You are on page 1of 9

Sonadih2nd clinker line Project

Learning from Project


Construction power requirements
Part-2

-KV Siva ram sarma

Learnings from project

1 1
Sonadih2nd clinker line Project
Total Power requirement

S.No Discipline Total Remark


Power kW

1 Mines 150 For Mines development


activities
2 Civil & structural construction 900 Both for civil & structural

3 Mechanical 325 Sonadih + Mejia combined

4 Electrical 155 Sonadih + Mejia combined

5 Labor hutment 250 Sonadih + Mejia combined

6 Employees & visiting executives 250 Sonadih + Mejia combined

Total connective load 2030

Say 2000

Operating power factor considered 0.8

Construction supply max operating load 2500 kVA

Construction supply Max demand required +20% 3000 kVA

If Grid supply is planned – The Voltage level should be at least – 11000 Volts
But alternate DG is also to be planned to reduce the Grid interruptions.
Learnings from project
(At least 2 sources are required to avoid the power interruptions)
2
Details are attached 2
Sonadih2nd clinker line Project
Details

1. Mines
2. Civil construction
3. Mechanical
4. Electrical
5. Labor hutment
6. Employees & visiting engineers infrastructure

Learnings from project

3 3
Sonadih2nd clinker line Project
1. Mines

• Mines power requirement is basically of illumination


Over burden removal is envisaged to make the raw material availability during plant start
up.

Power requirement is around – 150 kW

Learnings from project

4 4
Sonadih2nd clinker line Project
2. Civil & structural construction

S.No Power requirement of item Qty Total Remark


No power kW

1 Batching plant requires approx – 3 450 As presently Sonadih 2 & Mejia


150 kW –1
2 Civil area lighting –1 kW halogen 100 100 Based on Sonadih & Mejia
Lamps Experience
3 Concrete pumps – each of 30 kW 5 100 Based on Sonadih experience
though we need 5 pumps but
operating will be around 3 only.
4 Bar bending machines each of 7.5 6 50 Sonadih – 4 & Mejia –2
kW

5 Welding machines & misc load like 1 50 Welding machines for


work shop, lab & office etc lot structural are also considered
–25 No
6 Tower crane & man lift 1 100 Based on Sonadih experience
No

6 Inflatable tower lights each of 5 kW 8- 50 Based on Sonadih exp where in


10 we have procured 4 nos

Total power requirement 900 For the integrated plant

Learnings from project

5 5
Sonadih2nd clinker line Project
3. Mechanical

S.No Power requirement of item Qty Total Remark


No power kW

1 Misc Load like work shop, lab, Office 1 75 Considering the lab & office will
Lot be bigger than the existing
Sonadih set up
2 Lighting considering – 1 kW 50 50 The load will be less during the
halogens civil construction period
3 Winch machines each of 15 kW 3 50 For lifting of materials & man
lift etc

3 Welding machines, Grinding 1 150 100 kW is for welding


machines & other equipment Lot machines – 50 No operating
connected will be around 100
(existing Sonadih – 60 & Mejia
30 kW – For grinding & Misc
Total power requirement 325 For the integrated plant

Learnings from project

6 6
Sonadih2nd clinker line Project
4. Electrical

S.No Power requirement of item Qty Total Remark


No power kW

1 Misc Load like work shop, lab, Office 1 50 Considering the lab & office will
Lot be bigger than the existing
Sonadih set up
2 Lighting considering – 1 kW 25 25 The load will be less during the
halogens civil construction period
3 Winch machines each of 15 kW 2 30 For lifting of materials & man
lift etc

3 Welding machines, Grinding 1 50 30 kW is for welding machines


machines & other equipment Lot – 15No operating connected
will be around 25
20 kW – For grinding machines
& Misc
Total power requirement 155 For the integrated plant

Learnings from project

7 7
Sonadih2nd clinker line Project
5.Labor hutment

S.No Power requirement of item Qty Total Remark


No power kW

1 Lighting, Misc & Canteen 1 250 Combined Sonadih & Mejia for
requirement Lot 2000 peak workers
Total power requirement 250

Learnings from project

8 8
Sonadih2nd clinker line Project
6. Employees & Visiting executives

S.No Power requirement of item Qty Total Remark


No power kW

1 Lighting, Misc & Canteen 1 250 For 100 Engineers each of 2.5
requirement Lot kW
Total power requirement 250

Learnings from project

9 9

You might also like