Professional Documents
Culture Documents
Scheduling
Resources
and Costs
82
83
FIGURE 8.1
84
Resource-Constrained Scheduling
The duration of a project may be increased by
delaying the late start of some of its activities if
resources are not adequate to meet peak demands.
85
Physical Constraints
Activities that cannot occur in parallel or are affected by
contractual or environmental conditions.
Resource Constraints
The absence, shortage, or unique interrelationship and
interaction characteristics of resources that require a particular
sequencing of project activities
86
Constraint Examples
FIGURE 8.2
87
Time-Constrained Project
Must be completed by an imposed date.
Time is fixed, resources are flexible: additional resources
Resource-Constrained Project
Is one in which the level of resources available
cannot be exceeded.
Resources are fixed, time is flexible: inadequate resources
88
Risk Assumptions
Activities with the most slack pose the least
risk.
810
Botanical
Garden
FIGURE 8.3
811
Disadvantages
Loss of flexibility that occurs from reducing slack.
Increases in the criticality of all activities.
812
813
FIGURE 8.4
814
FIGURE 8.5
817
Problem
There are only eight design engineers who can be
assigned to the project due to a shortage of design
engineers and commitments to other projects.
820
EMR Project:
Network View
Schedule before
Resources Leveled
FIGURE 8.6
821
FIGURE 8.7
822
FIGURE 8.8A
823
FIGURE 8.8B
824
EMR Project
Network View
Schedule
after Resources
Leveled
FIGURE 8.9
825
FIGURE 8.10
826
Splitting
Splitting
A scheduling technique for creating a better project
schedule and/or increase resource utilization.
Involves interrupting work on an activity to employ the
schedule.
828
Splitting Activities
FIGURE 8.11
829
830
3. Resource bottlenecks
Shortages of critical resources required for multiple
831
832
833
FIGURE 8.12
834
FIGURE 8.13
835
FIGURE 8.14
836
FIGURE 8.15
837
FIGURE 8.16
838
FIGURE 8.17
839
FIGURE 8.18
840
Key Terms
Heuristic
Leveling
Planned value (PV)
Resource-constrained projects
Resource smoothing
Splitting
Time-constrained projects
Time-phased budget baseline
841