& sufyan saleem Dept, of electrical engineering bahaudian zakariya university Multan , Pakistan
1 DEPARTMENT OF ELECTRICAL ENGINEERING UCE&T BZU MULTAN HV Distribution System 1. Radial System 2. Closed Loop System 3. Open Loop System 4. Double Supply System 5. Grid Form Of HV System 6. Improved Radial System LV Distribution System 2 Primary distribution system is that part of the electric distribution system between distribution substation and distribution transformers. It is made up of circuits called primary feeders or distribution feeders. 3 4 In this system all the sections/branches of a feeder are fed from a single source in a fixed direction
5 Load Load Load Generator In this it is shown that there are two primary feeders from which further subfeeders supply to there respective loads. If any one of the feeder becomes faulty then supply through that feeder has to cut so no reliability 6 Merits Reasons Simple in design, construction, operation and maintenance Suitable size of conductor. Very simple protection schemes. Maintenance easy. Easy fault current calculations.
cheapest system No extra length of line and switching arrangements required. Less capital cost as different sizes of conductors can be used. As no alternative arrangements are necessary so shortest route can be adopted hence cost saving As used in rural areas so large spans can be used which further reduces cost
7 Demerits Reasons Very poor service reliability In case of fault on a feeder the supply to consumers from those feeders is cutoff and restored on fault removal. Excessive voltage drop and line losses Due to passage of total current through the common main section of the feeder, voltage drop(IR) and line losses will be more as compared to the system which facilitates distribution of load currents into two or more paths 8 It is considered more suitable for the areas with low density of load involving long distances and requiring low degree of availability. 9
10
5 132KV
4
Grid Station
11KV
3
2
Distribution Transformer
1
5
3
11KV 2
Distribution Substation
0.4KV
1
What is closed loop system? If a HT line emanating from a Grid station and covering the load area in shape of a loop, finishes at the same Grid station returning to same breaker or another independent breaker it is called closed loop and the system is called closed loop system. In this system each transformer has two sectinalizers, one on either side of the transformers tap-off point.
Typical wapda closed loop system Bus bar Station circuit breaker Sectionalizing switch closed transformer Load Sectionalizing switch closed Merits of closed loop system 1. This system is more reliable than radial system. At fault breaker at grid station opens. After tracing the fault the faulty section is isolated, and supply to remaining section is restored. The consumers dont have to wait very long till the rectification of the fault as in the case of Radial system. In case of two simultaneously faults, the consumers have to wait much till the rectification of the fault of at least one section. But possibility of two simultaneously faults is less. It is usually preferred that there must be two breakers instead of one. 2. Less voltage drop, less line losses As compared to radial system the voltage drop and line losses is less.
De merits of closed loop system This is an expensive system because of the following reasons.
It requires extra length of loop to complete the loop back to sub- station. Each transformer has to be provided with two sectionalizers , in absence of which the loop does not sere any purpose. In emergency total load of loop may have to be served from one side of loop, so higher size conductors are required to carry twice the current. Cost increases. Similarly in low load section the load during emergency must be more than 50%. They are used for small loops, If loop size is so large then the fault location time may exceed up to 5 to 6 hours. and if consumers are without electricity for this time then there is no justification to install such a system Application
It is usually recommended for HIGH density areas where distances are small. preferably for urban areas.
This system can be equally useful for rural areas where economy so permits. But to ensure effectiveness the loop should be of small size.
UNIVERSITY COLLEGE OF ENGINEERING & TECHNOLOGH, B.Z.U. OPEN LOOP SYSTEM In a closed-loop system with two breakers( one at each end), if one of the two sectionalizers of low-load-section is kept normally open, the system is named as open-loop system. COMPARISON b/w CLOSED-LOOP & OPEN-LOOP SYSTEM CLOSED-LOOP
OPEN-LOOP
If fault occurs, the supply of the whole loop goes off. The effect of fault is limited to faulty part, as one circuit breaker operates. Total loop has to be patrolled for fault location.
The faulty part of the loop is clearly known.
ADVANTAGES Economical Availability of service is improved Locating fault is easy
TRANSFORMER SECTIONALIZING SWITCH (OPEN) SUBSTATION BUS SECTIONALIZING SWITCH (CLOSED) STATION CIRCUIT BREAKER OPEN LOOP SYSTEM HRC FUSE Load Double Supply System Additional radial feeder is provided side by side to feed the same consumer.
Using automatic change over switches.
Duplicate supply system or parallel feeders.
Substation Bus Circuit Breaker Sectionalizing switch F U S E
TRANSFORMERS LOAD LOAD Merits and Demerits Advantages Disadvantages Higher service reliability. Very Expensive Extra feeders are installed which doubles the cost. Cost of sectionalizers. Additional length of line needed to connect the feeder to the transformer. Less line losses. Reduced Safety GRID FORM OF H.V SYSTEM In this system all the distribution transformers of a load area, are interconnected providing normally two or more alternatives. while the whole system is fed from two or more bulk supply sources. But availability can not be improved through manual operation of sectionalizer to isolate faulty section during emergency as it will take quite a considerable time to identify the faulty section and to determine the better alternative. as manual operation may result in wrong operation due to complexity of the system so to have a real benefit of this system, automatic switching arrangements with sophisticated protection schemes should be provided including establishment of a remote control center. C.B C.B C.B C.B C.B C.B C.B C.B C.B C.B C.B C.B C.B C.B C.B C.B C.B C.B C.B C.B C.B C.B C.B C.B C.B C.B C.B C.B C.B C.B C.B C.B C.B C.B C.B C.B C.B C.B C.B C.B STEP DOWN TRANSFORMER C.B C.B 11KV BUS BAR 132KV BUS BAR DISTRIBUTION TRANSFORMER C.B C.B C.B C.B 400 VOLT 400 VOLT
SINGLE LINE DIAGRAM OG GRIF FORM OF H.V-DISTRIBUTION SYSTEM Merits Most reliable because normally no possibility of failure of supply and availability is almost 100%. In case of two simultaneous faults, service to the consumers will not be affected at all, or effect will be limited. Demerits It is most costly system.
Applications The system being the most reliable, and at the same time the most costly, is recommended for the areas of highest priority of supply with very high load density. If the economy for a county is not a problem, this system is considered the most suitable one for urban areas, specially the big cities In this system we use sectionalizers so that in case of fault on one feeder a part of that can fed by other. 31 Usually Radial system is used due to following reasons:
As LT lines feed only one or few consumers so in case of fault only few consumers are affected. Simplest and cheapest.
In some important areas Open loop and Closed loop systems might also be used.
In This Scheme, Three Circuit Breakers Are Used For Controlling Two Circuits Which Are Connected Between Two Bus Bars. Normally, Both The Bus Bars Are in Service