Professional Documents
Culture Documents
By , P P AMBEDKAR
Construction of segmental bridge involves use of different machineries and requires huge amount of skilled manpower. Hence the intention of dissertation is to study the Methods & techniques used in Construction of Segmental Bridge by Under Slung Method which consist of following activities. 1. Construction of Sub-structure 2. Construction of super-structure
Pier
Construction of substructure
Cast-in-situ Pile
Detailed breakdown of activities is mentioned below
1. 2. 3. 4. 5. 6. Setting Out Removal of Overburden Driving Permanent Liner Boring / Chiseling Reinforcement Cage Lowering Concreting
1. Setting Out
Tripod
Driving monkey
Driving cap
Liner
4. Boring/ Chiseling
CHISEL
BAILER
Excavated mud
Bailer
TIME CYCLE
Sr.No. 1 2 3 4 5 6 7 8 9 Activity Road breaking/removal of top overburden/ Identification of utility services. Positioning tripod / winch Survey & setting out Permanent liner driving/ boring Chiseling(6m @ 0.1m/hour) Cage lowering Tremie Pipe lowering/flushing Concreting Removal of tripod/winch Total time for pilling There fore total time for one pile @ 20hours per day working Duration 2 days 2 hours 2 hours 20 hours 60 hours 2 hours 2 hours 3 hours 2 hours 93 hours 4.5 days
2. Exaction up to pile cap bottom level i. Excavation in soft soil ii. Chiseling in hard strata 3. Simultaneously chipping of pile 4. Preparation of bed with PCC 5. Cutting and bending and preparation of reinforcement cage 6. Shuttering for pile cap 7. Concreting
1. Clear area for excavation and marking 2. Exaction up to pile cap bottom level i. Excavation in soft soil ii. Chiseling in hard strata 3. Chipping of pile
Tying of reinforcement
6. Shuttering
7. Concreting of pile cap
Haizen cloth for curing
Shuttering
JCB Excavator Dumper Breaker (Jack hammer) Bar bending and cutting machine Concrete batching plant Transit Mixer Needle vibrators (60 mm)
TIME CYCLE
Sr.No. 1 2 3 4 5 6 7 8 9 10 Activity Waiting period for curing of pile Clearing area, survey and marking for excavation Excavation in soft soil Chiseling in hard rock Cutting and removing liner Chipping piles up to pile cap bottom level PCB) Preparation of bed with PCC as leveling course Reinforcement cutting, bending and fabricating cage Placing and fixing shuttering Concreting
Total time =
Duration 7 Days 2 Hours 12 Hours 2 Days 4 Hours 4 Days 8 Hours 1 Day 3 Hours 1 Hour
8.5 days
Construction of Pier
Job breakdown
1. Cutting, and bending of reinforcement 2. Preparation of reinforcement cage 3. Casting Pier starter 4. Erection of staging and simultaneously fixing shutters 5. Concreting of pier 6. De-shuttering and dismantling staging 7. Curing
1. Cutting, and bending of reinforcement & preparation of reinforcement cage 2.Casting Pier starter 3. Erection of staging and simultaneously fixing shutters
Pier shutter
Staging for supporting pier shutter & providing working platform at top for concreting
TIME CYCLE
Sr. no. 1 2 3 4 5 6 7 8 Activity Cutting and Bending Reinforcement Tying and Cage Preparation Casting Starter and Curing Staging and Simultaneously Shuttering Concreting Waiting till achieving strength for deshuttering Deshuttering Curing Duration 2 Days 1 Day 2 Hrs. 1 Day 3 Hrs. 1 Day 12 Hrs. 28 Days
3 days
CONSTRUCTION OF APPROCHES
Construction of approach involve two major activity that are as follows: i) Construction of Abutment wall. ii) Construction of Wing wall (Retaining wall)
Types of abutment:
Masonry abutments: RCC abutments:
R.C.C Abutments
In this case abutment wall is directly rest over raft /pile foundation. Whole abutment wall made of rich mix concrete. Abutment wall construction involves following activity:
1. Cutting, and bending of reinforcement 2. Preparation of reinforcement cage 3. Casting abutment starter 4. Erection of staging and simultaneously fixing shutters 5. Concreting of abutment. 6. De-shuttering and dismantling staging 7. Curing
RCC Abutment
Shuttering
Staging arrangement
Wing wall
The wings walls are of masonry or RCC masonry, now days wings wall are constructed with new technique that is Geosynthetic Soil Retaining wall in which precast RCC panel is used. The advantage of this construction system is given below.
1. It requires very limited construction space compared to the conventional wall systems. 2. The completed structure occupies less space compared to the conventional wall systems. 3. By using a facing of high rigidity, the stability of the wall system is increased while the deformation is minimized. 4. The geosynthetic layers are closely spaced so that a wide range of backfill can be used without affecting performance.
Construction of Superstructure
Construction of Superstructure of segmental bridge involves two major activities that are as follows: 1) Segment Casting 2) Segment Erection
Different method of segment casting: 1)Long line casting 2)Short line casting
1) Pre-cast Bed Survey and Setting out of moulds as per the co-ordinates.
EOT CRANE
REINFORCEMENT CAGE
Stopend
False work
Turn buckels
Inner formwork
TIME CYCLE
Sr. No. Activity Description Time Required in Hrs. 6 1 1/2 1 8 3 24 2 46 1 Total time= 92 Hrs
1 2 3 4 5 6 7 8 9 10
Base mold cleaning, rectification of rubber liner and applying POP Survey and marking Lowering reinforcement cage Lowering and aligning stopend with jacks and knuckle bolts Placing and fixing inner-formwork Concerting and finishing Curing till deshuttering stopend Deshuttring stopend Curing till deshuttering inner-formwork Lifting and stacking segment
Segment Erection
Probably the most significant classification of segmental bridges is by method of construction. Although construction methods may be varied as ingenuity of the designers and the contractor they fall into two basic categories: 1) Cast-in-Place segmental construction. (Balance Cantilever method) 2) Precast segmental construction.
Bracing
Concrete block
Lifter
Mac-alloy bar
8. Bearing Installation
8. Permanent Prestressing
TIME CYCLE
Sr. No. 1 2 3 4 5 6 7 Activity Staging Arrangement Placing of segments Dry Matching Glue and temporary stressing Install Bearing/ grouting and waiting till attain strength Permanent pre stressing Dismantle staging Duration 1 Day 1.5 Days 0.5 Days 1.0 Day 2.0 Days 0.5 Days 2 Days Average Progress: 6 Days per span
Case Study
NAME OF PROJECT: PUNE FLYOVER AT UNIVERSITY CIRCLE & AGRICULTURE COLLAGE . SITE ADDRESS: GANESHKHIND ROAD, UNIVERSITY CIRCLE, PUNE 411 007 NAME OF CONTRACTOR: AFCONS INFRASTRUCTURE LIMITED NAME EMPLOYER: MAHARASTRA STATE ROAD DEVELOPMENT CORPORATION NAME CONSULTANT: DAR CONSULTANTS (U.K) LTD. in association with DAR CONSULTANTS (I) PVT. LTD
GENERAL FEATURES OF UNIVERSITY CIRCLE FLYOVER 1) Length 2) Carriageway 3) Foundation 4) Substructure = = = = 700 M between abutments Single three lane carriageway Bored cast-in situ piles resting on rock RCC Piers Segmental, Deck width 12 M
5) Superstructure =
GENERAL FEATURES OF AGRICULTURE COLLEGE FLYOVER 1) Length 2) Carriageway 3) Foundation 4) Substructure = = = = 210 M between abutments Dual two lane carriageway Bored cast-in situ piles resting on rock RCC Piers Segmental, Deck width 16.4 M
5) Superstructure =
Reinforcement Yard : For fabrication of reinforcement of all structural elements like pile, pile cap, pier, precast segment, etc. Casting, Curing & : For casting, curing & stacking of Parapet, Retaining Stacking Bay wall & Kerbs. Fabrication workshop: For fabrication of structural steel for shuttering, supportive elements & temporary works. Mechanical workshop : For fabrication of tie rod
CLASSIFICATION OF SEGMENTS
No Type End Diaphragm (ED) 1 Segment width 1.45 Location & Function ED rest on Abutment. It also has a downstand that enables it to sit on bearings. It has a wall ... It houses coupler cones for pre- stressing cables which are locked here. It is located adjacent to ED segment. ID segment rest on all the piers except expansion piers. 2.725 2.917 There are 3 nos. SS in the middle of every span. CSS segment last segment of intermediate span which has stressing CSC Segment is starting segment of next span
Adjacent to End Diaphragm (EDA) Internal Diaphragm (ID) Standard Segment(SS) Coupling segment stressing end (CSS) Coupling segment coupling end (CSC)
2.095 2
4 5 6
2.917
SEGMENT ERECTION
There are 3 types of spans to be erected i.e.:
Type A-Beginning span of each bridge unit, Type B-Internal spans, Type C- End of each unit. Type A has 13 segments to be erected with an End diaphragm at the span. And a CSS segment at the end of the span. Type B Span start with CSC segment & end with CSS segment. Type C Span start with CSC segment & end with ED segment. the start of
PLAN SHOWING DIFFERENT TYPES OF SEGMENT WITH THERE LOCATION IN SPAN A TYPE.
Capacity of horizontal hydraulic jacks = 50T Capacity of screw jacks = 100T Capacity of one HT strands = 25T Stress induced in each strands = 25.26 Kg/cm2 Total stress induced in nineteen strands = 480 Kg/cm2 Total elongation of HT cables = 265mm Diameter of one stand = 15.7mm Diameter of one duct = 110mm Gluing material used = Sikadur (Component A & B) Quantity of gluing material required per joint = 70 kg Wastage of gluing material per joint = 7 kg Load carrying capacity of Bearing plate = 800T Grouting pressure = 5 Kg/cm2 Properties of gluing material given below
Gluing details Setting time Strength Mfg. by Segment Gluing Bearing Gluing 45 Min. 100 Mpa 24hrs. 1hr. in 45 Mpa 24hrs. in
Technical details
CONCLUSION
After studying detail procedure segmental construction that segmental bridges posses following advantages Rapid erection of superstructure. High quality & high strength of concrete can be achieved. Whenever we need to allow traffic underneath even during construction. The structural geometry may be adopted to any horizontal or vertical curvature or any roadway super-elevation. Concrete shrinkage & creep substantially reduced. Segmental construction relatively insensitive to weather condition. Enhanced durability of bridge.
The possible solution to the problems discussed in the case study can be enlisted as follows:
Perfect matching of segment at site can be achieved by considering vertical & horizontal alignment of bridge profile at the time of segment casting. Whenever the segments are not matched properly considerable time is lost in chipping out the segment faces. Hence the segment casting should be done accurately in accordance with drawings.
Thank You