REFRIGERANT COMPLIANCE MANAGEMENT

CUSTOMIZED ENVIRONMENTAL TRAINING

Refrigerant Compliance Management 1 / 63

Copyright

Training 4 Today 2001

Published by EnviroWin Software LLC

INSTRUCTOR
Insert Instructor Name Here

Refrigerant Compliance Management 2 / 63

Copyright

Training 4 Today 2001

Published by EnviroWin Software LLC

OBJECTIVES
Discuss Industrial Process Refrigeration. Discuss the Requirements of the Refrigerant Recycling Rule. Discuss How to Determine Full Charge of A System.

Discuss How to Calculate Leak Rate.


Discuss When to Make Leak Repairs. Discuss the Requirements for Retrofit and Retirement. Discuss the Requirements for Oil Changes. Discuss Disposal Requirements. Discuss Reports and Recordkeeping. Discuss Use of Contractors.
Refrigerant Compliance Management 3 / 63

Copyright

Training 4 Today 2001

Published by EnviroWin Software LLC

GOALS
Understand Industrial Process Refrigeration. Understand the Requirements of the Refrigerant Recycling Rule. Be Familiar With How to Determine Full Charge of A System. Understand How to Calculate Leak Rate. Understand When to Make Leak Repairs. Understand the Requirements for Retrofit and Retirement. Understand the Requirements for Oil Changes. Understand Disposal Requirements. Be Familiar With Required Reports and Recordkeeping.
Refrigerant Compliance Management 4 / 63

Copyright

Training 4 Today 2001

Published by EnviroWin Software LLC

BACKGROUND
Ozone depleting substances (ODS) are found in certain refrigerants manufactured before 1995. The United States and over 150 other countries signed the Montreal Protocol that pledges the phasing out of ODS by the end of 1995. EPA is authorized to assess fines of up to $27,500 per day for any violation of ODS regulations.

Refrigerant Compliance Management 5 / 63

Copyright

Training 4 Today 2001

Published by EnviroWin Software LLC

LEARNERS
Supervisors

Facility Engineers
Maintenance Personnel Department Managers

Building Occupants
Process Specialists Environmental and Safety Committees

Refrigerant Compliance Management 6 / 63

Copyright

Training 4 Today 2001

Published by EnviroWin Software LLC

OVERVIEW
The goal of this course is to provide supervisors with the tools needed to stay in compliance with the Clean Air Act Amendments relevant to industrial process refrigeration systems. It recommends practical, actions that can be carried out by facility management, maintenance personnel and building occupants. The course will help you to integrate good industrial process refrigeration management activities into your existing organization and identify which of your staff have the necessary skills to carry out those activities.
Refrigerant Compliance Management 7 / 63

Copyright

Training 4 Today 2001

Published by EnviroWin Software LLC

WHAT THIS COURSE DOES NOT DO


The course is not intended to provide information on the requirements for other types of refrigeration equipment or how to do everything required or permitted by the Clean Air Amendments, such as how to perform a leak test using an ultrasonic leak detector. These specialties required training beyond the intended scope of this course. Where this expertise is needed, outside assistance should be solicited.

Refrigerant Compliance Management 8 / 63

Copyright

Training 4 Today 2001

Published by EnviroWin Software LLC

CLEAN AIR ACT AMENDMENTS (CAAA)


Title VI, entitled Stratospheric Ozone Protection, is generally directed toward eliminating the threat posed to the earths protective stratospheric (or high-level) ozone layer by certain ozone-depleting substances (ODSs)

Refrigerant Compliance Management 9 / 63

Copyright

Training 4 Today 2001

Published by EnviroWin Software LLC

FEDERAL REGULATIONS
Pertinent Regulations: 40 CFR Part 82, Subpart F

Refrigerant Compliance Management 10 / 63

Copyright

Training 4 Today 2001

Published by EnviroWin Software LLC

REQUIREMENTS
Require service practices that maximize recycling of ozone-depleting compounds (both chlorofluorocarbons [CFCs] and hydrochlorofluorocarbons [HCFCs] and their blends) during the servicing and disposal of airconditioning and refrigeration equipment Set certification requirements for recycling and recovery equipment, technicians, and reclaimers Restrict the sale of refrigerant to certified technicians Require persons servicing or disposing of airconditioning and refrigeration equipment to certify to EPA that they have acquired recycling or recovery equipment and are complying with the requirements of the rule
Refrigerant Compliance Management 11 / 63

Copyright

Training 4 Today 2001

Published by EnviroWin Software LLC

REQUIREMENTS
Require the repair of substantial leaks in airconditioning and refrigeration equipment with a charge of greater than 50 pounds Establish safe disposal requirements to ensure removal of refrigerants from goods that enter the waste stream with the charge intact (e.g., motor vehicle air conditioners, home refrigerators, and room air conditioners)

Refrigerant Compliance Management 12 / 63

Copyright

Training 4 Today 2001

Published by EnviroWin Software LLC

APPLICABILITY
Industrial process refrigeration used in the chemical, pharmaceutical, petrochemical, and manufacturing industries This sector also includes industrial ice machines, appliances used directly in the generation of electricity, and ice rinks The refrigerant recycling rule applies to systems that contain and use a class I or class II substance as a refrigerant: Class I refrigerants are mostly chlorofluorocarbon (CFC) refrigerants or any mixture containing a CFC Class II refrigerants are hydrochloro-fluorocarbon (HCFC) refrigerants or any mixture containing an HCFC
Refrigerant Compliance Management 13 / 63

Copyright

Training 4 Today 2001

Published by EnviroWin Software LLC

APPLICABILITY
Applicability Triggers The leak repair requirements of this regulation are triggered when an owner or operator of an industrial process refrigeration system discovers that refrigerant is leaking at a rate that would exceed 35 percent of the total charge in a 12-month period

Refrigerant Compliance Management 14 / 63

Copyright

Training 4 Today 2001

Published by EnviroWin Software LLC

APPLICABILITY
Trigger Rates For all systems that have a refrigerant charge of more than 50 pounds:

SYSTEM Commercial refrigeration Industrial process refrigeration Comfort cooling All other refrigeration

RATE 35% 35% 15% 15%

Refrigerant Compliance Management 15 / 63

Copyright

Training 4 Today 2001

Published by EnviroWin Software LLC

APPLICABILITY

EXEMPTIONS OR EXCLUSIONS Leak repair provisions of this regulation do NOT affect systems normally containing 50 pounds or less of refrigerant

Refrigerant Compliance Management 16 / 63

Copyright

Training 4 Today 2001

Published by EnviroWin Software LLC

PROHIBITION ON VENTING
Section 608 of the Act prohibits individuals from knowingly venting ozone-depleting compounds used as refrigerants into the atmosphere Only four types of releases are permitted under the prohibition: 1. "De minimis" quantities of refrigerant released in the course of making good faith attempts to recapture and recycle or safely dispose of refrigerant 2. Refrigerants emitted in the course of normal operation of air-conditioning and refrigeration equipment such as from mechanical purging and leaks
Refrigerant Compliance Management 17 / 63

Copyright

Training 4 Today 2001

Published by EnviroWin Software LLC

PROHIBITION ON VENTING

3. Releases of CFCs or HCFCs that are not used as refrigerants 4. Small releases of refrigerant that result from purging hoses or from connecting or disconnecting hoses to charge or service appliances will not be considered violations of the prohibition on venting

Refrigerant Compliance Management 18 / 63

Copyright

Training 4 Today 2001

Published by EnviroWin Software LLC

RECLAMATION REQUIREMENT
EPA has also established that refrigerant recovered and/or recycled can be returned to the same system or other systems owned by the same person without restriction If refrigerant changes ownership, however, that refrigerant must be reclaimed Refrigerant used in MVACs and MVAC-like appliances is subject to the purity requirements of the MVAC regulations at 40 CFR Part 82 Subpart B EPA updates the list of reclaimers as new companies are added.
Refrigerant Compliance Management 19 / 63

Copyright

Training 4 Today 2001

Published by EnviroWin Software LLC

EQUIPMENT CERTIFICATION
EPA has established a certification program for recovery and recycling equipment EPA has approved both the Air-Conditioning and Refrigeration Institute (ARI) and Underwriters Laboratories (UL) to certify recycling and recovery equipment Certified equipment can be identified by a label reading: "This equipment has been certified by ARI/UL to meet EPA's minimum requirements for recycling and/ or recovery equipment intended for use with [appropriate category of appliance--e.g., small appliances, HCFC appliances containing less than 200 pounds of refrigerant, all high-pressure appliances, etc.]"

Refrigerant Compliance Management 20 / 63

Copyright

Training 4 Today 2001

Published by EnviroWin Software LLC

TECHNICIAN CERTIFICATION
EPA has established a technician certification program for persons ("technicians") who perform maintenance, service, repair, or disposal that could be reasonably expected to release refrigerants into the atmosphere The definition of "technician" specifically includes certain activities as follows: attaching and detaching hoses and gauges to and from the appliance to measure pressure within the appliance; adding refrigerant to or removing refrigerant from the appliance any other activity that violates the integrity of the MVAC-like appliances, and small appliances.
Refrigerant Compliance Management 21 / 63

Copyright

Training 4 Today 2001

Published by EnviroWin Software LLC

TECHNICIAN CERTIFICATION
Apprentices are exempt from certification requirements provided the apprentice is closely and continually supervised by a certified technician The Agency has developed four types of certification: 1. For servicing small appliances (Type I). 2. For servicing or disposing of high- or very highpressure appliances, except small appliances and MVACs (Type II). 3. For servicing or disposing of low-pressure appliances (Type III) 4. For servicing all types of equipment (Universal). Technicians are required to pass an EPA-approved test given by an EPA-approved certifying organization
Refrigerant Compliance Management 22 / 63

Copyright

Training 4 Today 2001

Published by EnviroWin Software LLC

REFRIGERANT SALES RESTRICTIONS


Effective November 14, 1994, the sale of refrigerant in any size container is restricted to technicians certified either under the program described previously in Technician Certification or under EPA's motor vehicle air conditioning regulations The sales restriction covers refrigerant contained in bulk containers and pre-charged parts The restriction excludes refrigerant contained in refrigerators or air conditioners with fully assembled refrigerant circuits

Refrigerant Compliance Management 23 / 63

Copyright

Training 4 Today 2001

Published by EnviroWin Software LLC

CERTIFICATION
Certification by Owners of Recycling and Recovery Equipment EPA requires that persons servicing or disposing of air-conditioning and refrigeration equipment certify to the appropriate EPA Regional Office that they have acquired recovery or recycling equipment and that they are complying with the applicable requirements of this rule This certification must be signed by the owner of the equipment or another responsible officer and sent to the appropriate EPA Regional Office

Refrigerant Compliance Management 24 / 63

Copyright

Training 4 Today 2001

Published by EnviroWin Software LLC

RECLAIMER CERTIFICATION
Reclaimers are required to return refrigerant to the purity level specified in ARI Standard 700-1993 Reclaimers must release no more than 1.5 percent of the refrigerant during the reclamation process and must dispose of wastes properly Reclaimers must certify to the Section 608 Recycling Program Manager at EPA headquarters that they are complying with these requirements and that the information given is true and correct EPA encourages reclaimers to participate in a voluntary third-party reclaimer certification program operated by the Air-Conditioning and Refrigeration Institute (ARI) EPA maintains a list of approved reclaimers
Refrigerant Compliance Management 25 / 63

Copyright

Training 4 Today 2001

Published by EnviroWin Software LLC

FULL CHARGE
The full charge is the amount of refrigerant necessary for an industrial process refrigeration system to operate at normal operating characteristics and conditions There are two reasons why you need to know how much refrigerant is in the full charge for a system: 1. The leak repair requirements of this law do not apply to any system whose full charge is 50 pounds or less of refrigerant in any independent refrigerant circuit 2. To calculate the leak rate for a system, you need to know the full charge
Refrigerant Compliance Management 26 / 63

Copyright

Training 4 Today 2001

Published by EnviroWin Software LLC

FULL CHARGE
To determine the full charge, you must use one of the following five methods: 1. Measure the refrigerant 2. Calculate the weight of the refrigerant charge in the system 3. Use the manufacturer's information 4. Establish range 5. Use a combination of 1-4

Refrigerant Compliance Management 27 / 63

Copyright

Training 4 Today 2001

Published by EnviroWin Software LLC

LEAK RATE
Each time you add refrigerant to a system normally containing 50 pounds or more of refrigerant, you should promptly calculate the leak rate. If the leak rate is higher than the trigger rate, you are required to do one of the following: a. Repair leaks; b. Retrofit the system; or c. Retire the system from service.

Refrigerant Compliance Management 28 / 63

Copyright

Training 4 Today 2001

Published by EnviroWin Software LLC

LEAK RATE

Four Steps to Calculating a Leak Rate 1. #lbs refrigerant added #lbs refrigerant in normal full charge

2. #days since refrigerant last added 365 days

Refrigerant Compliance Management 29 / 63

Copyright

Training 4 Today 2001

Published by EnviroWin Software LLC

LEAK RATE
Calculating a Leak Rate continued 3. Take the number you determined in step 1 and divide it by the number you determined in step 2. 4. Multiply the number you determined in step 3 by 100 (to calculate a percentage).

Refrigerant Compliance Management 30 / 63

Copyright

Training 4 Today 2001

Published by EnviroWin Software LLC

LEAK RATE
Timing After refrigerant is added, you should calculate the leak rate as soon as you can If the system is leaking above the trigger rate, the law imposes strict deadlines for repairing the leaks or retrofitting or retiring the system For example, if you wait three days to determine the leak rate, there will be three less days available to solve the problem

Refrigerant Compliance Management 31 / 63

Copyright

Training 4 Today 2001

Published by EnviroWin Software LLC

LEAK RATE

Purged Refrigerant In calculating the leak rate, you may exclude purged refrigerant that is destroyed A destruction efficiency of at least 98 percent is required There are monitoring, recordkeeping, and reporting requirements

Refrigerant Compliance Management 32 / 63

Copyright

Training 4 Today 2001

Published by EnviroWin Software LLC

LEAK RATE
Recordkeeping/Reporting Keep records that show: 1. The date and type of service; 2. How much refrigerant was added; and 3. The date when the refrigerant was added It may be required and is always advisable to keep records of the full charge and leak rate

Refrigerant Compliance Management 33 / 63

Copyright

Training 4 Today 2001

Published by EnviroWin Software LLC

LEAK REPAIR

If a system is leaking above the trigger rate, leak repairs are required within 30 days of discovery Repairs must bring the annual leak rate below the trigger rate Leak repairs are not required if you retrofit or retire the system

Refrigerant Compliance Management 34 / 63

Copyright

Training 4 Today 2001

Published by EnviroWin Software LLC

LEAK REPAIR

Industrial Process Shutdown When an industrial process shutdown is needed to repair leaks from industrial process refrigeration systems, a 120-day repair period (rather than a 30-day period) is allowed.

Refrigerant Compliance Management 35 / 63

Copyright

Training 4 Today 2001

Published by EnviroWin Software LLC

LEAK REPAIR
Unavailable Repair Parts or Other Regulations That Require Additional Time Additional time beyond the 30- or 120-day time periods is allowed to conduct leak repairs if the necessary repair parts are unavailable or if other applicable federal, state, or local regulations make a repair within 30 or 120 days impossible EPA must be notified if repairs cannot be completed within 30 or 120 days of discovery Only the additional time needed to receive delivery of the necessary parts or comply with the pertinent regulations will be permitted

Refrigerant Compliance Management 36 / 63

Copyright

Training 4 Today 2001

Published by EnviroWin Software LLC

LEAK REPAIR
Repair Verification: There is a requirement to verify the success of leak repairs for industrial process refrigeration systems Two tests, called initial and followup verification tests are required for each repair site A successful test verifies that a leak has been repaired

Refrigerant Compliance Management 37 / 63

Copyright

Training 4 Today 2001

Published by EnviroWin Software LLC

LEAK REPAIR
What are these tests for? The primary purpose of the initial verification test is to verify that a leak or leaks have been repaired before refrigerant is added back to the system Even when the system is not evacuated to complete repairs, initial and follow-up verification tests are required The primary purpose of the follow-up verification test is to re-verify that repairs continue to hold after the system is returned to its normal operating Characteristics or conditions

Refrigerant Compliance Management 38 / 63

Copyright

Training 4 Today 2001

Published by EnviroWin Software LLC

LEAK REPAIR
Initial Verification Test An initial verification test must be conducted following any leak repairs A refrigeration system may not be brought back on line (if it has been taken off line), unless a) an initial verification test indicates that repairs have been successfully completed or b) a decision to retrofit or retire is made. The initial verification test must be conducted before the replacement of the full charge of refrigerant In systems that have not been evacuated, the initial verification test must be conducted as soon as practicable after the repair work is completed
Refrigerant Compliance Management 39 / 63

Copyright

Training 4 Today 2001

Published by EnviroWin Software LLC

LEAK REPAIR
Follow-up Verification Test A follow-up verification test must be conducted: Within 30 days after the initial verification test, where normal operating characteristics or conditions have been maintained; or Within 30 days of bringing the system back on line, if taken off line, and where the system is operating at normal operating characteristics or conditions. In certain cases the results of a follow-up verification test may be less reliable if the test is conducted at normal operating characteristics or conditions

Refrigerant Compliance Management 40 / 63

Copyright

Training 4 Today 2001

Published by EnviroWin Software LLC

LEAK REPAIR
Initial and Follow-up Verification Test Methods Initial and follow-up verification tests may use any method that meets sound professional judgment Examples include: A soap bubble test; or Electronic leak detectors; or Ultrasonic leak detectors; or A pressure test; or A vacuum test; or A fluorescent dye and black light test; or An infrared test or near infrared; or Halon refrigerant gas detection methods
Refrigerant Compliance Management 41 / 63

Copyright

Training 4 Today 2001

Published by EnviroWin Software LLC

LEAK REPAIR
Unsuccessful Tests If you have an unsuccessful follow-up verification test, you must notify EPA and develop a retrofit or retirement plan within 30 days of the failed test If it is going to take you more than one year you must also submit the plan If the follow-up verification test indicates that the repairs to the system have not been successfully completed, the owner or operator is required retrofit or retire the system There are some options where the owner or operator is relieved of the obligation to retrofit or retire the system
Refrigerant Compliance Management 42 / 63

Copyright

Training 4 Today 2001

Published by EnviroWin Software LLC

LEAK REPAIR
Activity Technician Required? Evacuating the refrigerant Yes Adding refrigerant Yes Changing the oil Yes Adding oil Yes Replacing a gauge Yes Changing or calibrating a DP cell Yes Changing a pressure-relief valve Yes Drawing a sample of refrigerant or oil Yes

Refrigerant Compliance Management 43 / 63

Copyright

Training 4 Today 2001

Published by EnviroWin Software LLC

LEAK REPAIR
Activity Helping dismantle a system for disposal
Any of the tasks listed so far, performed under the direct supervision of a certified technician Maintenance that would not reasonably release refrigerant Fixing leaks by tightening nuts or bolts, if no specific reason to think the activity may go wrong and increase the rate of release Any work on the system after the refrigerant has been evacuated
Technician Required?

Yes Yes No

No

No

Refrigerant Compliance Management 44 / 63

Copyright

Training 4 Today 2001

Published by EnviroWin Software LLC

RETROFIT AND RETIREMENT


Owners or operators are not required to repair leaks if they develop, implement, and complete a 12-month retrofit or retirement plan Three conditions, however, must be met: 1. The retrofit or retirement plan must be developed within 30 days of detecting the leak and a copy must be kept on site; and 2. The plan must be dated and the original made available for EPA inspection upon request; and 3. Retrofit or retirement activities must be completed within a 12-month period of the plan's date

Refrigerant Compliance Management 45 / 63

Copyright

Training 4 Today 2001

Published by EnviroWin Software LLC

RETROFIT AND RETIREMENT


Time Extensions for Retrofit or Retirement of Industrial Process Refrigeration Systems Additional time beyond the initial 12-month period is allowed for the following three circumstances occur: 1. A delay is caused by the requirements of other applicable federal, state, or local regulations 2. A suitable replacement refrigerant is not available

continued
Refrigerant Compliance Management 46 / 63

Copyright

Training 4 Today 2001

Published by EnviroWin Software LLC

RETROFIT AND RETIREMENT


Time Extensions for Retrofit or Retirement of Industrial Process Refrigeration Systems continued
3. The unit is custom-built and the supplier of the system or a critical component has quoted a delivery time of more than 30 weeks from when the order is placed If the owner or operator of a custom-built industrial process refrigeration system has received an additional 12-month period for retrofit or retirement activities, but still requires more time to complete the retrofit or retirement, then a request for additional time may be submitted to EPA
Refrigerant Compliance Management 47 / 63

Copyright

Training 4 Today 2001

Published by EnviroWin Software LLC

RETROFIT AND RETIREMENT


Relief From Obligation to Retrofit or Retire You may be relieved of this requirement if either of the following efforts is successful: 1. Make second efforts to repair the same leaks that were the subject of the first repair attempt 2. Within 180 days of a failed follow-up verification test associated with the initial repair efforts, establish that the leak rate is below the trigger rate

Refrigerant Compliance Management 48 / 63

Copyright

Training 4 Today 2001

Published by EnviroWin Software LLC

SYSTEM MOTHBALLING
System mothballing is the intentional shutdown of a refrigeration system for an extended period of time, where the refrigerant has been evacuated from the system to at least atmospheric pressure When a refrigeration system is in a mothballed condition, refrigerant leaks that existed when the system was operating have effectively been stopped because the system has been evacuated The time-related requirements resume on the day the system is brought back on line and is no longer considered mothballed Leak repairs following mothballing on industrial process refrigeration systems are still subject to initial and follow-up verification tests
Refrigerant Compliance Management 49 / 63

Copyright

Training 4 Today 2001

Published by EnviroWin Software LLC

SYSTEM MOTHBALLING
Applicability When a system is mothballed, the time suspensions are available for all types of systems, including commercial, industrial process, and any other systems containing more than 50 pounds of refrigerant Time suspensions under system mothballing apply to all time-related requirements for repairing leaks or replacing, retrofitting, or retiring a system, including time extensions that may be allowed in specific circumstances for industrial process refrigeration systems

Refrigerant Compliance Management 50 / 63

Copyright

Training 4 Today 2001

Published by EnviroWin Software LLC

SYSTEM MOTHBALLING
System mothballing requires the refrigerant to be removed from the system to at least atmospheric pressure If the owner or operator intends to make repairs to the system that require opening the system, the refrigerant must be removed to the required evacuation levels for that refrigerant before the system is opened

Refrigerant Compliance Management 51 / 63

Copyright

Training 4 Today 2001

Published by EnviroWin Software LLC

SYSTEM MOTHBALLING
Example of System Mothballing If the system operated for five days after discovery of the exceedance of the leak rate and then was shut down and mothballed for two months, when the system returned to operating, the owner would still have 25 days to either repair the leaks or develop a 12-month retrofit or retirement plan

Refrigerant Compliance Management 52 / 63

Copyright

Training 4 Today 2001

Published by EnviroWin Software LLC

OIL CHANGES
EPAs refrigerant recycling amendments also address procedures to minimize emissions of refrigerant during oil changes The oil in a refrigeration system may contain large amounts of refrigerant EPA requires a reduction in pressure prior to an oil change so that the bulk of the refrigerant is recovered The maximum pressure allowed is 5 psig

Refrigerant Compliance Management 53 / 63

Copyright

Training 4 Today 2001

Published by EnviroWin Software LLC

OIL CHANGES
There are two acceptable procedures to assure recovery of refrigerant: 1. Evacuate the refrigeration system, or isolated portion, to a pressure no higher than 5 psig and then remove the oil; or 2. Drain the oil into a system receiver to be evacuated to a pressure no higher than 5 psig
These procedures minimize the loss of refrigerant from: a) the oil, and b) the interior of the refrigeration system as the oil comes out
Refrigerant Compliance Management 54 / 63

Copyright

Training 4 Today 2001

Published by EnviroWin Software LLC

SAFE DISPOSAL REQUIREMENTS


Equipment that is typically dismantled on-site before disposal has to have the refrigerant recovered in accordance with EPA's requirements for servicing However, equipment that typically enters the waste stream with the charge intact is subject to special safe disposal requirements Under these requirements, the final person in the disposal chain is responsible for ensuring that refrigerant is recovered from equipment before the final disposal of the equipment Technician certification is not required for individuals removing refrigerant from appliances in the waste stream
Refrigerant Compliance Management 55 / 63

Copyright

Training 4 Today 2001

Published by EnviroWin Software LLC

HAZARDOUS WASTE DISPOSAL


If refrigerants are recycled or reclaimed, they are not considered hazardous under federal law In addition, used oils contaminated with CFCs are not hazardous on the condition that: They are not mixed with other waste They are subjected to CFC recycling or reclamation They are not mixed with used oils from other sources Used oils that contain CFCs after the CFC reclamation procedure, however, are subject to specification limits for used oil fuels if these oils are destined for burning

Refrigerant Compliance Management 56 / 63

Copyright

Training 4 Today 2001

Published by EnviroWin Software LLC

RECORDKEEPING AND REPORTING


Leak Repair (Industrial Process Refrigeration) If the repairs have failed the follow-up verification test: a) Documentation of the following information and report it to EPA within 30 days after verification test: the identification of the facility; the leak rate; the method used to determine the leak rate and full charge; the date of discovery that the leak rate was above the trigger rate; the location of leaks to the extent determined to date; b) Notify EPA if you discover that the repairs will take longer than you have previously told EPA

Refrigerant Compliance Management 57 / 63

Copyright

Training 4 Today 2001

Published by EnviroWin Software LLC

RECORDKEEPING AND REPORTING


Full Charge If the full charge of an industrial process refrigeration system is determined by establishing a range or combining the use of an established range, records must be maintained. These records must include: Identification of the owner or operator of the system; Location of the system; Original range for the full charge of the system, its midpoint, and how the range was determined; Any and all revisions of the full charge range and how they were determined; and Dates such revisions occurred
Refrigerant Compliance Management 58 / 63

Copyright

Training 4 Today 2001

Published by EnviroWin Software LLC

RECORDKEEPING AND REPORTING


Purged Refrigerant Records must include ALL of the following: Flow rate; Quantity or concentration of the refrigerant in the vent; Periods of purge flow; Identification of the facility and a contact person; General description of the refrigeration system; Description of the methods used to determine the quantity of refrigerant sent for destruction; Frequency of monitoring and data-recording; and Description of the control device and destruction efficiency
Refrigerant Compliance Management 59 / 63

Copyright

Training 4 Today 2001

Published by EnviroWin Software LLC

RECORDKEEPING AND REPORTING


Retrofit or Retirement (Industrial Process Refrigeration) If you complete successful retrofit or retirement within the normal oneyear period, the amendments do not require any new recordkeeping or reporting Records reportable to EPA must be maintained on site for three years

Refrigerant Compliance Management 60 / 63

Copyright

Training 4 Today 2001

Published by EnviroWin Software LLC

TIPS FOR USING CONTRACTORS


Remember, You Control Your Facility or Area! Review Procedures With Them Before Starting the Job!

Ensure They Are Properly Trained!


Determine Their Environmental Compliance Record! Determine Who Is in Charge of Their People!

Determine How They Will Affect Your Facilitys


Environmental Compliance!

Refrigerant Compliance Management 61 / 63

Copyright

Training 4 Today 2001

Published by EnviroWin Software LLC

ELEMENTS OF A SUCCESSFUL REFRIGERANT COMPLIANCE PROGRAM


1. DETAILED WRITTEN REFRIGERANT COMPLIANCE
INSPECTION GUIDELINES. 2. DETAILED WRITTEN REFRIGERANT COMPLIANCE BEST MANAGEMENT PRACTICES. 3. EXTENSIVE EMPLOYEE TRAINING PROGRAMS 4. PERIODIC REINFORCEMENT OF TRAINING 5. SUFFICIENT DISCIPLINE REGARDING IMPLEMENTATION 6. PERIODIC FOLLOW-UP
Refrigerant Compliance Management 62 / 63

Copyright

Training 4 Today 2001

Published by EnviroWin Software LLC

THE IMPORTANCE OF A CLEAN ENVIRONMENT


I would ask all of us to remember that protecting our environment is about protecting where we live and how we live. Let us join together to protect our health, our economy, and our communities -- so all of us and our children and our grandchildren can enjoy a healthy and a prosperous life.

Carol Browner Former EPA Administrator

Refrigerant Compliance Management 63 / 63

Copyright

Training 4 Today 2001

Published by EnviroWin Software LLC

You might also like