Project Overview Installation of a N.G.H.P Offshore Pipeline with the purpose to supply natural gas to Evia island and a Power Plant in Aliveri. Size of the pipeline :20 Total length of the Pipeline approximately 14.2 km Maximum water depth along the pipeline route: 70m. Offshore pipeline was consist of two offshore sections, joined together offshore by Above Water Tie In method.
Asprofos Services 5 Main purpose is to provide assurance to the Client. Review of Plans, Procedures, Method Statements etc. Review the field engineering output, Review the procurement process/attendance in deliverance etc. Monitor if the HSE procedures are fulfilled, Technical support to the Client in its dealing with the Authorities, Contract administration services (EPC contract). Management Services (N/A)
The Team The Team was divided into two (2) sub teams. The Supervising Engineering Team (Field): Site Construction Supervision Head Site Offshore Pipeline Supervising Engineer Site Shore Approach Supervising Engineer Site Engineer
Management/Review /Support Team (Head Offices): Project Management Pipeline Specialists
6 Main Documents Review Project Management Documents: Project Overview Manual, Quality Manuals, Project Control Docs, Projects HSE Docs etc Design Engineering Documents: PIPELINE ON BOTTOM STABILITY ANALYSIS PIPELINE FREE SPAN ANALYSIS CATHODIC PROTECTION PHILOSOPHY AND DETAILED DESIGN REPORT PIPELINE PROTECTION DESIGN TECHNICAL SPECIFICATION FOR SACRIFITIAL ANODES GEOTECHNICAL CROSS SECTIONS VESSEL POSITIONING PROCEDURE SURVEY REPORT & CHARTS (PRE LAY AS LAID) FLOODING, CLEANING, GAUGING AND HYDROTESTING PROCEDURE PIPELINE ABOVE WATER TIE IN MANUAL
7 Main Documents Review Design Engineering Documents: SHORE APPROACH METHOD START-UP MOORING ARRANGEMENT SHORE PULL SEQUENCE PIPELINE AWTI SEQUENCE PIPES TRANSPORTATION (METHODS) PRE-LAY SURVEY CHARTS FOR ANCHOR CORRIDOR GEOTECHNICAL STUDY FOR THE TRENCH DREDGING AND BACKFILL PRE-LAY SURVEY AT LANDFALLS TRENCHING AND BACKFILLING MANUAL WAVE PREDICTION STUDY WAVE PREDICTION STUDY AT LANDFALL POINTS WELDING COATING PROCEDURE
8 9 Main Field Activities Sequence Pipe/Material/Equipment Deliverance. Installation of Anchors and Concrete Blocks. Dredging Activities Mooring Activities Welding/Sandblasting/Coating Activities Shore Pull Activities Normal Pipe Laying AWTI Backfilling/Wave Protection/ Reinstatement 10 Main Field Activities 1. Pipe/Material/Equipment Deliverance.
11 Main Field Activities 2. Anchoring - Mooring.
12 Main Field Activities 3. Dredging Activities
13 Main Field Activities Trench Long. Profile 4. Welding/Sandblasting/Coating Activities
14 Main Field Activities 15 Main Field Activities 5. Shore Pull Activities
16 Main Field Activities - Shore Pull Sequence
17 Main Field Activities 6. Normal Pipe Laying
18 Main Field Activities 7. AWTI
19 Main Field Activities AWTI Stress Analysis 20 Main Field Activities 8. Backfilling/Wave Protection/ Reinstatement
21 Wave Protection Design
22 284, EL. VENIZELOU str. GR-176 75 KALLITHEA ATHENS, GREECE