Professional Documents
Culture Documents
by Dr Wang, ShouQing
Department of Building National University of Singapore
Introduction
Outline:
Undergraduate Module: BU3114/BU3380 Graduate Module: BS5235
Lectures service as guideline only and emphasis will be placed on those require calculation and logic thinking/inference. Please read additional books/journals, do the tutorial questions (1a+b, 2 & 3) and finish the assignment given in the Outline.
Dr Wang, ShouQing, Department of Building, National University of Singapore
Get up 0m 8:00 AM
Get up 0m 8:00 AM
A baseline for control established. Determine Finish from Start or vise versa
Importance of Planning/Mgmt
Lessons learnt from the example:
Working logic affects total project time Some activities are critical while other are not A baseline for control
Construction projects characteristics (unique, long period, outdoor, sequential & parallel activities, many parties/resources involved, lot of info) require well planning To construct safely a quality facility on time and within budget with given resources
Dr Wang, ShouQing, Department of Building, National University of Singapore
Planning How to Do
Organizing the project team Developing the construction plan Setting the cost budget
Planning When to Do It
Sequencing and scheduling activities Allocating people and resources to activities
Dr Wang, ShouQing, Department of Building, National University of Singapore
Philosophy of Management
(similar to launching of a missile)
The planning sets the targets to form the basis for controlling/management. The controlling ensures the project execute as planned or amended.
Dr Wang, ShouQing, Department of Building, National University of Singapore
Project Organization
Purposes of Project Organization: define flow of interactions among people
Who decides what Who tells whom what Who responds Who performs what work
Company Head
Project Manager
Construction
Administration
Accounting
PM has strong authority over his subordinate members. After project is completed, members are either sent to other sites or laid off. Adopted by most small-medium companies (also clients) to keep overhead cost low by deploying almost entire manpower on site and minimizing headquarters.
Dr Wang, ShouQing, Department of Building, National University of Singapore
Structural Department
Geotechnical Department
Project Member
Project Member
Project Coordinator
Project Member
Opposite to the pure project type. Team members work together as expertise-contributors from various functional departments. PM acts merely as a coordinator. Position of departments is stronger than the PM. Common in design firm and some specialist contractors
Dr Wang, ShouQing, Department of Building, National University of Singapore
Matrix Type
Functional Department
Top Management
Functional Department
Project Manager
Functional Department
Project Member
Project Member
...
Project Member
In between pure project & functional department types. Decision-making shared by PM & functional depts. PM has authority over the team members while departmental managers have authority to instruct their staff assigned to the project. Found in large firms esp. design-build contractors.
Dr Wang, ShouQing, Department of Building, National University of Singapore
Site Layout
First tasks to prepare a job layout for:
Permanent facilities to be erected Access roads Offices Warehouses for tools and small materials Storage of bulky materials & heavy equipment Yards for fabricating reinforcing steel & forms Tower cranes
Construction Activities
A construction project is broken down into specific activities (definable objective, scope, beginning and ending points) Work breakdown structure (WBS) is often used Once the activities are identified, the sequence of the activities (logic) should also be determined according to technical and managerial requirements
Dr Wang, ShouQing, Department of Building, National University of Singapore
Task 1.0
Task 2.0
Task 3.0
Subtask 1.1
Subtask 1.2
Subtask 1.3
Subtask 2.1
Subtask 2.2
Subtask 3.1
Subtask 3.2
Fourth-Level WBS
Level 1
Task 1.0 site preparation Task 2.0 masonry Construction of apartment
Level 2
Level 3
Work package 2.4.4 remove forms
Level 4
WBS Codes/Numbers
Similar to the Chapter Table of Contents numbers of a book/ Chapter 1 (level 1) dissertation. Chapter 2 (level 1) Numbering depends Chapter 2.1 (level 2) on level. Chapter 2.2 (level 2) Useful for structuring Chapter 2.2.1 (level 3) project & arranging Chapter 2.2.2 (level 3) Chapter 2.2.3 (level 3) activities. Chapter 2.3 (level 2) Software can autoChapter 3 (level 1) assign WBS Chapter 3.1 (level 2) codes/numbers.
Dr Wang, ShouQing, Department of Building, National University of Singapore
Activity Duration
To determine the length of time to accomplish an activity, the planner needs to:
Take off the quantity of work for each activity Determine the method of construction, crew types/ numbers and plant types/numbers to be used Estimate the productivity of selected crew/plant performing the defined work based on job conditions and experiences etc.
Usually, the more input of resources, the shorter the duration (Effort/Resource-driven Duration).
Dr Wang, ShouQing, Department of Building, National University of Singapore
The duration of some activities such as curing of concrete depends on specifications. Sometimes it is hard to know the exact duration of some activities but its distribution.
Dr Wang, ShouQing, Department of Building, National University of Singapore
Planning Method
Bar chart (Gantt Chart)
Popularised by Henry L Gantt and Frederick W Taylor in early 20 century Shows works versus time (see next slide)
Left part shows activities ID, name, duration, resources, cost, start/finish time, values etc. Right part, using time-related bars, shows each activitys start time, finish time and duration, etc.
Principal advantage: readily understandable Yet an extremely useful tool and may often be seen accompanying a network diagram
Dr Wang, ShouQing, Department of Building, National University of Singapore
Example of Barchart
Total Cost
Min Cost
Direct Cost
Indirect Cost
Optimum TPT
TPT
Velocity Diagram
Line-of-Balance Example
Discontinuity of work allowed: e.g. after Remove form 1, stop 3 days, then Remove form 2. Pros: each activities finish at earliest time with shortest TPT=34d
Wall
Elect form
3days
2 days
1 days
3 days
2 days
Examples of Diagram
Activity-on-Arrow Diagram (see previous slide) Activity-on-Node Diagram
A node can be a circle, rectangle, etc.
Tutorial
Dr Wang, ShouQing, Department of Building, National University of Singapore
Tutorial
Dr Wang, ShouQing, Department of Building, National University of Singapore
A site is divided into three areas. In each areas, four activities A, B, C, D are carried out in sequence, i.e. A->B->C->D, and from area 1->2->3, Draw network diagram.
Assume only one crew/plant for A, B, C and D respectively, e.g. one Excavator for A (excavation), Labor-1 for B (formwork), Labor-2 for C (steel bar), Labor-3 for D (concrete). Activity-on-Node Diagram: Technical Logic
A1
B1
C1
D1
A2
B2
C2
D2
A3 Activity-on-Arrow Diagram:
B3 Technical Logic
C3
D3
A1
B1
C1
D1
B2
C2
D2
B3
C3
D3
Calculation Procedure
Based on correctly drawn Network Diagram Forward Pass Calculation (EST, EFT) Determine TPT Backward Pass Calculation (LFT, LST) Compute TF Compute FF Identify Critical Path (CP) Above concepts will be explained in next example
Dr Wang, ShouQing, Department of Building, National University of Singapore
Definition:
E
3 2 5 2 5 0 0 0 0
2 3 2 3
0 1 2 3
Timescale
0 1
A B C F E
1 2
2 3
3 4
4 5
Earliest Start Time: EST EST1st Activity=Start Time=0 ESTjk= max{EFTij} 4 H 3 5 3 Earliest Finish Time: EFT 2 EFTij= ESTij + Dij 6 8 3 G 0 Total Project Time: TPT Finish TPT=max{EFT 3 3 2 last Activity}=Tcp 6 5 5 2 Latest Finish Time: LFT 8 LFTlast Activity=TPT TPT LFTij=min{LSTjk} I 5 8 0 Latest Start Time: LST 3 5 8 0 5 LSTij=LFTij - Dij Total Float: TF Legend: A-O-A TFij=LSTij-ESTij=LFTij-EFTij Activity i j k Free Float: FF Duration FFij=ESTjk-EFTij EST EFT TF Characteristics of TF & FF LST LFT FF Critical Path TFijFFij TFcritical activity=FFcritical activity =0
Comparison of TF and FF
TF: assume all activities start at EST; excess time (less duration) by which an activity can delay or expand without affecting TPT (but possibly affecting the EST of its succeeding activities) FF: assume all activities start at EST; excess time by which an activity can delay or expand without affecting the EST of its succeeding activities and the TPT For an activity, always TF FF (? When =)
Dr Wang, ShouQing, Department of Building, National University of Singapore
Comparison of TF & FF
B
DA
ESTA
TFA
EFTA
B is As immediate successor
TFA=LSTA-ESTA=LFTA-EFTA FFA=ESTB-EFTA ? TFB= ? FFB= LFTA
FFA A
LSTA
TFA
DA
ESTB LSTB
EFTB
LFTB
DB
Dr Wang, ShouQing, Department of Building, National University of Singapore
Critical Path
Critical Path (CP) is the chain of activities with zero TF; it is the longest duration path from Start Node to End Node in the network TPT=Tcp=(Dactivities on CP) Increase/decrease of the Dactivities on CP affect TPT (?) Critical activities have zero TF and FF Activities on CP must be carefully monitored (?) There may be more than one CPs in a network Non-CP may become CP if reduce Dactivities on CP ? How to calculate Activity-on-Node Diagram?
Dr Wang, ShouQing, Department of Building, National University of Singapore
End
Duration distribution falls within a and b with m representing most likely, not (a+b)/2 Assumptions:
activities duration are independent TPT is with normal distribution
Dr Wang, ShouQing, Department of Building, National University of Singapore
PERT Procedure
Draw network diagram (same as CPM) Calculate expected time for each activity: te=(a+4m+b)/6 (beta distribution theory) Calculate forward & backward & identify CP Calculate for activities on CP the Std Deviation = V =(b-a)/6 where Variance V=[(b-a)/6]2 Calculate expected: TPT=(tcp) Calculate Std Deviation of TPT: SDTPT = cp2 Estimate the probability of project completing by certain time and the level of confidence
Dr Wang, ShouQing, Department of Building, National University of Singapore
te = 3.33 vt =0.444
2 3 6
te = 3.0 vt =0.444
1 3 5 E
te = 5.33 vt =1.778
2 5 10 F
te = 8.33 vt = 1.00
6 8 12
PERT Example
te = 3.0 vt =0.111
2 3 4 G
te = 6.83 vt = 0.25
5 7 8
te = 3.0 vt =0.111
2 3 4
Find critical path (CP) and TPT using te values: path ABCD duration=3.33+3.0+5.33+8.33=20 path AEFD duration =3.33+3.0+6.83+8.33=21.49 (CP) path AGD duration=3.33+3.0+8.33=14.66 (or calculate the diagram using the same method of CPM) Find the Variance Vt and Standard Deviation of TPT: Vt=vt(AEFD)=0.444+0.111+0.25+1.0=1.805; =Vt=1.344
0.6 73 -0.1 46 -1.4 0.7 76 -0.2 42 -1.6 0.8 79 -0.3 38 -1.8 0.9 82 -0.4 34 -2.0 1.0 84 -0.5 31 -2.5
Resource Allocation
Early vs. Late Schedules & Smooth
Resource Histogram
Resource Histogram
Resource Histogram
Resource Histogram
EFTA
BA=EFTB LSTA
A
LSTA
B
ESTB LSTB
A
EFTB
LFTA
B B
LFTB
n! If A & B cant be carried out concurrently, there are two reschedule schemes: If reschedule B after A, the delay AB =? If reschedule A after B, the delay BA =? If more than 2 parallel activities, how many reschedule schemes?
Indirect Cost
Direct Cost
Optimum Duration
Duration for min cost (normal duration)
Duration (day) 12 Indirect cost ($) 900 Normal: Critical path Normal duration Direct cost Indirect cost Total cost
9 700
A D
8 660
F
7 620
B
C E
G
12
? Selection of Schedule:
According to management strategy etc.
Cost
10
Time
12
Completed portion in a barchart is marked accordingly The Current Date (Review Date) is the basis for rescheduling. All unfinished activities will be scheduled forward from this date according to their duration/logic For already finished, actual starts should be furnished to update the project schedule so as to make it consistent
Dr Wang, ShouQing, Department of Building, National University of Singapore
Therefore
Planned project % complete= project budget (actual activity % complete*activity budget) Actual project % complete = project budget
BCWS
Comparison can be made between the planned project % complete and the actual project % complete to evaluate project performance
Dr Wang, ShouQing, Department of Building, National University of Singapore
A B C D E F G H
100 60 20 60 0 0 0 0
C A C T I V I T Y
H Day
0% 0% 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46
Evaluate the Planned vs Actual Project % Complete: Planned project % complete = BCWS / Project budget =19600/46480 = 42% Actual project % complete = BCWP / Project budget =19200/46480 = 41% Schedule Variance in % =41% - 42%= -1% (slightly behind) (based on Schedule Variance, also = -400/46480-1%) Forecast of project cost at completion: $43200 (save 3280) Conclusions: the project is now on schedule & well under budget while the forecasts are also good.
Dr Wang, ShouQing, Department of Building, National University of Singapore
Draw & calculate network, preferably by software Identify CP, TPT, resource histogram, cost etc. Consider (physical, safety, resource, management etc.) constrains & make adjustments/optimisation Implement, monitor, control & adjust the plan
Dr Wang, ShouQing, Department of Building, National University of Singapore
Cost calculating/summarising
Reporting & communication See hardcopy examples by Primavera Project Planner (P3) and MS-Project
MS-Project Software
FS= -1d
FF=3d
Effort-driven or Resource-driven Duration Various Concepts of Time/Schedule: Calculated, Actual, Constrain, Baseline Project Calendar (the calculation based on) Resources Calendar (different resources may have different calendars)
Dr Wang, ShouQing, Department of Building, National University of Singapore
SF=6d
LC is a new way to manage construction production, with implications for commercial relationships & project delivery processes. Concept borrowed from M&P industry; started in construction in 80; still under developing.
Dr Wang, ShouQing, Department of Building, National University of Singapore