Professional Documents
Culture Documents
• 150-175 ohm ,
15A60secc on 4160v
system, 3w
• 0.55 ohm , 500A,for
10sec on 480v, 3
phase, 3w
• Derived neutral with
grounding resistor
Methods of solidly grounding the neutral of three-
phase systems
Earthing for ship
• Distribution systems of ships are usually have
their neutral points earthed to the ship’s hull
through a resistor
• The resistor in neutral line limits earth faults
currents and protects equipment
- Insulated Neutral System
- Earthed Neutral System
- Resistance earth Neutral System
Insulated Neutral to Earth
• This system is totally insulated from the ship’s hull
• This system maintains continuity of power supply to
the equipment even in the event of single phasing
fault.
• This ensure power supply to critical equipment
• The power supply to the equipment can disrupt only
if two single phase faults occur simultaneously in two
lines which is then equivalent to short circuiting
faults
• But such fault occur very rare
Insulated Earth Neutral
Gen
Load
Earth
Insulated Earth 3-Phase
Gen Load
Gen Load
Gen
Load
Earth Fault
Neutral Earth 3-Phase
Gen Load
Fault in
Earth Line
High voltage grounding for ships
• The high voltage (e.g. 6.6 kV) installation covers the
generation, main supply cables, switchgear,
transformers, electric propulsion (if fitted) and a few
large motors e.g. for side-thrusters and air
conditioning compressors.
• For all electrical equipment the key indicator to High
Voltage Equipment voltage level which enhances the
current flow.
• Remember that an electric shock current as low as 15
mA can be fatal
High voltage grounding for ships
• The risk to people working in HV areas is greatly minimized by the
diligent application of sensible general and company safety regulations and
procedures.
• Personnel who are required to routinely test and maintain HV equipment
should be trained in the necessary practical safety procedures and certified
as qualified for this duty.
• Approved safety clothing, footwear, eye protection and hard that should be
used where danger may arise from arcs, hot surfaces and high voltage etc.
• The access to HV switchboards and equipment must be strictly controlled
using a permit-to-work scheme and isolation procedures together with
live-line tests and earthing-down before any work is started.
• The electrical permit requirements and procedures are similar to permits
used to control access in any hot-work situation, e.g. welding, cutting,
burning etc. in a potentially hazardous area. All work to be carried out on
HV Equipment is subject to an Electrical Permit to Work (EPTW)
EPTW
Guidelines for the necessary declarations and procedures are :
- Risk assessment
- Chief Electro technical Officer (CETO) or Chief Engineer
- Agreement on safety precautions and HV circuit has been isolated and
earthed.
- Suspension or completion of the designated work
- Cancellation of the permit with a signature from the authorizing officer.
EPTW
- A Permit-to-Work is usually valid only for 24 hours.
Some marine and offshore companies will also
require an associated electrical isolation Certificate to
declare and record exactly where the circuit isolation
and ear thing has been applied before the EPTW can
be authorized.
• A Sanction to- Test safety certificate may also be
required when an electrical test (e.g. an electrical
insulation test) is to be applied.
HV live-line testing components.
• This is necessary as the circuit earth generally has to be
removed during such testing. Before earthing-down the
particular circuit or equipment declared in the EPTW
• it must be tested and proved dead after disconnection and
isolation. This can only be carried out by using an approved
live- line tester as shown
• The tester itself must be proven before and after such a test.
• This is checked by connecting the tester to a known HV
source (supplied either as a separate battery operated unit or
included as an internal self-test facility).
• Two people should always be together when working on HV
equipment.
Earthing down
• Before work can be allowed to commence on HV equipment it
must be earthed to the hull for operator safety.
• As an example, consider the earthing arrangements at an HV
switchboard.
• Here, the earthing-down method is of two types:
1- Circuit Earthing:
• After disconnection from the live supply, an incoming or
outgoing feeder cable is connected by a manually operated
switch to connect all three conductors to earth.
• This action then releases a permissive-key to allow the circuit
breaker to be withdrawn to the TEST position.
• The circuit breaker cannot be re-inserted until the earth has
been removed and the key restored to its normal position
Earthing down
2- Bus-bar Earthing
• When it is necessary to work on a section of the HV switchboard bus-bars,
they must be isolated from all possible electrical sources.
• This will include generator incomers, section or bus-tie breakers and
transformers (which could back-feed) on that bus-bar section.
• Earthing down is carried out at a bus-section breaker compartment after
satisfying the permissive key exchanges.
• In some installations the application of a bus-bar earth is by a special
earthing circuit breaker which is temporarily inserted into the switchboard
solely for the bus-bar earthing duty.
• For extra confidence and operator safety, additional earthing can be
connected local to the work task with approved portable earthing straps
and an insulated extension tool, e.g. at the terminals of an HV motor
Bus-bar Earthling
• Remember to always connect the common
wire to earth first before connecting the other
wires to the three phase connections.
• When removing the earthling straps, always
remove the earth connection last.