The document discusses the issue of load shedding in Pakistan. It outlines the historical background of power supply and demand. Several reasons are provided for the current shortage, including late finalization of power policies, reliance on unsolicited power proposals, and lack of emphasis on alternative energy. Suggested remedies include developing alternative energy sources, using coal for power generation, and improving energy conservation and efficiency.
The document discusses the issue of load shedding in Pakistan. It outlines the historical background of power supply and demand. Several reasons are provided for the current shortage, including late finalization of power policies, reliance on unsolicited power proposals, and lack of emphasis on alternative energy. Suggested remedies include developing alternative energy sources, using coal for power generation, and improving energy conservation and efficiency.
The document discusses the issue of load shedding in Pakistan. It outlines the historical background of power supply and demand. Several reasons are provided for the current shortage, including late finalization of power policies, reliance on unsolicited power proposals, and lack of emphasis on alternative energy. Suggested remedies include developing alternative energy sources, using coal for power generation, and improving energy conservation and efficiency.
February 9, 2009 By Muhammad Ziauddin Organization Historical Background Load duration curve Capacity, capability & availability Shortage Reasons Remedies / Suggestions Historical Background Pre 1994 era Sever load shedding Post 1994 era Surplus power in the system 2002 Power Policy Lengthy procedure Approval of feasibility Tariff negotiation & approval Security packages High load growth Current Situation Supply / Demand Balance Load duration curve Capacity, Capability and Availability Demand Supply
Power Supply/Demand Balance 0 5,000 10,000 15,000 20,000 25,000 30,000 35,000 40,000 45,000 50,000 55,000 60,000 65,000 70,000 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 Year D e m a n d / S u p p l y
( M W ) Demand Supply Load Duration Curve 18th August 2007 9,000 10,000 11,000 12,000 13,000 14,000 15,000 16,000 17,000 010002000300040005000600070008000900100011001200130014001500160017001800190020002100220023002400 Time in hrs L o a d
i n
M W Computed System Demand Actual Load Supplied Actual Availability Load Duration Curve 21st August 2008 9,000 10,000 11,000 12,000 13,000 14,000 15,000 16,000 17,000 18,000 0100 0200 0300 0400 0500 0600 0700 0800 0900 1000 1100 1200 1300 1400 1500 1600 1700 1800 1900 2000 2100 2200 2300 2400 Time in hrs L o a d
i n
M W Computed System Demand Actual Load supplied Acutal Availability Load Duration Curve 10th January 2007 5,000 6,000 7,000 8,000 9,000 10,000 11,000 12,000 13,000 010002000300040005000600070008000900100011001200130014001500160017001800190020002100220023002400 Time in hrs L o a d
i n
M W Computed System Demand Actual Load Supplied Actual Availability Load Duration Curve 23rd January 2008 5,000 6,000 7,000 8,000 9,000 10,000 11,000 12,000 13,000 010002000300040005000600070008000900100011001200130014001500160017001800190020002100220023002400 Time in hrs L o a d
i n
M W Computed System Demand Actual Load supplied Acutal Availability Reasons Late finalization of 2002 power policy Late initiation of new projects Long processing time Not soliciting new power plants Reliance of unsolicited proposal WAPDA was not allowed to install thermal power plants Private sector started taking advantages Availability of machines in the international market
Reasons (contd) No serious efforts on effeciency improvement and energy conservation Time of day metering system is not up to its strength Hydropower not comming up Small hydro power plants are not being taken up by WAPDA Closure of some IPP & WAPDAs power plants Not payment of fuel bills to fuel suppliers
Reasons (contd) International investors are not comming with enthusiasm International recession Governace issue No serious efforts to exploit alternative energy resources Huge reserve of coal is not being used Issues Most of the new thermal power plants are based on fuel oil Cost of electricity generations Fuel imports major implecations on forx reseve Volatility of crude oil prices Fuel transporation and import infrastructure Road / railway network Port facilities
Issues (contd) Gas is not available for new power plants Un efficient energy useage No incentive from the government to develop alternative energy resources Rental power plant is sucidal
Remedies / Suggestions Development of alternative energy The Regulator should be linient in tariff for wind and solar power plants Manufacturing facility for wind and solar power plants be encouraged by the government Coal should be used for power generation including imported Coal Thermal power plants should be installed by WAPDA in parllel to IPPs More emphasis should be on energy conservation and efficiency improvement
Remedies / Suggestions (contd) Time of day tariff should be implemented in all catagories of consumers A digonostic study should be conducted for oil transporatation infrastructure and port facilities Captive power plant should brougt on bar Industrial sector should be encouraged to install their own power plants and surplus should be purchased by WAPDA at a competitive price Thanks