Professional Documents
Culture Documents
Intermittent Flow
Low Reservoir Pressure
Graphical Method
Unloading line method
2. Intermittent Design
Fallback method
Percent load Method
Design Parameter
Out flow Curve
Temperature profile
Fluid Velocity
Outflow Correlation
Duns and Ros (Large diameter tubing, high GLR, low & mist flow rates)
Orkiszewski
(Slug flow, moderate liquid volume fractions) Griffith and Wallis (High liquid volume , low GLR)
Gas Gradient
gas density(Ib/Ft3 ) G-grad.(Psi/Ft) pgas =SG. pair PV= (m/Mw)*RT Pair (m/V)= Pair= Pgas= S.G*
Mw*P RT 28.97*P RT 28.97*P RT Where: P =Pressure , Psi R= 10.73 T=Teperature RO) 460+T)
V1
Operating valves
Water Grad=0.45
V2 V3
Whisky valves
V4 V5
Gas Grad
AFE
PSurf = PVO* Ct
Ct= Ct=
PD
OP
Decrease Set Pressure of Bottom Valve 25-30 psi (Flagging the bottom valve)
PSurf = PBT* Ct
A Psp = Pg (A)+ Pp(B) PVOsur = Psp/ A
Where R=B
A=1-R
Temperature Correction
Decrease Set Pressure of Bottom Valve 25-30 psi (Flagging the bottom valve)
Pvc1
PSurf = Pvc* Ct
Pvc2
A
Pvc3 Pvc4 Pvc4
Casing Operating
Fluid Operating
AFE
PSurf = PVO* Ct
System allow extra gas to go in one side than other. Results in one or both zones producing at less than optimum Use injection pressure-operated in one side and production pressure operated in the other
Design considerations
Prediction of inflow & outflow - Above BPP. - Below BPP Suitable tubing size - Small size gives high friction losses.
- Large gives excessive gas slippage
Design considerations
Temperature
-It is better to use actual survey. If not
Amb WHT Amb WHT
available,
If Not
Unloading depth
BHT
Design considerations
Temperature (Cont.
- Temp. is rate sensitive, if - Design temp > actual upper valve will remain open . - Design temp < upper valve will close.
Valve Spacing
- Closer in high rate wells. - Wider in low rate wells.
Valves
- Bellows Type. (Need temperature correction - Spring Type (may not sufficient in high pressure setting
Design considerations
Gas Volume How You Can Calculate Required GV ?
1. Use Nodel analysis to select optimum GLR.
GLR 400 GLR 1000 GLR 700
Press
GLR 500
Q,BPD
Design considerations
2. Required Gas Vol = Design GLR*BFPD- FGOR*BOPD MSCF
Port size
-You can select your port size based on required gas volume (see the following chart) -it is recommended to increase port size as go deeper
Qactual = Qchart/ corr. factor Correction Factor= 0.0544 GT
Where G : Gas Gravity T : Temperature
Design considerations
Gas Passage
unloading
Unloading
It is displacing killing/completion fluid to depth of operating valve.
Kick off
when well is shut , fluid level rise to level equal to res. Press.
opening gas on the well till the well start to produce called
kick off.
Recommended Practices Prior To Unloading Clean the well of mud prior to running G.L. Valves to avoid damage Reverse circulation should not be used (Injection gas pressure operated valves)
Unloading procedures
Install two pin chart on recording both annulus and tubing side Open gas on well gradually to minimize velocity across 1st valve to avoid valve cut. Pressure incremental by 50 psi every 8-10 min till pressure reach 400 psi. then pressure incremental 100 psi every 8-10 min.
You may increase the gas above the design gas just to unload the well.
300 290 280 270 260 250 240 230 220 210 200 190 180 170 160 150 140 130 120 110 100 90 80 70 60 50 40 30 20 10 0
6000 7000 8000 9000 10000 11000 12000
TVD DEPTH, FT
Temperature F
0
0
100 120 140 160 180 200 220 240 260 280 300 0 0 0 0 0 0 0 0 0 0 0
1000
2000
3000
4000
5000
6000
TVD DEPTH, FT
7000 8000 9000 10000 11000 12000 13000
-60
-30
30
60
90
Temperature F
Production Decline
Incremental Gas Utilization Factor GUF It is ratio of incremental oil divided by incremental injection gas. High GUF reflect efficient lift gas.
Low GUF reflect inefficient lift gas.
Maximum GUF: obtained by drawing tangent line from orign to The optimization curve.
- Applied when reservoir management exist. Case 2 :Not all wells must necessarily be kicked off and produce, but wells with high GUF will be kick off in preference to wells with a lower GUF.
- applied when maximum oil is the main objective
Well with highest max. GUF is the first well to be kicked off
The next additional GUF of this well is then compared with the maximum GUF of remaining wells, If - If the next additional GUF is > the other max GUFs then the gas further allocated to the same well, otherwise -The gas lift allocated to the well with next highest GUF (i.e second well kick off) ----- continue till Continue with comparing the additional GUF of kick off wells with max. GUF of wells not yet kicked off till all gas has been used
Maximum GUF
Seat (Port)
Check Valve V-Packing
VALVE Fig
Latches
Screw to the top of the valve provides the neck for wireline tool engagement
Running Procedures
Pulling Operation
Design considerations
All system should be design carefully according field requirements (current &future)
Facilities to
- Avoid high back pressure - Deliver sufficient , clean gas volume
Press
Match point
Q,BPD
depth
UP=1000
UP=1500
Well perf @ 20 wc
UP=1500 UP=1000
depth
Bopd
IG MMSCF
UP=1500
WC 20 % Base
Press
UP=1000
Bopd
Q,BPD
IG MMSCF
Parameters selection
The upstream (O.P) will be selected based on economic study (additional oil VS additional cost)
Q TOTAL: After calculate the amount of gas required for
every well, Then the total amount of gas can be calculated
Pressure Losses
- Separator to compressor Weymouth equation - Compressor to the well panhandle equation