Sonadih2nd clinker line Project
Total Power requirement
Say 2000
If Grid supply is planned – The Voltage level should be at least – 11000 Volts
But alternate DG is also to be planned to reduce the Grid interruptions.
Learnings from project
(At least 2 sources are required to avoid the power interruptions)
2
Details are attached 2
Sonadih2nd clinker line Project
Details
1. Mines
2. Civil construction
3. Mechanical
4. Electrical
5. Labor hutment
6. Employees & visiting engineers infrastructure
3 3
Sonadih2nd clinker line Project
1. Mines
4 4
Sonadih2nd clinker line Project
2. Civil & structural construction
5 5
Sonadih2nd clinker line Project
3. Mechanical
1 Misc Load like work shop, lab, Office 1 75 Considering the lab & office will
Lot be bigger than the existing
Sonadih set up
2 Lighting considering – 1 kW 50 50 The load will be less during the
halogens civil construction period
3 Winch machines each of 15 kW 3 50 For lifting of materials & man
lift etc
6 6
Sonadih2nd clinker line Project
4. Electrical
1 Misc Load like work shop, lab, Office 1 50 Considering the lab & office will
Lot be bigger than the existing
Sonadih set up
2 Lighting considering – 1 kW 25 25 The load will be less during the
halogens civil construction period
3 Winch machines each of 15 kW 2 30 For lifting of materials & man
lift etc
7 7
Sonadih2nd clinker line Project
5.Labor hutment
1 Lighting, Misc & Canteen 1 250 Combined Sonadih & Mejia for
requirement Lot 2000 peak workers
Total power requirement 250
8 8
Sonadih2nd clinker line Project
6. Employees & Visiting executives
1 Lighting, Misc & Canteen 1 250 For 100 Engineers each of 2.5
requirement Lot kW
Total power requirement 250
9 9