You are on page 1of 6

BUSINESS RESEARCH CENTER

MUHAMMAD IRFAN-2784
FAROOQ QAISAR
WAQAS ULLAH SHAH-2854
ARSHAD SIDDIQUE
Cost & Time for Business Research Center
Main Activities Time = 52 Weeks = 1 Year Cost = 60000000
Initiating 5 Weeks 1040000
Construction 24Weeks 20000000
Procurement 4 Weeks 20000000
Human Resource 3 Weeks 7000000
Utilities 6 Weeks 5000000
Closing = 42 Weeks = 53040000
Remaining = 10 Weeks = 6960000
Objective of Business Research Center


The BRC wishes to engage faculty from other departments in the university when
appropriate research projects arise.

To become a research resource for local and regional organizations. Since the
emphasis of the BRC on applied research, outside organizations are expected to be
the primary source of research projects.

The BRC will provide services to organizations when the educational objectives of
the BRC are compatible with the research objectives of an organization.

The BRC to provide applied educational experiences to students in a variety of
research areas related to business. The research areas include but are not limited to
the following: human resources, marketing, operations, finance, accounting,
business law and security, management information systems and economics.

Justification and Background of the Project
PURPOSE
To understand the Benefits and Challenges of having Business Research Center in the
University, and to explore Institutional Strategies that Capitalize on the Strengths and to
improve the Weaknesses of the University.
IMPACT
University will offer a number of benefits to other academic institutions.

Research Center can aid in faculty recruitment and retention, facilitate collaboration in
research, secure research resources, offer a sense of community and promote continued
learning, afford organizational flexibility, and focus on societal problems and raise funds.

Research center can also create tensions and present management challenges to
institutional leaders.

Research Center in the University will increase the ranking of the University
BUSINESS RESEARCH
CENTRE
DURATION : 1 YEAR
COST : 60 MILLIONS
INITIATING
DURATION : 1 MONTH
TOTAL COST : 1.4
CRORE.
PROJECT CHARTER
DURATION : 1 WEEK
COST : 1 LAC
LOCATION
DURATION : 1 WEEL
COST : NIL
BUILDING DESIGN
DURATION : 1 WEEK
COST : 3 LAC
CONTRACTOR
DURATION : 2 WEEKS
COST : 1 CRORE
CONSTRUCTION
TOTAL DURATION :
TOTAL COST :
EXTERNAL CONSTRUCTION
DURANTION 100
weeks:
COST :
RAW MATERIALS
DURATION :
COST :
INTERNAL CONSTRUCTION
DURATION :
COST :
CEALING
DURATION :
COST :
WINDOWS AND DOORS
DURATION :
COST :
FLOUR
DURATION : COST :
INSTALL CABINET
DURATION :
COST :
LAY TILES
DURATION :
COST :
PROCUREMENT
TOTAL DURATION :
COST ::2CAROR
INFRASTRUCTURE
DURATION :
COST :1 CAROR
EQUIPMENTS
DURATION :
COST :1CAROR
HUMAN RESOURCE
MANAGEMENT
DURATION:2WEEK
ACQUIRE PROJECT TEAM
DEVELOP PROJECT TEAM
MANAGE TEAM WORK
UTILITIES
ELECTRICITY
AIR CONDITION
INTERNET AND
NETWORKINGSYSTEM
CLOSING
CLOSING PROJECT

You might also like