRI
BUS-1
BUS-2
29
LINE
LINE
29
30
30
BREAKER
LINE
M L SHESHADRI
ISOLATOR
POWER TRANSFORMER
LINE
31
31
In this scheme
THE the
ELECTRIC
STATION
breakers areSUB
arranged
in a ring with
circuits connected between breakers.
M L SHESHADRI
32
For an extended circuit outage, the line isolator may be opened and the ring
can be closed.
No changes to protective relays are required for any of the various operating
conditions or during maintenance.
M L SHESHADRI
The circuits connected to the ring are arranged so that sources are alternated
with loads.
03/20/15
The ring bus scheme is economical in cost, has good reliability, is safe for
operation, is flexible, and is normally considered suitable for important sub
stations up to a limit of five circuits.
It is common practice to build major sub stations initially as a ring bus; for more
than five outgoing circuits, the ring bus is usually developed to the breakerand-a-half scheme.
33
33
ISOLATOR
03/20/15
BUS-1
M L SHESHADRI
BREAKER
LINE
TIE BREAKER
35
BUS-2
35
I-CONFIGUARATION
DIA4
FEEDER11
DIA5
DIA6
BAY2
BAY5
BAY8
BAY11
BAY14
BAY17
BAY3
BAY6
BAY9
BAY12
BAY15
BAY18
BAY13
DIA3
FEEDER9
BAY16
FEEDER7
BAY10
DIA2
BAY1
BUS-1 DIA1
FEEDER5
BAY7
FEEDER3
BAY4
FEEDER1
BUS-2
36
FEEDER2
FEEDER4
FEEDER6
FEEDER8
FEEDER10
FEEDER12
D-CONFIGUARATION
FEEDER5
FEEDER10
BAY14
BAY13
BAY7
DIA1
FEEDER9
BAY8
BAY3
BAY1
BAY2
FEEDER6
DIA3
BAY15
FEEDER2
BAY9
FEEDER1
DIA5
BUS-1
BAY5
FEEDER3
BAY11
FEEDER4
FEEDER7
DIA6
BAY18
BAY16
DIA4
BAY12
BAY10
DIA2
BAY6
BAY4
BUS-2
BAY17
FEEDER8
FEEDER11
FEEDER12
37
M L SHESHADRI
03/20/15
38
38
M L SHESHADRI
39
THANK YOU
03/20/15
ANY QUESTIONS ?
M L SHESHADRI
41
41