Introduction Scope of ready mix concrete Comparisons between various options Material required for RMC Equipment required for RMC Merits and demerits for RMC
Estimate
Conclusion
Project report
INTRODUCTION
Ready-mix concrete (RMC) is a ready-to-use material, with predetermined mixture of cement, sand, aggregates and water. RMC is a type of concrete manufactured in a factory according to a set recipe or as per specifications of the customer, at a centrally located batching plant . It is delivered to a worksite, often in truck mixers capable of mixing the ingredients of the concrete between routes or just before delivery of the batch. This results in a precise mixture, allowing specialty concrete mixtures to be developed and implemented on construction sites.
HISTORY
Ready mix concrete was first patented in Germany in 1903, its commercial delivery was not possible due to lack of transportation needs. The first commercial delivery was made in Baltimore USA in 1913.The first revolving drum type transit In 1931, a RMC plant was set up .mixer was developed in 1926 for the construction of Heathrow airport, London. In the mid 90s there were about 1100 RMC plants in UK consuming about 45% of cement produced in that country. In Europe in 1997 there were 5850 companies producing a total of 305 million In USA by 1990, around 72% (more than 2/3rdof .cusecs of RMC cement produced was being used by various RMC plants. In Japan first RMC plant was set up in 1949. By 1992 Japan was the then largest producer of RMC, producing 18196 million tons of concrete. In many other countries of the world including some of the developing countries like Taiwan, Malaysia etc., RMC .industry is well developed.
MERITS OF R. M. C.
Better quality concrete is produced. Elimination of storage space for basic materials at site. Elimination of Procurement / Hiring of plant and machinery. Wastage of basic materials is avoided. Labor associated with production of concrete is eliminated. Time required is greatly reduced Noise and dust pollution at site is reduced. Organization at site is more streamlined. Durable& Affordable No storage space required either for raw materials or for the mix Lower labor and supervisory cost No wastage at site/Environment friendly Availability of concrete of any grade
DEMERITS OF R. M. C.
Need huge initial investment. Not affordable for small projects (small quantity of concrete) Needs effective transportation system from R.M.C to site. Traffic jam or failure of vehicle creates problem if proper dose of retarder is not given. Labors should be ready on site to cast the concrete in position to vibrate it and compact it.
CONCLUSION
Ready Mix Concrete plant is a modern technique of production of concrete in large quantities away from the actual site of placing. It is very useful in cities where demand of concrete is very high and construction sites are in congested areas where mixing on site is not possible. It is suitable for projects like Dam, Roads, Bridges, commercial complex, Malls and all types of mass construction where time limit plays a vital role and where demand is huge.
THE PROJECT
Only concrete has been selected Concrete=36,000 m
Time one year
Alternatives
Two alternatives
To bargain RMC from market. To invest and purchase own plant and machinery.
COARSE AGGREGATES
PICC Code
Description
030501 Coarse Aggregates 030501.01.20 12mm ( 1/2" ) & down in size (Margallah) 030501.01.21 19mm ( 3/4" ) & down in size (Margallah)
FINE AGGREGATES
PICC Code
030510 030510.01
Description
Fine Aggregates Sand
030510.01.01 Coarse Sand (Local) 030510.01.02 Fine Sand (Local) 030510.01.10 Coarse Sand (Lawrencepur)
M M M
CEMENT
PICC Code
030520 Cement
Description
030520.01
Bag
402.50
030520.02
Bag
700.00
030520.03
Bag
414.50
ADMIXTURES
PICC Code
030535 030535.10
Description
Concrete Admixtures Retarders Admixtures
Unit
Avg Rates(Rs.)
Ltr
42.50
Ltr.
Ltr.
39.00
45.00
Ltr
90.00
030535.70.10 Concure 90
Ltr
57.50
LABOUR
PICC Code
500510.04
Description
Construction Foreman
Unit
Avg Rates(Rs.)
500510.04.05
General Foreman
Hour
128.00
500510.04.15
Hour
82.00
Unskilled Labour
PICC Code
500530
Description
Un Skilled Labour
Unit
Avg Rates(Rs.)
500530.01
500530.02 500530.10 500530.20
Labour
Water Man Electrician Helper Helper
Hour
Hour Hour Hour
50.00
50.00 48.00 48.00
Description
Plants (Rental)
Unit
Avg Rates(Rs.)
510501.10
510501.10.10
510501.10.30
Hour
2050.00
CONSTRUCTION EQUIPMENT
Description
Construction Equipment (Rental) Front End Loader
Unit
Avg Rates(Rs.)
Front End Loader 1.5 M Front End Loader 2.5 M Front End Loader 3.00 M
POWER GENERATORS
PICC Code 510502.09 510502.09.01 510502.09.02 Description Power Generators 150 KVA 250 KVA Hour Hour 2276.96 3490.44 Unit Avg Rates(Rs.)
510502.10
Lift Machine
Hour
325.00
TRANSIT MIXERS
PICC Code
510502.12 510502.12.01
Description
Transit Mixers Capacity 6 M
Unit
Avg Rates(Rs.)
Hour
1695.41
510502.12.02
Capacity 4 m
Hour
1550.02
510502.12.03
Daff (4 m)
Hour
1550.02
510502.13
510502.13.06
Hour
485.39
510502.13.10
Diesel Delivery Truck with 100 Hour mm (4") Diameter Pump, 10,000 Liters (Capacity)
713.67
CONCRETE PUMP
PICC Code
510502.25
Description
Concrete Pump
Unit
Avg Rates(Rs.)
510502.25.05
Mobile 80 M / Hour
Hour
1595.00
510502.25.10
Static 45 M / Hour
Hour
1200.00
ON GROUND UP TO 6 M HEIGHT
PICC Code Item Description
Un Material Labour Machinery Overhead Composite & Profit it (Rs) (Rs) (Rs) (Rs) (Rs)
M 2260.46 515.19
M 2476.47 515.19 M 2660.43 515.19
194.59
194.59 194.59
594.05
637.25 674.04
3564.28
3823.49 4044.25
033005.04.16
M 2927.28 515.19
194.59
727.41
4364.46
PICC Code
Item Description
Overhead Composite Material Labour Machinery & Profit Unit (Rs) (Rs) (Rs) (Rs) (Rs)
033005.04 Nominal Mix Ratio. 1 : .20 3:6 033005.04 Nominal Mix Ratio. 1 : .24 2:6 033005.04 Nominal Mix Ratio. 1 : .28 2:4 033005.04 Nominal Mix Ratio. 1 : .32 3:3 033005.04 Nominal Mix Ratio. 1 : .36 2:3 033005.04 Nominal Mix Ratio. 1 : .40 1.5 : 3 033005.04 Nominal Mix Ratio. 1 : .44 1.5 : 1.5 033005.04 Nominal Mix Ratio. 1 : .48 1:2
M 3360.60 515.19
194.59
814.08
4884.45
M 3572.53 515.19
M 4144.11 515.19
194.59
194.59
856.46
970.78
5138.77
5824.66
M 4115.46 515.19
M 4578.87 515.19 M 4865.94 515.19 M 6110.14 515.19 M 6134.25 515.19
194.59
965.05
5790.28
6346.37 6690.86 8183.89 8212.82
Economic theme
We assume there is no inflation for the whole year Life of project one year Use full life of plant and machines 5 year Gds apply MACRS
Deprecation
Book Value after 1 year By using MACRS depreciation (20% for 1st year) B.V after 1 year for Batching Plant = 4200000(4200000*.20) = 3360000 PRs B.V after 1 year for Two Transit mixers =8000000(8000000*.20) = 6400000 PRs B.V after 1 year for Power generator = (1,073,880(1073880*.20) = 859104 PRs B.V after 1 year for Front end loader= (1,200,000(1,200,000*.20) = 960000 PRs