Tarasafe Garment Unit

Apparel park, Khokhra, Ahmedabad


Current Status Planned Status
Unplanned events
Labour short-supply
1.5 months
Plinth masonry over
entire tie beam grid
Compartment filling & compaction is
taking 3x more time
Unplanned work of
approx. Rs. 10 lacs
Resulted delay caused filling activity
to be executed during rain
Short supply of earth and
sand during rain
Supplier strike since last
week
Planned Actual
Bottlenecks
Ensuring daily line of
work for Min. 90
labours.
MIS & Actions
Finalization of Concreting &
related items
Finalization of Concreting & related items
Scenario - 1 Scenario - 2 Scenario - 3
Concrete finish Conventional concrete finish Semi exposed finish Semi exposed finish - steel plate
pattern in slab
Formwork Contractor formwork (Conventional) Client supplied plywood,
contractor supplied wall plates,
patties etc.
Client supplied plywood, contractor
supplied steel plates, wall plates,
patties etc.
Supporting structure H frame / Cuplock H frame / Cuplock H frame / Cuplock
All slabs and beams All slabs and beams in plywood All slabs in steel plates & all beams
in plywood
Costs
Plastering 8,71,200 - -
Painting 5,54,400 - -
Plywood - 14,70,000 7,35,000
Rendering - 15,84,000 15,84,000
Alt. 1 With Mixture machine
Concreting conventional 46,87,500 46,87,500 46,87,500
Cement 13,05,000 13,05,000 13,05,000
With Mixture machine 74,18,100 90,46,500 83,11,500
Alt. 2 With RMC
Labour rate with
shuttering 3125000 3125000 3125000
RMC cost 4500000 4500000 4500000
With RMC 90,50,600 1,06,79,000 99,44,000
Conclusion
Alternate 1 will take about 310 days to
complete.
Alternate 2 will take about 190 days to
complete.
Incremental costing is about Rs. 16,32,500/-
Savings of more than 120 days.
Impacts of Alternative-2
Consistent quality of concrete as it is produced in
controlled environment of batching plant.
No worry about w/c ratio and concrete strength.
Can be done in nights.
Min. 10,000 sq.ft. of shuttering set is required to
achieve desired cycle. (approx. 33% of total GF slab
area)
100 cu.m. of concreting in a single day.
Min. Labour requirement 90 labours
Bar benders 15 pair
Carpenters 15 pair
Other labours 30 nos.

MIS and Actions